Memorandum of Understanding
Section 404 of the Clean Water Act
And
National Environmental Policy Act
Integration Process for Surface Transportation Projects in North Carolina
Applicability
Background
Concept of Concurrence
Project Team
Concurrence Points and Project Phases
Implementation Procedures
Conflict or Dispute Resolution
Modification
Signatures
Primary Signatories
Partnering Signatories
Applicability:
- These procedures will generally apply to all new location projects and all projects that require an individual permit under Section 404 of the Clean Water Act. FHWA, USACE, NCDENR, and NCDOT will consult early in the project development process and apply screening criteria to identify specific projects that will follow this process.
Note: If a project is being developed under the North Carolina Environmental Policy Act without FHWA involvement, this process will still be applicable but will be implemented without FHWA participation.
- Regulatory/Resource Agency participation in this process does not imply endorsement of all aspects of a transportation plan or project. Nothing in these procedures is intended to diminish, modify, or otherwise affect the statutory or regulatory authorities of the agencies involved. In the event of any conflict between this process and other statutes or regulations, the statutes or regulations control.
Background:
In a May 1, 1992 agreement, the U. S. Department of Transportation, the Office
of the Assistant of the Army (Civil Works), and the U. S. Environmental
Protection Agency (EPA) developed policy that would (a) improve interagency
coordination and (b) would integrate NEPA and Section 404 procedures. On
May 14, 1997, the Wilmington District of the USACE, the North Carolina Division
of FHWA and NCDOT signed an Interagency Agreement that provided
procedures to integrate NEPA and Section 404 for transportation projects in
North Carolina. This integrated approach is part of an effort to streamline the
project development and permitting processes. The objective is to ensure that
the regulatory requirements of Section 404 of the Clean Water Act are
incorporated into the NEPA decision-making process for transportation projects.
The original process is hereby modified to incorporate experience gained with
years of use of the 1997 agreement, guidance from the USACE-NCDOTNCDENR
permit process improvement workshop, and incorporation of the
streamlining provisions of the Transportation Equity Act for the 21st century (TEA-
21). This process will continue to be regularly evaluated for its effectiveness and
modified as appropriate.
Concept of Concurrence:
The process is conducted under the concept of “concurrence” with a project team
organization. Concurrence implies that each team member and the agency they
represent agrees to decisions made at strategic points in the project
development process and in doing so “pledges” to abide by the decision made
unless there is a profound changed condition. The USACE, NCDENR, NCDOT
and FHWA jointly lead the project team. Concurrence points are defining points
in the NEPA project development and Section 404 permitting process.
Concurrence is sequential and must be achieved in proper order. As an
example, it is not possible to have agreement on alternatives selected for
detailed study (Concurrence Point 2) without first achieving agreement on
purpose and need (Concurrence Point 1).
The intent of the streamlined process is to ensure that agency concurrences are
obtained before proceeding to the next step or concurrence point. Concurrence
will be documented by signature of a concurrence form summary statement. If an
agency cannot concur, they agree to provide a written explanation of the basis
for non-concurrence to the Project Team. All agencies agree to attempt to
resolve issues causing non-concurrence and to try to do so on an informal basis
within 15 working days of the subject concurrence meeting.
Having concurred at a particular milestone, a team member will not request to
revisit previous concurrence points unless there is substantive new information
that warrants a reevaluation. Examples of such a reevaluation might include:
- a change in the assumptions on which the project purpose or need was based;
- a change in regulatory authority that extends regulatory jurisdiction to include an area or resource that was not previously regulated;
- discovery of an impact, resource or additional information that was not previously identified or did not previously exist; or
- discovery of engineering limitations.
All team members agree that staffing changes are not sufficient reason to revisit
a previous concurrence point and that newly involved agency staff will abide by
the project decisions made by previous staff and the team. A request to revisit a
previous concurrence point will be provided in writing to team leaders and will
include supporting documentation. Team leaders (FHWA, USACE, NCDENR,
and NCDOT) will respond to the request in writing with a carbon copy, or email
with cc’s, to the entire Project Team.
Project Team:
NCDOT will coordinate with the USACE, FHWA, and NCDENR to identify team
members for each project. NCDOT will provide written verification of participating
team members for each project. It is recognized that many statutes and
regulations must be met in order to achieve concurrence and make good project
decisions. Therefore, the following agencies will normally participate unless they
decline.
U. S. Army Corps of Engineers
Federal Highway Administration
North Carolina Department of Transportation
U. S. Environmental Protection Agency
U. S. Fish and Wildlife Service
North Carolina DENR, Division of Water Quality
North Carolina Wildlife Resources Commission
North Carolina Department of Cultural Resources
The following agencies will be requested to participate when a project is within
their respective geographic area:
North Carolina DENR, Division of Coastal Management (within the twenty coastal counties)
Metropolitan Planning Organizations (MPO’s) (in MPO areas)
National Park Service (in the vicinity of national parklands)
U. S. Coast Guard (Coast Guard permitted bridges)
U. S. Forest Service (in the vicinity of national forest property)
Tennessee Valley Authority (within TVA region)
U. S. Fish and Wildlife Service – Refuge (in the vicinity of federal refuges)
Eastern Band of Cherokee Nation-Tribal Historic Preservation Officer
North Carolina Division of Marine Fisheries and National Oceanic and
Atmospheric Administration (NOAA) (when there is any possibility that resources under their jurisdiction are in the project vicinity. Appendix B provides a list of Coastal Plain counties where the NOAA and NCDMF should be contacted to determine their participation in projects in these counties.)
