Process I - Projects on New Location
General
Project Team Meetings
Step by Step Implementation Procedures
Initiation of Project Study
Data Collection
Develop Project Team
Project Scoping
Notice of Intent
Develop Purpose and Need (P & N)
Concurrence Point 1 - Purpose and Need and Study Area Defined
Environmental Features Map
Alternative Corridors Development, Functional Design and Citizens Information Workshop (CIW)
Alternative Development, Analysis, and Screening Meetings
Concurrence Point 2 – Detailed Study Alternatives Carried Forward (DSA)
Environmental Analyses and Preliminary Design of Detailed Study Alternatives
Concurrence Point 2A – Bridging Decisions and Alignment Review
Prepare Draft EIS/EA, Conceptual Mitigation Proposal and Section 404 Application
Issue DEIS/EA and Submit Section 404 Application
Notice of Availability and Section 404 Public Notice
Corridor/Design Public Hearing
Agency and Public Comment Period
Post Hearing Meeting and Resolve Comments
Concurrence Point 3 – LEDPA/Preferred Alternative Selection
Concurrence Point 4 A – Avoidance and Minimization
Prepare Final EIS or FONSI
Issue Final EIS or FONSI
Agency and Public Comment Period
Prepare and Issue Record of Decision (ROD)(EIS Projects)
Design Public Hearing or Public Information Meeting
Develop Right of Way Plans for the Project
Concurrence Point 4B – 30 Percent Hydraulic Review
Complete Right of Way Plans for the Project
NCDCM On-Site Pre-Application Meeting
Concurrence Point 4C – Permit Drawings Review
Compensatory Mitigation Requirements
Submit Updated Permit Application
Permit Application Review & Processing
Agency Public Notice if Required
Permit Decision
Changes to the Project’s Design, Construction Methodology or Construction Timeframe
Final Plans for the Project
Let Project
Preconstruction Meeting
Compliance Monitoring
Project Completion
Permit Process
General
A process flow chart that outlines the Section 404/NEPA Merger 01 Process
(Merger 01 Process) for projects on new location is attached (Process I). This
flow chart depicts the major milestones in the process but it does not include all
of the many activities that NCDOT must complete in the project development
process. These other activities will be completed by NCDOT and input provided
into the merger process at the appropriate time. For example, public involvement
is a critical component of the project development activities and will be ongoing
throughout the process. Information developed through public involvement will
be made available to Project Team members for consideration in the decision
making process.
Project Team Meetings
Team meetings will be held at each of the concurrence points in the Process.
Additional meetings may be held as determined necessary by the Project Teams.
NCDOT’s Project Development Engineer should coordinate closely with the
appropriate USACE, FHWA, and NCDENR team members in scheduling any
meetings and clearly defining the purpose of the upcoming meeting. The Project
Development Engineer or Hydraulics Project Engineer will send the package of
information for the meeting to team members so that they will have it in hand at
least two weeks prior to the meeting. The transmittal to each team member
should clearly state the purpose and objective of the meeting. This will allow
team members time to review the information and be prepared to discuss any
issues or concerns they have at the meeting. Appendix A provides guidance on
information to be presented at each concurrence meeting.
At the end of each meeting, the Project Development Engineer or Hydraulics
Project Engineer, with the team’s help, will summarize the results of the meeting,
including agreements or concurrence points achieved. If agreement or
concurrence is not obtained, the next steps or action items should be clearly
identified. If additional information or action is required, the type of information
or action needed and the responsible agency(ies) or team member(s) should be
clearly noted.
The Project Development Engineer is responsible for preparing a summary of all
meetings for distribution to all team members, except the summary for the 4B
and 4C Concurrence meetings that will be completed by the Hydraulics Project
Engineer. Each team member will read the meeting summary that includes
issues agreed upon, outstanding issues, and action statements (next steps)
carefully to ensure accuracy of the project records. Substantive errors and
omissions will be identified and provided within 30 days to the Project
Development Engineer or Hydraulics Project Engineer for prompt resolution.
On-site project field reviews can be very beneficial in helping to understand a
project’s purpose and need, human and natural environmental features and
alternative analysis. Project Teams are encouraged to hold combined field
reviews/meetings as needed to assist in the decision making process.
Step by Step Implementation Procedures
The following discussion is intended to provide more detailed guidance and
explanation on the various steps and concurrence points in the attached flow
chart. The numbered paragraphs correspond to steps or blocks in the chart.
1. Initiation of Project Study
NCDOT will begin the project study by gathering background data and
information and sending out the project scoping letter and/or start of study letter.
This letter initiates the project’s concept and solicits input from federal and state
agencies (including the State Clearinghouse), local government agencies, the
public, and other NCDOT units and branches. The level of detail provided in
these letters includes a TIP description and a vicinity map.
2. Data Collection
The Project Development Engineer will collect all available information, including
aerial photography (orthophotographs), and background data needed to hold a
project scoping meeting, as identified by responses to the scoping letter and
standard requirements.
3. Develop Project Team
The Project Development Engineer will consult with the appropriate USACE,
NCDENR and FHWA representative to identify specific Project Team members.
NCDOT will provide written verification of team members to all the team
members. If an agency declines to participate on the team, their decision will be
documented in writing to NCDOT, NCDENR, USACE and FHWA. If an agency
drops from the Project Team during the process, their self-removal will also be
documented in writing.
4. Project Scoping
The Project Scoping Meeting is held by NCDOT to discuss background data,
preliminary purpose and need, engineering and environmental inventories, the
proposed scope of the project, and potential substantial project issues.
Resource agencies will be invited to attend and provide input. Agencies should
provide written input in response to the scoping letter or attend the scoping
meeting.
