spiral curve ƒ9
A transition curve of constantly
changing radius placed between a high-speed tangent
and a central curve; it permits a gradual speed
adjustments.ƒ8
Typically, a minimum of 200' of spiral is required
on interstate design. Also see CS,
run off, run out, SC,
and superelevation.
subgrade excavation - ƒ10
Excavation volumes that are backfilled with an earthwork
material.
subsoil excavation - ƒ10
Excavation
required to remove unsuitable material either 1)
down to the bottom of the proposed template or 2)
down to the bottom of the unsuitable material layer
in cases where excavation limits are defined.
"suicide" lane
ƒ1
DOT jargon Term refering a five (5) lane
undivided stretch of roadway with the middle 14'
to 16' wide turning lane. There is no insinuation
of negativity on the term "suicide". This
terminology is not officially used in any standard
NCDOT Roadway plans.