Process II – Widening and Other Improvement Projects
General
Project Team Meetings
Step by Step Implementation Procedures
Initiation of Project Study
Data Collection
Environmental Features Map
Develop Purpose and Need
Develop Project Team
Project Scoping
Hold Citizens Informational Workshop
Request Environmental Input and Preliminary Mapping
Concurrence Point 1 - Purpose and Need and Study Area Defined
Environmental Analysis
Notice of Intent (When Applicable)
Develop Design Options
Concurrence Point 2 – Design Options for Detailed Study
Preliminary Design of Detailed Study Alternatives
Concurrence Point 2A – Bridging Decisions and Final Alternatives to Carry Forward
Prepare Draft EIS/EA, Conceptual Mitigation Proposal and Section 404 Application
Issue DEIS/EA and Submit Section 404 Application
Notice of Availability and Section 404 Public Notice
Design Public Hearing
Agency and Public Comment Period
Post Hearing Meeting
Concurrence Point 3 – LEDPA/Preferred Alternative Selection
Concurrence Point 4A – Avoidance and Minimization
Prepare Final EIS or FONSI
Issue Final EIS or FONSI
Agency and Public Comment Period
Prepare and Issue ROD (EIS Projects)
Development of Right of Way Plans
Concurrence Point 4B – 30 Percent Hydraulic Review
Complete Right of Way Plans for the Project
NCDCM On-Site Pre-Application Meeting
Concurrence Point 4C – Permit Drawings Review
Compensatory Mitigation Requirements
Submit Permit Application(s)
Permit Application Review & Processing
Agency Public Notice if Required
Permit Decision
Changes to the Project’s Design, Construction Methodology or Construction Timeframe
Complete Final Plans for the Project
Let Project
Preconstruction Meeting
Compliance Monitoring
Project Completion
Permitting Process for Phased Widening Projects
General
A process flow chart that outlines the Section 404/NEPA Merger 01 Process
(Merger 01 Process) for widening projects is attached (Process II). This flow
chart depicts the major milestones in the process but it does not include all of the
many activities that NCDOT must complete in the project development process.
These other activities will be completed by NCDOT and input provided into the
merger process at the appropriate time. For example, public involvement is a
critical component of the project development activities and will be ongoing
throughout the process. Information developed through public involvement will
be made available to Project Team members for consideration in the decision
making process.
Project Team Meetings
Team meetings will be held at each of the concurrence points in the Process.
The Project Teams may hold additional meetings as determined necessary.
NCDOT’s Project Development Engineer should coordinate closely with the
appropriate USACE, FHWA, and NCDENR team members in scheduling any
meetings and clearly defining the purpose of the upcoming meeting. The Project
Development Engineer or Hydraulics Project Engineer will send the package of
information for the meeting to team members so that they will have it in hand at
least two weeks prior to the meeting. The transmittal to each team member
should clearly state the purpose and objective of the meeting. This will allow
team members time to review the information and be prepared to discuss any
issues or concerns they have at the meeting. Appendix A provides guidance on
information to be presented at each concurrence meeting.
At the end of each meeting, the Project Development Engineer or Hydraulics
Project Engineer, with the team’s help, should summarize the results of the
meeting, including agreements or concurrence points achieved. If agreement or
concurrence is not obtained the next steps or action should be clearly identified.
If additional information or action is required, the type of information or action
needed and the responsible agency(s) or team member(s) should be clearly
noted.
The Project Development Engineer is responsible for preparing a summary of all
meetings for distribution to all team members, except the summary for the 4B
and 4C Concurrence Meetings, which will be completed by the Hydraulics Project
Engineer. Each team member will read the meeting summary that includes
issues agreed upon, outstanding issues, and action statements (next steps)
carefully to ensure accuracy of the project records. Substantive errors and
omissions will be identified and provided within 30 days to the Project
Development Engineer or Hydraulics Project Engineer for prompt resolution.
On-site project field reviews can be very beneficial in helping to understand a
project’s purpose and need, human and natural environmental features and
alternative analysis. Project Teams are encouraged to hold combined field
reviews/meetings as needed to assist in the decision making process.
Step-by-Step Implementation Procedures
The following discussion is intended to provide more detailed guidance and
explanation on the various steps and concurrence points in the attached flow
chart. The numbered paragraphs correspond to steps or blocks in the chart.
1. Initiation of Project Study
NCDOT will begin the project study by gathering background data and
information and sending out the project scoping letter and/or start of study letter.
This letter initiates the project’s concept and solicits input from federal and state
agencies (including the State Clearinghouse), local government agencies, the
public, and other NCDOT units and branches. The level of detail provided in
these letters includes a TIP description and a vicinity map.
