Responsibilites
Pre-Meeting
During Meeting
Post Meeting
General
Post Meeting
Concurrence
- The NCDOT Project Team Member will pursue signing of the concurrence from Project Team members who did not attend the concurrence meeting but indicated intent to concur.
- Project Team Members who do not attend concurrence meetings, but indicated intent to concur, will provide written concurrence to the NCDOT Project Team Member.
Non-concurrence
TBD by ILT
General
- NCDOT is responsible for providing a summary of public input comments as soon as possible to team members.
- Once comments at CP 4B are addressed, the Hydraulics Unit can move forward and design towards CP 4C.
- NCDOT and USFWS, NMFS and SHPO are responsible for keeping the USACE informed of Section 7 and Section 106 issues (furnish copy of Section 7 and Section 106 correspondence to USACE, provide USACE opportunity to attend meetings to discuss Section 7 issues, etc.).
|
 |
 |