In lieu of a scoping meeting, a formal start of study meeting may be held on
projects that the Project Development Engineer concludes that a formal meeting
will expedite the project. This meeting will include all NCDOT Branches and
Units responsible or participating in project development activities and local
government representatives having an interest in the project. Resource agencies
will be invited to attend and provide input.
The purpose of this meeting is to share information regarding anticipated
economic and transportation benefits and/or adverse impacts to the community,
and known human and natural environmental constraints. The meeting will also
provide local government representatives an opportunity to provide input into the
project scope.
At the project scoping meeting, NCDOT will provide the proposed project
schedule. The meeting attendees will present any issues that may impact the
proposed schedule. Needed revisions to the project schedule will be identified
and adjusted appropriately by NCDOT.
5. Notice of Intent
If NCDOT and FHWA determine an EIS should be prepared, a Notice of Intent
will be filed in the Federal Register. If it is not clear at this point that potential
project impacts warrant an EIS, the decision to prepare a Notice of Intent may be
delayed until step 12 when more information is available.
6. Develop Purpose and Need (P & N)
Transportation Planning provides a Planning Level Purpose and Need for each
project that was developed during the systems planning process to the Project
Development Engineer. In cases where Transportation Planning does not have
personnel assigned to a particular area, the Project Development Engineer will
develop a draft Purpose and Need. Also, additional engineering and
environmental inventory data may be obtained for use in further developing and
refining the Purpose and Need for a project. The type of information and level of
detail collected must be determined for each project and could include
information such as the following:
- Preliminary limits of the study area
- Existing traffic and future no-build average daily traffic
- Roadway geometric deficiencies and accident history
- Transportation plans
- Land use plans
- Areas of interest to local citizens and elected officials
- Legislative mandates
- Economic initiatives
- Intermodal relationships, including bicycle/pedestrian systems, transit (rail and bus), port facilities and airport facilities
- Project history and background information including feasibility studies and community issues
- Highway Needs Inventory (HNI) status
- GIS Mapping
- Aerial Photography
- Other readily available information
7. Concurrence Point 1 - Purpose and Need and Study Area Defined
The Purpose and Need (P & N) Statement forms the basis for identification of
alternatives to be evaluated. Therefore, concurrence will be obtained on the
Purpose and Need before potential alternatives are identified. NCDOT will
prepare a draft Purpose and Need Statement, along with supporting technical
documentation. The P & N information package will be sent to team members so
that they will receive it at least two weeks prior to the team meeting. The
supporting technical information will include a GIS map of the study area and a
summary of any information or comments from the public concerning purpose
and need and community concerns. This statement should clearly demonstrate
that a “need” exists and should define the “need” in terms understandable to the
general public. The statement should clearly describe the problems that the
proposed action is to correct.
A team meeting will be held to discuss the draft P & N Statement and Study Area
along with supporting data. Team members will review the information prior to
the meeting and be prepared to discuss any concerns. At the meeting, the
NCDOT Project Development Engineer will provide GIS level mapping of the
Study Area and aerial photography (orthophotography). Also, any other readily
available information will be presented for the team’s information. The Study
Area may need to be expanded to accommodate environmental features. Also, it
may be necessary to conduct more than one meeting on Purpose and Need if
additional information is needed to define the Project Study Area. The goal of the
meeting is for team members to concur with and sign the Purpose and Need and
Study Area concurrence form.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
If concerns are raised at the team meeting, which require additional
documentation or revisions to the P & N Statement, the NCDOT will incorporate
the additions or revisions and redistribute the P and N Statement for concurrence
or comment. This will be done prior to the follow-up Concurrence Point 1 meeting
or as soon as possible if it is determined that a second meeting is not required.
8. Environmental Features Map
After Purpose and Need and Study Area concurrence has been obtained,
NCDOT, with consultation from the agencies, will develop an environmental
features map illustrating resource areas of concern as well as topographic or
photogrammetric mapping. The purpose of this mapping is to provide a means
for identifying alternatives that warrant study on a screening level basis. Such
features on the mapping will include but are not limited to:
- Infrastructure and topography
- Community features (i.e., boundaries, schools, churches, community centers, hospitals, transit dependent populations, demographics, etc.
- Floodplains
- Historic properties and possible areas of archaeological concern
- Wetlands, streams, buffers, river basins, and water supply watersheds (GIS level information)
- Wildlife refuges and game lands
- Recreational areas and parks
- Hazardous material sites
- Existing land use map and locally adopted land use plan
- Threatened and Endangered Species information
- Significant Natural Heritage Program Areas
- Identify utilities within project study area using best available information
Based on the environmental features map, the study area may be re-confirmed.
Generally, the study area will not be redefined unless new information
necessitates re-evaluation
9. Alternative Corridors Development, Functional Design and Citizens Information Workshop (CIW)
The NCDOT Project Development Engineer and the Design Engineer will identify
preliminary corridors that address the Purpose and Need for the project and
consider the environmental constraints within the study area. The Design
Engineers will prepare functional designs for each preliminary corridor that is
considered. A functional design is a very general design that includes horizontal
and vertical alignments, edge of pavements, slope stakes, and right of way limits
for all alignments and interchanges. No turn lanes or superelevation are added
at this stage. This design is done on orthophotographs.
After identification of the preliminary corridors, the NCDOT will hold a Citizens
Informational Workshop (CIW) or conduct other public involvement to present the
Project Purpose and Need for the project and preliminary corridors that are
identified. Project Team members are encouraged to attend and participate in
these workshops to fully understand public concerns and issues. A file
memorandum will be prepared by the Project Development Engineer to
summarize and document public input and it will be included as part of the
informational package for team members. The Project Team will consider the
comments received at the CIW in selecting alternatives to be studied further.
