spacer spacer   spacer   spacer   spacer  
Title Header spacer
 
HOME
spacer
 
CONTACT
spacer
spacer  
SEARCH!
spacer
spacer
spacer
  NCDOT icon  NC DOT
  NCDOH icon  NC DOH
  NCgov.com icon  NC GOV
spacer
spacer spacer spacer spacer spacer spacer spacer spacer spacer
 
 
spacer
 
Unit Support    |    Staff   |    Project Special Provisons    |    Project Services    |   
spacer spacer
spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer spacer spacer
spacer
  Spring Field Review Site 2
spacer
spacer spacer  
Spring Field Review Site 2

Description: U-2524AA/AB - GUIFORD COUNTY

Location: Greensboro Outer Loop – Kings Mill Road overpass.

Item(s) of Interest: This overpass is located near a subdivision. The Division Office is concerned about driving piles adjacent to the nearby slab-on-grade houses. Evaluated a variety of foundation types for the end bents to avoid the potential liability of vibration-induced damage. The site has a high rock line, and therefore auger cast piles were initially considered, but were considered too expensive. Next auger/driven piles (where the piles would be driven after auguring a short distance), but it was deemed still too risky.
Noisewall on bridge.

Observations and Points of Discussion:

  • Single span bridge at a site with unusual situation due to neighborhood involvement.
  • Rockline 10 – 15 ft. below the roadway.
  • Original design included 9 ft. tall piles supporting the end bent cap.
  • Roadway approach fill has been in place for several months.
  • Division requested an alternate design. Auger cast piles were considered.
    • The Department does not have much experience with them, and hence there was too much risk associated with their use at this site.
  • The revised design includes 8ft of reinforced select material supporting the end bent on a spread footing.
  • The Geotechnical Engineering Unit (GEU) will monitor any vibration and movement in the end bent for about a year.
    • Stress gauges buried in the embankment will record data at each stage of construction. GEU anticipates stresses will dissipate over time.
      Vibration from grading operation may be comparable to pile driving.
      Monitoring ground stresses and movement in the embankment will assist the Department in determining if the embankment on future projects could be built once. Currently, embankments are built up and the soil is allowed to consolidate during the waiting period. Then a portion of the embankment is excavated for construction of the end bent and placement of the reinforced approach fill.
  • Noise walls on bridge will be included at this site.
  • Silt fences failed near roadway.
  • Would a 3-sided culvert on footings be a good option at this site?
      Lighting in culvert would be a maintenance concern, and also possible graffiti problems.
      Buried structures, especially prefabricated structures, have no well established method for rating.

picture 1 picture 2 picture 3 picture 4 picture 5 picture 6
 
picture 7 picture 8 picture 9 picture 10 picture 11 picture 12
 
picture 13 picture 14 picture 15 picture 16 picture 17 picture 18
 
picture 19 picture 20 picture 21 picture 22 picture 23 picture 24
 
picture 25 picture 26 picture 27 picture 28 picture 29 picture 30



spacer spacer
spacer
 
North Carolina DOT Logo   The North Carolina
Department of Transportation