Structure Design Unit's Submittal Forms for Proposed Heavy Equipment on Bridge
Structure Design Unit's Submittal Forms for Proposed Heavy Equipment on Bridge
When the Contractor is proposing to place heavy equipment on a new bridge deck, the proposed plan shall be submitted to the Engineer, in accordance with the Standard Specifications, Section 420-20.
For background, also see the Chief Engineer-Operations memo dated September 24, 2007.
The Contractor is not required to use these submittal data forms for any submittal. The submittal data form is only an aid in making a complete submittal.