Any additional corridors recommended by the public will be considered by
NCDOT and presented to the Project Team as appropriate.
10. Alternative Development, Analysis, and Screening Meetings
Prior to the first Project Team meeting on alternatives, the Project Development
Engineer will send team members a copy of a draft Preliminary Alternative
Analysis Report, which includes the summary of public input. At the meeting on
alternatives, team members should be prepared to discuss the alternatives and,
if appropriate, suggest modifications to NCDOT’s preliminary conceptual
alternatives and/or recommend additional alternatives. Also, team members may
- Identify specific or additional environmental resources that are important
- Recommend any additional alternatives/studies necessary
NCDOT will prepare detailed minutes of the meeting. It is recognized that one or
more team meetings may be necessary to develop, analyze and screen
alternatives to satisfy every agency’s needs. Team member comments will be
noted in minutes of the meeting prepared by the Project Development Engineer.
Prior to the Project Team meeting for Concurrence Point 2 (Detailed Study
Alternatives Carried Forward), the Preliminary Alternatives Report will be
completed and distributed to the Project Team members. The report will identify
all the alternatives considered during the preliminary alternatives phase of the
project and provide justification for those alternatives recommended for
elimination from further consideration. The decision to eliminate alternatives
must be made jointly by the team members. No alternatives will be eliminated
without the concurrence of each member of the Project Team. The rationale for
eliminating alternatives from further consideration will be documented by the
Project Development Engineer.
If no additional alternatives or studies are requested, the team may proceed
directly to step 11(Concurrence Point 2).
11. Concurrence Point 2 – Detailed Study Alternatives Carried Forward (DSA)
The intent of the Concurrence Point 2 meeting is to obtain consensus from the
Project Team on which corridors will be fully evaluated as alternatives, including
the “no build” alternative, in the environmental document. The alternatives
selected must meet the purpose and need of the project with the exception of the
“no build” alternative.
The Project Team will strive to reach agreement on alternatives that meet the
Purpose and Need and include all alternatives that should be evaluated in detail
in the environmental document to fulfill NEPA and Section 404 requirements.
Concurrence by the Project Team on detailed study alternatives to be included in
the draft document, as part of the NEPA and NCEPA process and corresponding
Section 404 Permit Public Notice, is not a commitment on the part of the
regulatory agency to permit any of the alternatives nor is it a commitment for the
engineers to seal any alternative. Rather, it is for the purpose of obtaining public
and agency comments on the merits of each alternative for consideration by the
decision-makers in the selection of the Least Environmentally Damaging
Practicable Alternative (LEPDA)/Preferred Alternative.
At the Project Team meeting, the following topics will be discussed and
documented in the meeting minutes:
- The rationale for retaining or dropping preliminary conceptual alternatives
- The level of involvement of other agencies and interested parties (i.e., Coast Guard, local agencies, Section 106 consulting parties, etc.), as well as their comments (if any) on the project
- Type of access control (may be discussed earlier in process if implicit in purpose and need)
The NCDOT will request formal concurrence at this meeting by asking team
members to sign the Concurrence Point 2 form. The signatures indicate that the
team member’s comments on the Preliminary Alternatives Report were
adequately addressed and no new issues were raised during the meeting. If
additional documentation or revisions to the report are necessary, the NCDOT
will incorporate the additions or revisions and redistribute the report. If
necessary, an additional team meeting will be scheduled to resolve outstanding
concerns. Once concurrence is reached, no new alternatives will be added
unless there is significant new information, or significant changes to the project,
the environment, constructability, or laws and regulations.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
12. Environmental Analyses and Preliminary Design of Detailed Study Alternatives
After the detailed study alternatives are selected, the potentially impacted human
and natural resources, including wetland and stream delineations will be
identified for each alternative. NCDCM’s GIS-based wetland inventory mapping
program should be used to help identify wetland significance. The Project
Development Engineer, in coordination with the Office of Natural Environment,
will determine if there are resources that will require bridging decisions at Step
13, Concurrence Point 2A, and if so, will invite the Project Team members to
attend an agency field review meeting. Also, if appropriate, an agency field
review meeting will be held to:
- Verify jurisdictional wetland and stream boundaries. The USACE will provide written jurisdictional verifications immediately after the field review meeting
- Review any potential mitigation sites that may be noted during the delineation effort and coordinate with Ecosystem Enhancement Program (EEP)
- Review potential bridging decisions, if applicable
After receipt of the delineations and necessary preliminary mapping, the Design
Engineer will begin to develop the preliminary designs for each alternative. The
preliminary design is a very specific design that includes horizontal and vertical
alignments, edge of pavements, slope stakes, turn lanes, superelevation, and
right of way revisions. This design is done on preliminary mapping.
During the development of the design, care will be taken to avoid and minimize
impacts to the natural and human environment based on information provided by
the appropriate units in NCDOT.
Where it is not practicable to avoid impacts, minimization measures will be
employed using context sensitive design and other means to fit the project within
the study area. The Design Engineer will coordinate the preliminary design for
each detailed study alternative with the Utility Sections. The Utility Sections will
identify areas where any known utilities are impacted.
13. Concurrence Point 2A – Bridging Decisions and Alignment Review
After the preliminary designs are complete, impacts based on project footprint will
be identified and quantified. At this time, the preliminary designs will include any
recommended control of access that will be acquired for the project. The control
of access limits are needed so it can be reflected in right of way estimates,
shown to the public and for the Project Team’s review. In addition, potential
service road locations and potential utility impacts are identified so the impacts
can be included in the comparison of the project alternatives.
Using the hydraulic recommendations and all available environmental
information, the Project Team will determine the placement and length of bridges.
