How do I print a reference copy of the CBOM for a project?

After the Contract Bill of Materials has been reviewed for accuracy and completeness, it is helpful to have a hard copy for the Project Inspectors to use to identify what materials define each line item, how those materials are received, and what certifications might be required.

There are several ways to get this information from HiCAMS.

Option 1

Go to Inquiries -> Standard Reports. The Select a Report window opens.

Option 2

Go to Functions -> Contract Maintenance -> Review Contract BOM.

Note: All materials used on a project should be received in HiCAMS unless they have a How Received code of "Not Received". Materials in this category should still have invoices and documentation collected on the project, and kept with the project record files with a note stating "Not received in HiCAMS".

---