Rural Planning Organizations (RPO’s) may be invited to participate as advisory
members for projects within their geographical area. Advisory members will not
sign concurrence forms.
Each participating agency will develop protocol to determine which office or
individual of each agency will participate. NCDOT’s representative on the Project
Team will be the Project Development Engineer. To represent NCDOT in all
areas of concern related to the natural and human environment, design and
safety considerations, a representative from the Office of Human Environment,
the Office of Natural Environment, the Design Engineers (Roadway Design,
Hydraulics, Structure, Geotechnical, etc), Construction Engineers, Transportation
Planning and the Division Office should also be invited to attend Project Team
meetings to provide technical information and input. (Each agency will determine
whom to invite to the meeting based on project issues.)
Concurrence Points and Project Phases
There are seven strategic decision (concurrence) points in the NEPA project
development and permitting process:
1. Purpose and Need and Study Area Defined: The foundation upon which justification for the project is established.
2. Detailed Study Alternatives Carried Forward: Alternatives which satisfy the purpose and need for the project. These alternatives will be studied and evaluated in sufficient detail to ensure good transportation and permit decision-making.
2A. Bridging Decisions and Alignment Review: Identification of bridge locations and approximate lengths and a review of the preliminary alignment for each alternative
3. LEPDA/Preferred Alternative Selection: The alternative selected as the “least environmentally damaging practicable alternative” or LEDPA (NEPA preferred alternative), through the project development and permitting process.
4A. Avoidance and Minimization: A detailed, interdisciplinary and interagency review to optimize the design and benefits of the project while reducing environmental impacts to both the human and natural environment.
4B. 30 Percent Hydraulic Review: A review of the development of the drainage design.
4C. Permit Drawings Review: A review of the completed permit drawings after the hydraulic design is complete and prior to permit application.
Implementation Procedures:
Attached to this MOU are implementation procedures which provide detailed
information that have been developed to provide guidance for the Section 404/
NEPA Merger 01 Process (Merger 01 Process). These implementation
procedures have been developed for three basic types of projects as follows:
- Process I - Projects on New Location
- Process II - Widening and Other Improvement Projects
- Process III - Bridge Replacement Projects Processed as a Categorical Exclusion
The guidance for each of these processes consists of a flow chart and detailed
guidance on how to complete each step of the flow chart. If there is doubt as to
which process to follow, the Project Team will decide which process to use.
Conflict or Dispute Resolution:
Concurrence at critical identified points in the project development and permitting process is the key to the success of the Merger 01 Process. However, it is recognized that there may be instances where the Project Team cannot reach concurrence due to diverse agency missions, philosophical differences or policy issues. If the team members of an agency or agencies cannot concur, the approved guidance for conflict or dispute resolution will be initiated. See Appendix C.
Modification:
Substantive changes to this process will require approval of all primary signatories. Modification may be proposed by one or more signatories. Proposals for modification will be circulated to all signatories for a 30-day review period. Approval of such proposals will be indicated by written acceptance. A signatory may terminate participation in this agreement upon 30-day written notice to all other signatories.
Signatures:
The four agencies listed below as primary signatories are the process owners of the Merger 01 Process. These agencies are the primary decision-making authority with regard to NEPA and Section 404 permitting and are responsible for conflict or dispute resolution.
The agencies listed as partnering signatories have a significant role as project
team members in the Merger 01 Process, and in some cases, may have a
statutory compliance role or regulatory function to fulfill. Nearly all of the listed
agencies are currently participating as project team members under the existing
Merger Process. In addition, many of the listed agencies have participated in
developing the Merger 01 Process procedures. By signing this document, these
agencies agree to participate and abide by the procedures described in the
Merger 01 Process. Such agreement does not compromise or eliminate
statutory or regulatory remedies available to the listed agencies (e.g. 404(q) or
(c)) nor does it circumvent statutory requirements that are mandated to specific
agencies. The intent of this agreement is to provide an interactive, predictable
process that allows agencies to address their statutory and regulatory
requirements during the development of transportation projects within the State
of North Carolina.
Primary Signatories:
Partnering Signatories:
______________________________________________________
U. S. Environmental Protection Agency
|
____________
Date
|
______________________________________________________
U. S. Fish and Wildlife Service
|
____________
Date
|
______________________________________________________
National Marine Fisheries Service
|
____________
Date
|
______________________________________________________
North Carolina Wildlife Resources Commission
|
____________
Date
|
______________________________________________________
North Carolina Department of Cultural Resources
|
____________
Date
|
______________________________________________________
U. S. Coast Guard
|
____________
Date
|
______________________________________________________
U. S. Forest Service
|
____________
Date
|
______________________________________________________
Tennessee Valley Authority
|
____________
Date
|
______________________________________________________
National Park Service
|
____________
Date
|
|