In addition, a review will be made to determine which natural resources warrant
additional avoidance measures. The bridge locations and approximate lengths
will be identified on each alternative.
A concurrence meeting will be held to gain concurrence for all bridge locations
and lengths. At this point identification of any changes to the preliminary design
that might be needed before finalization of the preliminary engineering and
completion of the environmental document should be addressed. All team
members will be asked to sign a concurrence form at the meeting to signify that
they agree with the bridge locations and approximate lengths. After the bridge
locations are determined, an updated construction cost estimate and summary of
impacts for each alternative will be developed. This information will be provided
for each alternative within the Draft EIS or EA. In order to develop accurate cost
estimates, where appropriate (such as habitat fragmentation), additional
avoidance and minimization techniques that carry high monetary costs, such as
wildlife crossings and retaining walls, will also be identified.
During the Concurrence Point 2A meeting, the Project Team will discuss which
federal, state, and local environmental statutes and regulations may apply to
each of the detailed study alternatives. Within NCDOT, the Office of the Natural
Environment (ONE) is responsible for ensuring that the specific required steps
are followed for each of the environmental permits, certifications, consultations,
reviews and determinations that may be required throughout the project’s life.
The Hydraulics Unit will ensure that FEMA flood insurance program regulations
are followed where applicable.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and adjusted
appropriately by NCDOT.
Upon reaching this concurrence point, the Project Development Engineer will
document all avoidance and minimization to all resources that has been achieved
to this point in project development. This information will be provided to the
Project Team and to ONE for inclusion in the updated permit application. Also,
the Project Development Engineer will notify the Ecosystem Enhancement
Program (EEP) of the worst-case preliminary design impacts.
14. Prepare Draft EIS/EA, Conceptual Mitigation Proposal and Section 404 Application
The environmental document will be completed according to NEPA and an
identification of impacts will be made for each of the alternatives that are studied
in detail. There will be a discussion of why preliminary alternatives were
eliminated.
NCDOT will address potential on-site compensatory mitigation options. For
potential on-site mitigation sites, NCDOT ONE will prepare a feasibility study that
includes an environmental evaluation that identifies historic resources,
threatened and endangered species, parks, community issues, etc. NCDOT
ONE may arrange an agency field meeting to review any potential on-site
mitigation opportunities, discuss the environmental evaluation results, and
determine which sites are acceptable to the agencies.
Pursuant to the Memorandum of Agreement among the NCDOT, NCDENR, and
USACE signed July 22, 2002, the Ecosystem Enhancement Program (EEP) will
provide all compensatory mitigation that is not satisfied by acceptable on-site
mitigation. Preliminary determinations about the Federal, state, and local
environmental statutes and regulations that may apply to each of the detailed
study alternatives will be included within the environmental document. If the
project is within a CAMA county(ies), then potentially relevant CAMA land use
plan policies that may apply to each detailed study alternative will also be
included within the draft environmental document.
All information produced in previous studies will be incorporated in an
environmental document.
The FHWA and NCDOT will review the preliminary environmental document for
adequacy as it relates to NEPA requirements. NCDOT will revise the
environmental document based on these comments or consult further with
FHWA to resolve issues.
The NEPA document shall develop an analysis of secondary/indirect and
cumulative impacts of sufficient scope and detail to fulfill all NEPA requirements.
In addition, the analysis should be developed, in concurrence with current
policies and procedures, to a level of detail sufficient to make decisions required
by all other state and Federal laws, statutes, rules, and regulations.
15. Issue DEIS/EA and Submit Section 404 Application
NCDOT and FHWA will sign the title page of the environmental document (DEIS
or EA) prior to NCDOT circulating it. NCDOT will submit the Section 404 permit
application to the USACE at the time of document approval. NCDOT will also
provide the USACE with a mailing list developed in the public involvement
process that includes adjacent property owners and mailing labels. The
environmental document will be distributed to federal agencies, State
Clearinghouse, and local agencies and organizations for review and comment.
After issuance of the environmental document, an interagency field review will
be made unless the Project Team determines otherwise. The purpose of this
meeting is for team members to review alternatives in the field prior to the
Concurrence Point 3 meeting; however, it may not be necessary if team
members have reviewed alternatives in the field previously.
16. Notice of Availability and Section 404 Public Notice
The USACE will issue a Section 404 Public Notice, if appropriate. The
environmental document and Public Notice are made available for public and
agency comment for the prescribed time frames. NCDOT should consult with the
USACE, NCDOT board members, and other interested parties to set the public
hearing date. Once the date is set, the USACE should be immediately notified of
location, time and place. NCDOT will publicize the public hearing.
17. Corridor/Design Public Hearing
NCDOT will hold the Corridor/Design Public Hearing. Project Team members
are encouraged to attend the public hearing to fully understand the public
concerns. The USACE and other Project Team members will be invited to attend
the public hearing.
18. Agency and Public Comment Period
The public may submit written comments to NCDOT, FHWA and/or the USACE
after, the public hearing. Also, agency and public comments on the
environmental document should be submitted to FHWA and NCDOT and the
Section 404 Public Notice comments should be sent to the USACE. The
agencies will format their letters to identify which comments are pertinent to the
selection of the LEDPA/Preferred Alternative.
NCDOT will adequately address those specific comments prior to selection of the
Least Environmentally Damaging Practicable Alternative (LEDPA)/Preferred
Alternative and distribute their responses within the information material for the
Concurrence Point 3 meeting.
