How should a Material Received Report for Reinforced Concrete Pipe be entered?
This FAQ last updated May 1, 2007
Reinforced Concrete Pipe belongs to the Minimum Sampling Guide Material Type of Pipe Culverts, Concrete.
- This Material Type is received on a Material Received Report (MRR).
- It has a Project Certification Criticality of Critical.
- The Pipe must be Pretested and Alternate IDs must be entered.
- For Contracts let before 2/20/2007 , the Alternate IDs do not need to match an Alternate ID entered on a Field Inspection Report for the Accepted Quantity to update.
- For Contracts let on or after 2/20/2007 , the Alternate IDs must match an Alternate ID entered on a Field Inspection Report for the Accepted Quantity to update.
- The Pipe should be stamped "NC DOT Approved".
Where is the Alternate ID found on Concrete Pipe?
Since January, 2007, Concrete Pipe manufacturers have been required to paint or sticker each piece of pipe with the plant's ID number, size of pipe, and year made. For example, 36" pipe made in January, 2007 at plant CP21 would be marked CP21-36-07
- This information must be on the inside of the pipe, within 12 inches from the end of the pipe. It must also be listed on the Bill of Lading.
- Manufacturers will continue to etch into the pipe the manufacturing date and class of pipe during production.
- NCDOT inspectors will continue to stamp the pipe with NC and the class of pipe (for example, 3B).
- If the Alternate IDs are missing from either the pipe or the Bill of Lading, or do not match the designated format, please contact Sam Frederick at 919-733-7091.
Here's how to enter a Material Received Report for Reinforced Concrete Pipe in HiCAMS:
- Go to the Review Materials Receipts window. (Functions > Contract Tracking > Review Material Receipts) On the Review Material Receipts window, enter/select your contract number, and select the Line Item for which the pipe is being used.
- Create a New MRR by doing an Insert.
- Enter the MRR Nbr, Date, Line Item Number, Material, Received Quantity, Received By, and Plant ID in the new row. If you do not know the plant ID, click on the Approved Producer/Supplier icon on the General tab in the lower portion of the window, and select your producer from the list.
- Click in the Alternate ID tab, and then click the Insert button. A new row will appear in the "Alternate ID" portion of the window. The Alternate ID field will pre-populate with the plant id you entered and a hyphen, for instance, CP21-.
- Enter an Alternate ID type of Lot.
- Complete the Alternate ID field with the diameter of the pipe, a hyphen, and then the two digit year of manufacture for the pipe being entered on the MRR. The completed Alternate ID will look like this: CP21-36-07.
NOTE: All alternate ids are in English units. The English units are to be used on English and Metric projects.
- Repeat the insert steps to link additional Lot numbers to this MRR.
- Save the Record.
By entering the lot numbers with the MRR, the Accepted Quantity will update in the Project Certification records.
For additional information about this topic, please contact Randy Pace, Sam Frederick, or Francine Ward at 919-733-7091.
---