How are "Early Wasting of Unclassified" Supplemental Agreements entered?
In HiCAMS, the user is required to include either a line item or contract time statement on all supplemental agreements. This type of supplemental agreement does not result in a change in the quantity or price for any line items.
To enter this type of Supplemental Agreement, go to Functions -> Review Contract Adjustments -> Review Supplemental Agreements
Follow the instructions in the Supplemental Agreements User Guide with these exceptions:
On the General Tab:
On the Contract Times Tab:
- Type of Work Affected is Affected work.
- Extension is 0 days. The zero cannot be entered directly - first type in another number and delete it. Then enter a 0.
- Select Override Comment. Highlight the existing comment and Delete it. Enter an appropriate contract time statement such as " No extension of the completion date(s) will be allowed as a result of the changes provided herein". Questions regarding appropriate contract time statements should be directed the Construction Unit.
Click on the Activate button and follow the regular Approval process.
NOTE: This Supplemental Agreement will require approval from the State Construction Engineer or delegate because the Override Comment box has been checked.
For additional information about this topic, please contact the Construction Unit at 919-733-2210.
---