19. Post Hearing Meeting and Resolve Comments
Following the comment periods, NCDOT will review and summarize the
comments received from the document review and public hearing process. The
USACE will forward the comments on the Section 404 Public Notice for inclusion
in the summary. NCDOT will then hold a post-hearing meeting. Project Team
members are invited to attend this meeting. The purpose of this meeting is to
evaluate all substantive comments received and determine if any additional
studies or changes are needed to properly address issues that have been
raised. Any additional work or studies to resolve comments will be completed by
NCDOT. All agency comments on the environmental document and Section 404
Public Notice that affect the selection of the LEDPA/Preferred Alternative will be
addressed and appropriate information or responses prepared prior to the
Concurrence Point 3 meeting.
20. Concurrence Point 3 – LEDPA/Preferred Alternative Selection
A Project Team meeting will be held to determine the Least Environmentally
Damaging Practicable Alternative (LEDPA) [Preferred Alternative under NEPA].
The Project Development Engineer will send the package of information for the
meeting to Project Team members so they will have it in hand at least two weeks
prior to the meeting. The package will include a matrix (for example, summary
information from DEIS) illustrating a comparison of impacts for the detailed study
alternatives and a brief summary of previous Project Team decisions. The
package will also include a summary of substantive comments received from
agencies and the public and how these comments were addressed.
When all substantive comments relative to the LEDPA/Preferred Alternative
selection submitted by the agencies during the environmental document review
and the public hearing/public notice commenting period have been adequately
addressed and no new issues have been identified, the Project Team will select
a LEDPA/Preferred Alternative. At the time it is selected, Project Team members
will be reasonably certain that the LEDPA/Preferred Alternative will comply with
all relevant regulations and permit requirements, is safe, and can be authorized.
Project Team members in agreement with the LEDPA/Preferred Alternative will
provide their formal concurrence at this meeting by signing the Concurrence
Point 3 form.
During the Concurrence Point 3 meeting, the Project Team will confirm the
preliminary determination made during the Concurrence Point 2A meeting about
the federal, state, and local environmental statutes and regulations that may
apply to the LEDPA/Preferred Alternative.
This confirmation is required due to changes that may have occurred in the
project design and/or in the statutes and regulations since the preliminary
determination was made during the Concurrence Point 2A meeting. Within
NCDOT, the Office of the Natural Environment (ONE) is responsible for ensuring
that the specific required steps are followed for each of the environmental
permits, certifications, consultations, reviews and determinations that may be
required throughout the project’s life. The Hydraulics Unit will ensure that FEMA
flood insurance program regulations are followed where applicable.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
The public will be notified of the selection of the LEDPA/Preferred Alternative via
newsletter, news release or other means determined satisfactory by NCDOT
policy.
21. Concurrence Point 4 A – Avoidance and Minimization
Following selection of the LEDPA/Preferred Alternative, a Project Team meeting
will be held to discuss additional avoidance and minimization efforts not included
in the preliminary design during the alternative analysis phase of the project.
This concurrence point should address issues such as alignment shifts,
horizontal and vertical alignment, slopes, construction techniques In addition,
service road locations should be reviewed for avoidance and minimization and
utility relocations should be reviewed for minimization.
For projects where bridge length and location were not previously agreed to, a
decision on these parameters will be included in the Concurrence Point 4A
meeting. Upon agreement that project jurisdictional impacts have been avoided
and minimized to the maximum extent practicable based on current information
and design available at that time, the Project Team members will sign the
Concurrence Point 4A form. When avoiding and minimizing jurisdictional
resource impacts, other resources will be considered.
It should be recognized that additional minimization may be achieved during the
final design process with more precise mapping, including the project hydraulic
design (Concurrence Points 4B and 4C). Upon reaching Concurrence Point 4A,
the Project Development Engineer will document all avoidance and minimization
that has been achieved to this point in project development. This information will
be provided to the Project Team and to the Office of Natural Environment for
inclusion in the updated Section 404 permit application. NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
22. Prepare Final EIS or FONSI
NCDOT/FHWA will prepare the Final EIS or FONSI. The Final EIS or FONSI will
discuss the rationale behind the selection of the LEDPA/Preferred Alternative. It
is not necessary to complete Concurrence Point 4A prior to the completion of the
Final EIS or FONSI. However, any additional avoidance and minimization
measures that have been identified or incorporated up to that point in the project
development should be included in the Final EIS or FONSI. The FHWA and
NCDOT will review the final environmental document for adequacy as it relates to
NEPA requirements. NCDOT will revise the environmental document based on
these comments or consult further with the FHWA to resolve issues. The final
environmental document will include all environmental commitments and the
mitigation plan to address all resources, such as wetlands, streams, Section 106,
Section 4(f), public access, etc.
Preliminary determinations about the federal, state, and local environmental
statutes and regulations that may apply to the LEDPA/Preferred Alternative will
be included within the final environmental document. If the project is within a
CAMA county(ies), then potentially relevant CAMA land use plan policies that
may apply to the LEDPA/Preferred Alternative will also be included within the
final environmental document.
23. Issue Final EIS or FONSI
NCDOT and FHWA will sign the title page of the final environmental document
(FEIS or FONSI) prior to distribution by NCDOT. If FHWA expects to issue a
FONSI for a highway project of four or more lanes on new location or a new
controlled access freeway, copies of the EA shall be made available for public
review for a minimum of 30 days before FHWA makes its final decision.
NCDOT’s Citizens Participation Unit will announce this public availability by a
notice similar to a public hearing notice. The environmental document will be
distributed to federal agencies, State Clearinghouse, and local agencies and
organizations for review and comment.
24. Agency and Public Comment Period
The agencies and the public may submit written comments to NCDOT and
FHWA concerning the FEIS or FONSI document. In consultation with FHWA,
NCDOT will respond directly to the commenting agencies concerning comments
received on a FONSI. Comments received on a FEIS will be addressed in the
ROD with copies provided to the commenting agency.
