Each Friday the Highway Maintenance
Engineer should turn in all completed survey sheets to
the District Office. This will allow data to be entered as the
survey is being conducted rather than all at once at the end.
Only distress information will be entered by field personnel.
Changes, deletions, and additions will be handled in Raleigh.
When a county is complete the
Highway Maintenance Engineer should turn in all remaining data
sheets, including green forms, to the District Office. Once
all data has been entered for a county, the survey book should
be reassembled and sent to the Division Maintenance Engineer
along with all green forms. The Division Maintenance Engineer
will be responsible for sending this to Jerry Blackwelder in
the Pavement Management Unit in Raleigh. Remember to make
a copy of all data before sending it in.
The Highway Maintenance Engineers
should also turn in a weekly Progress Report (provided by Pavement
Management Unit) to the Division Maintenance Engineer each Friday.
This report should show the number of rating hours and the number
of miles completed for that week. The Division Maintenance Engineer
should review and then send one compiled report to the Pavement
Management Unit, including a division wide progress total.
All surveys should be completed
and data entered by March 1.
If there are any problems or questions,
please call one of the trainers.
Follow up visits will be made by
the trainers while the survey is being conducted. This will assist
the raters by clearing up questions and problems that may arise..