25. Prepare and Issue Record of Decision (ROD)(EIS Projects)
FHWA will issue the ROD. The ROD will address any comments received on the
FEIS. A Notice of availability will be issued by NCDOT.
26. Design Public Hearing or Public Information Meeting
A corridor/design public hearing was held after the Draft Environmental Impact
Statement (Draft EIS) or the Environmental Assessment (EA) was completed.
Because there was not a selected alternative presented to the public during the
corridor/design public hearing, another hearing or citizens’ informational
workshop will be held to display the selected alternative and to review any
changes that were made within the design during the remainder of the NEPA
process. This meeting should be held prior to the project being sent to right of
way. Comments from the public will be reviewed to determine any needed
changes. Changes requested from the public and accepted by the Project Team,
if necessary, will be incorporated into the design prior to completion of right of
way plans.
(For phased projects please refer to text at the end of this document.)
27. Develop Right of Way Plans for the Project
After selection of the LEDPA/Preferred Alternative, the Location and Surveys
Unit and the Photogrammetry Unit perform the final surveys and deliver the plan
sheet mapping needed for the development of the right of way and final plans.
Upon receiving the plan sheets, the design engineers begin to develop the right
of way plans for the project. After the design engineers complete the horizontal
and vertical alignment for the roadway, the Utility Sections will review the
horizontal and vertical alignment and will coordinate with the Hydraulics Unit
regarding the utility locations. The Hydraulics Unit begins the development of the
proposed drainage design and the Geotechnical Engineering Unit begins the
detailed geotechnical investigations for the project. (The Design Engineers will
develop the right of way plans following the alignment that was agreed upon at
Concurrence Point 4A).
28. Concurrence Point 4B – 30 Percent Hydraulic Review
At the time the hydraulic design for the project is 30 percent complete, the
Hydraulics Project Engineer will hold a Concurrence Point 4B meeting to review
the development of the drainage design. All appropriate Project Team members
should attend (USACE and NCDWQ attendance is mandatory. If the project is
within a CAMA county(ies), NCDCM attendance is mandatory). If a project
requires a State Stormwater Management Permit, the Hydraulics Project
Engineer will work with the NCDWQ Stormwater Management Section to obtain
the permit and report its progress to the team members. The Hydraulics Project
Engineer will provide the package of information to team members so that they
receive it two weeks in advance of the meeting.
Also, before the Concurrence Point 4B meeting is held, the Hydraulics Project
Engineer will consult with the ONE staff to ensure that the environmental surveys
(wetlands, threatened and endangered species, streams, and buffer) for each
project is complete and current.
At the 4B meeting, the Hydraulics Project engineer will present preliminary
drainage designs to the team members. The drainage plans will depict the
boundaries of the affected environmental areas (wetlands, perennial and
intermittent streams, buffers, Coastal Area Management Act Areas of
Environmental Concern (CAMA AEC’s), etc.), existing draining structures, layout
of proposed drainage structures, and stormwater best management devices.
Large structures such as bridges and box culverts will also be discussed.
The Hydraulics Unit will take notes of comments received during the meeting.
The Hydraulics Unit will distribute meeting minutes, which will include how
comments will be addressed. Also, the meeting minutes will identify onsite
mitigation opportunities that will be incorporated into the project design as
appropriate.
It is understood minor vertical changes may be needed due to hydraulic needs.
If vertical changes do occur that result in additional environmental impacts, minor
horizontal adjustments in alignment may be appropriate.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
29. Complete Right of Way Plans for the Project
Upon receiving the completed hydraulic design for the project, NCDOT Design
Engineers incorporate the hydraulic design, locate any remaining service road
locations, and establish the proposed right of way limits for the project. The
Structure Design Engineers begin to develop the designs for bridges and
culverts. The Utility Sections will begin to coordinate the determination of the
utility conflicts and the development of the utility relocation preliminary designs
with the Utility owners and the Design Engineers. The project is then reviewed
with construction and right of way personnel to note any additional changes that
may be required. The right of way plans are completed and sent to the Right of
Way Branch to begin purchase of land required for the project.
30. NCDCM On-Site Pre-Application Meeting
For projects within a CAMA County (ies) that require a CAMA major permit, the
NCDOT Office of Natural Environment Permit Specialist will request an on-site
pre-application meeting with the appropriate NCDCM Field Representative. The
purpose of this meeting is to review the plans and/or permit drawings and
information that will be submitted with the CAMA permit application. This will
ensure that when the CAMA major permit application is formally submitted, it
contains all of the information necessary for processing. The purpose of this
meeting is not to make changes to the project design, construction methodology
or construction timeframe. However, if any potential changes to the project are
identified at the on-site pre-application meeting, then they will be discussed with
the full Project Team at the Concurrence Point 4C meeting prior to approval.
31. Concurrence Point 4C – Permit Drawings Review
At the time the hydraulic design is 100 percent complete and the permit drawings
for the project are finalized, the Hydraulics Unit will hold a Concurrence Point 4C
meeting. At the Concurrence Point 4C meeting, the Hydraulics Project Engineer
will present copies of the Stormwater Management Plan to the Project Team
members. A Stormwater Management Plan is a narrative, project-specific,
Stormwater Design Report. It outlines project involvement, river basins,
classifications of the involved water bodies, selected structural and non-structural
best management practices, best management practice devices, and major
structures (bridges and box culverts). The final permit drawings for the permit
application will also be reviewed and revised based on comments received at this
meeting.
Any area where utility relocations affect additional environmental resources
beyond the footprint of the roadway will be shown on the permit drawings and will
be included in the impacts presented in the application.
In addition, if the project is within a CAMA county(ies) and a CAMA Major permit
is required, then all utility relocations that are not included in the permit drawings
will be described within the CAMA Major Permit application either in narrative
form or in a separate spreadsheet. The level of detail of utility relocation
information required within the CAMA major permit application will be determined
on a project-by-project basis at the NCDCM on-site pre-application meeting.
The Hydraulics Engineer will record minutes of the meeting and will address the
team’s comments. Changes will be made based on the team’s comments. The
changes will be made in the permit drawings before the permit application is
sent. The Concurrence Form indicates that the Project Team agrees that the
drawings as presented are satisfactory to be submitted with the application.
(This does not supercede the regulatory review process.)
After the changes are incorporated, the Hydraulics Engineer will ask for a
signature of the Concurrence Form. The Concurrence Form will be detailed
enough to document and identify changes. Any changes to impacts to wetlands,
streams, buffers, or AEC’s that occur after the 4C document is signed will require
the resource agencies to revisit the design, and may require a new 4C meeting.
The NCDOT Permit Specialist will contact the agencies via e-mail, letter, phone
call or scheduling a meeting as appropriate to facilitate review of these changes.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
32. Compensatory Mitigation Requirements
Compensatory mitigation requirements will be identified based on final project
impacts.
In those events where on-site mitigation opportunities are available and
determined acceptable and/or necessary by the Project Team, the mitigation plan
and design will be developed in concert with the overall project design. Removal
of existing causeway fills is strongly encouraged to offset project impacts and/or
create mitigation credits for future project impacts. The on-site mitigation will be
developed and implemented by NCDOT in collaboration with the Project Team
and EEP. Under no circumstances will the project be permitted until such time
that the detailed on-site mitigation plan is complete and approved by the
permitting agencies. Pursuant to the Memorandum of Agreement among the
NCDOT, NCDENR, and USACE, signed July 22, 2002, the Ecosystem
Enhancement Program (EEP) will provide all compensatory mitigation that is not
satisfied by acceptable on-site mitigation.
33. Submit Updated Permit Application
The Office of Natural Environment Permit Specialist submits updated permit
application(s) as appropriate to all of the agencies for which permits are required.
Permit application(s) will be submitted within approximately two months after the
4C meeting. The permit application package will vary according to each
agencies specific requirements.
34. Permit Application Review and Processing
Upon receiving the permit application from NCDOT, the permitting agency(ies)
will review the application for completeness. If the permit application is
determined to be incomplete, the permitting agency(ies) will return the application
to NCDOT for additional information, and/or inform NCDOT of the additional
information that is required.
After the permitting agency (ies) determine that the permit application is
complete, the permitting agency (ies) will assemble and distribute the application
package for comment to any designated review agencies. This process varies
according to the permit being requested.
If the permit application is found to be incomplete or inaccurate after processing
has begun, or if additional information from NCDOT is necessary to adequately
assess the project, the permitting agency(ies) that have permit processing
deadlines may place an application on hold. NCDOT may also request in writing
that its permit application be placed on hold at any time. If the permit application
is placed on hold by the permitting agency(ies), the processing shall be resumed
upon receipt of the necessary changes or necessary information from NCDOT. If
NCDOT requested that the permit application be placed on hold, the processing
shall be resumed upon receipt of a written request from NCDOT to resume
processing.
During the permit application review and processing period, additional
discussions and/or meetings may be conducted between NCDOT and the
environmental agency(ies) to resolve any outstanding issues. The goal of the
Merger 01 Process, however, is to resolve all of these issues before the permit
application is submitted to prevent delays in the construction letting.
35. Agency Public Notice if Required
If required by law or otherwise determined to be appropriate, the permitting
agency(ies) will issue a Public Notice requesting comments from the public on
the permit application. For example, the USACE is required to issue a Public
Notice for any project that requires an Individual Permit. The USACE Public
Notice is normally issued for a 30-day review and comment period. In such a
case, the Public Notice would have been issued after the Draft EIS or EA and
prior to Concurrence Point 3. However, if, in the opinion of the USACE, an additional Public Notice is
warranted due to changes in the project or new information, a second Public
Notice will be issued. NCDCM is required to issue a 30-day Public Notice after a
permit application is accepted as complete for any project that requires a CAMA
Major Permit. NCDWQ generally is not required to issue a separate Public
Notice.
36. Permit Decision
After the relevant permitting agency(ies) have reviewed the permit application(s)
for compliance, and comments have been received and properly considered from
the public, as well as relevant state and federal review agencies, a permit
decision will be made. The permit decision may be in the form of an approval,
approval with conditions or denial. If a permit is issued, it will typically list specific
conditions or restrictions on the development. The project must be constructed
according to the permit conditions. A permit decision may be in the form of a
denial if the outstanding issues have not been resolved satisfactorily. A permit
denial is very unlikely for projects that follow the Merger 01 Process provided that
the full Project Team has reached concurrence at each concurrence point.
After a permit decision is made by a state permitting agency, then the state
agency decision can be appealed by NCDOT or by a third party. If this occurs,
then the state permitting agency(ies) will respond according to their specific
requirements.
37. Changes to the Project’s Design, Construction Methodology or Construction Timeframe
If changes to the project’s design, construction methodology or construction
timeframe are needed at any time, additional coordination with the relevant
environmental agency(ies) will be required. This includes the agencies that have
permit authority over the project, as well as any other agencies that implement
federal, state and local environmental statutes and regulations that apply to the
project. If changes occur after the permit decisions are made, these changes
may require the submittal of a request for a modification, amendment, Letter of
Refinement or renewal to the relevant permit(s). A primary goal of the Merger
01 Process is to greatly reduce, and eliminate if possible, the number of changes
that may require additional coordination with the environmental agency (ies) after
the original permits are issued. Permit modifications, in particular, are very timeconsuming
and problematic for all concerned parties due to the relatively short
timeframe required for resolution.
It is the responsibility of NCDOT to conduct any additional coordination that may
be required with the relevant environmental agency(ies). Coordination with the
relevant environmental agencies, including the submittal of any required permit
modification requests, should occur at least 2-3 months before the work in
question must be conducted to allow adequate time for processing. When reviewing the request, the relevant environmental agency(ies) may
request additional information before making a decision. The decision may be in
the form of an approval, approval with conditions or denial.
38. Final Plans for the Project
During the course of the right of way acquisition, the design engineers will begin
to develop the final plans for the project. The final design is a very detailed
design that also includes computing and summarizing contract quantities
required for the project, incorporating right of way revisions, compiling plans from
various units (Traffic Engineering Branch, Roadside Environmental Unit, Utilities
Section, etc.) and incorporating them in the project. After receiving all necessary
permits, NCDOT will make sure that all environmental commitments and permit
conditions are incorporated. NCDOT will ensure that construction drawings
match the permit plan drawings and permit conditions, including any permit
modifications.
39. Let Project
The project is advertised so that all interested contractors can bid on the project.
The bids are opened on the project letting date. After receiving bids, the project
is considered for award by the NCDOT Board of Transportation. The Board then
usually awards the contract to the low bidder and construction will usually start
approximately 45 days after the contract is awarded. The contractor will be
bound to the permit conditions and any environmental commitments that were
developed during the NEPA and/or NCEPA environmental documentation.
40. Preconstruction Meeting
After the contract is awarded, and prior to the initiation of construction, NCDOT
and the Contractor will hold a preconstruction meeting. NCDOT will provide all
Project Team members with a copy of the final plans at least 2 weeks prior to the
preconstruction meeting along with a description of any changes that have been
made to the project’s design, construction methodology or construction
timeframe. The purpose of this meeting is to review the final plans and the
contents of the bid package, including any permit conditions and environmental
commitments. The preconstruction meeting will be scheduled for a time when
the USACE, NCDWQ and NCDCM (if a CAMA major permit was issued) can
attend. All of the Project Team members will be invited to the preconstruction
meeting with a minimum of thirty (30) days notice.
41. Compliance Monitoring
The NCDOT Division Engineer will ensure that all permits, permit conditions and
associated documents are readily available on site at all times. The Division
Engineer is responsible for ensuring that all federal, state, and local
environmental statutes and regulations are adhered to after the project is let,
including any permit conditions, and environmental commitments.
The Division Environmental Officer will provide assistance to the Division
Engineer in meeting these requirements. Representatives from USACE,
NCDCM, NCDWQ and other environmental agencies may visit the project site,
including any disposal or borrow areas, at any time to conduct compliance
inspections.
42. Project Completion
All work, including compliance with environmental conditions, must be completed
prior to the expiration date of the permits. If necessary, a permit renewal may be
requested. The decision to renew a permit may be in the form of an approval,
approval with conditions or denial depending upon the relevant agency(ies)
specific requirements. Renewal (extension) of permits must occur before the
permits expire.
Upon completion of all work approved within the 401 Water Quality Certification
or applicable Buffer Rules, and any subsequent modifications, NCDOT will return
the Certificate of Completion to the NCDWQ 401/Wetlands Unit after obtaining
the Division Engineer’s signature.
Upon completion of all work, the Division Engineer and Division Environmental
Officer will sign and return the USACE compliance form to the USACE.
Permitting Process for Phased New Location Projects
Many project corridor lengths are broken into a number of project segments and
are funded at different timeframes for right of way acquisition and construction.
Therefore, right of way plan preparation and final plan preparation occur at
various timeframes depending upon the project segment’s schedule.
For a project that has multiple project segments, the following process will occur:
the NEPA document will be written for the entire project corridor length (Steps 1-
26). At the time of the Draft EIS or EA issuance, the NCDOT will submit a
Section 404 application for the entire project corridor. The application will also
include the plan for how compensatory mitigation will be addressed for the entire
project (Step 32). An approved compensatory mitigation plan must be provided
for the entire project before any project segment is permitted. Following the
submittal of the application, the steps in the process that extend to the issuance
of the FONSI or ROD (whichever is applicable) and the public information
meeting will be completed for the entire project corridor length and Concurrence
Point 4A will be achieved for the entire project corridor length.
The development of right of way plans on through to the project letting and
construction (Steps 27-42) will begin for the project segment(s) that are
imminently scheduled for right of way acquisition and letting. At the time the right
of way plans are completed, an updated permit application will be submitted that
will include right of way plans for the projects segment(s) that are imminently
scheduled for right of way acquisition and letting. Preliminary designs will be
submitted with the permit application for the remaining project segments that are
scheduled for later years. The permitting agencies will then take final action on
the permit application for all project segments. Any permits that are issued will
have conditions that a final design will have to be submitted and written approval
and/or permit modification obtained from the USACE and NCDENR before
construction can begin on those project segments where only preliminary design
was submitted with the application.
As the right of way and letting date draws near for the remaining project
segment(s), the development of right of way plans and the completion of steps
that lead to the project letting and construction (Steps 27-42) will be completed
for each project segment(s). At the time the right of way plans for the remaining
project segment(s) are completed, a request for a permit modification will be
submitted for those project segment(s). This request will contain the final design
information for the project segment(s). Prior to providing written approval and/or
permit modification, the USACE and NCDENR, in coordination with the Project
Team, will ensure that all appropriate avoidance and minimization measures
have been incorporated in the project design. NCDOT
|