2. Data Collection
The Project Development Engineer will collect all available information, including
aerial photography (digital mosaic), and background data, needed to hold the
project scoping meeting, as identified by responses to the scoping letter and
standard requirements.
3. Environmental Features Map
NCDOT - with consultation from the agencies - will develop an environmental
features map illustrating resource areas of concern as well as topographic or
photogrammetric mapping. The purpose of this mapping is to provide a means
for identifying alternatives that warrant study on a screening level basis. This
mapping could also be used by the team to gauge the applicability of the Merger
01 Process. Such features on the mapping will include but are not limited to:
- Infrastructure and topography
- Community features (i.e., boundaries, schools, churches, community centers, hospitals, transit dependent populations, demographics, etc.
- Floodplains
- Historic properties and possible areas of archaeological concern
- Wetlands, streams, buffers, river basins, and water supply watersheds (GIS level information)
- Wildlife refuges and game lands
- Recreational areas and parks
- Hazardous material sites
- Existing land use map and locally adopted land use plan
- Threatened and Endangered Species information
- Significant Natural Heritage Program Areas
- Utilities within project study area using best available information
Based on the environmental features map, the study area may be re-confirmed.
Generally, the study area will not be redefined unless new information
necessitates re-evaluation.
4. Develop Purpose and Need
Transportation Planning provides a Planning Level Purpose and Need for each
project that was developed during the system planning process to the Project
Development Engineer. In cases where Transportation Planning does not have
personnel assigned to a particular area, the Project Development Engineer will
develop the Purpose and Need (P & N). Also, additional engineering and
environmental inventory data may be obtained for use in further developing and
refining the purpose and need for a project. The type of information and level of
detail collected must be determined for each project and could include
information such as the following:
- Preliminary limits of the study area
- Existing traffic and future no-build average daily traffic
- Roadway geometric deficiencies and accident history
- Transportation plans
- Land use plans
- Areas of interest to local citizens and elected officials
- Legislative mandates
- Economic initiatives
- Intermodal relationships, including bicycle/pedestrian systems, transit (rail and bus), port facilities and airport facilities
- Project history and background information including feasibility studies and community issues
- Highway Needs Inventory (HNI) status
- MPO Constrained Long Range Plan status
- Major Investment Study (MIS) status/information
- GIS Mapping
- Aerial Photography
- Available Mapping with Delineated Jurisdictional Areas
- Traffic Study and Capacity Analysis
5. Develop Project Team
The Project Development Engineer will consult with the appropriate USACE,
NCDENR and FHWA representatives to identify specific Project Team members.
NCDOT will provide written verification of team members to all the team
members prior to Step 9 (Concurrence Point 1). If an agency declines to
participate on the team, its decision will be documented in writing to NCDOT,
NCDENR, USACE and FHWA. If an agency drops from the Project Team during
the process, its self-removal will also be documented in writing.
6. Project Scoping
The Project Scoping Meeting is held by NCDOT to discuss background data,
preliminary purpose and need, engineering, environmental inventories, the
proposed scope of the project, and potential substantial project issues.
Resource agencies will be invited to attend and provide input. Agencies should
provide written input in response to the scoping letter or attend the scoping
meeting.
At the project scoping meeting, NCDOT will provide the proposed project
schedule. The meeting attendees will present any issues that may impact the
proposed schedule. Revisions to the proposed schedule will be made, as
necessary.
7. Hold Citizens Informational Workshop
After the project scoping meeting, citizens’ informational workshop will be held to
introduce the project to the public. The general scope of the project work will be
discussed with the public. Also, the public will be informed that NCDOT and
agency staff will begin work in the project vicinity to gain the necessary survey
and environmental information to proceed with the development of the NEPA
document.
8. Request Environmental Input and Preliminary Mapping
After the Citizens Information Workshop, the PDEA engineer will request
environmental input from PDEA’s Office of Natural Environment and Office of
Human Environment or a private engineering firm, using available mapping and
request forms. A study corridor should be developed which would encompass
the worst case-widening scenario on both sides of the existing facility.
The Design Engineer, in coordination with the PDEA Project Development
Engineer, will request either preliminary plan sheet mapping or final surveys and
base plan sheets so the plan sheets and environmental delineations will be
available at the Concurrence Point 2 meeting. It should be noted that final
surveys will normally be requested for short projects (usually about 5 miles or
less in length) that are to be constructed in one project segment. Preliminary
plan sheet mapping will normally be requested for projects that are long (greater
than 5 miles) and have multiple project segments.
9. Concurrence Point 1 - Purpose and Need and Study Area Defined
The Purpose and Need (P & N) Statement forms the basis for identification of
alternatives to be evaluated. Therefore, concurrence will be obtained on the
Purpose and Need before potential alternatives are identified. NCDOT will
prepare a draft Purpose and Need Statement, along with supporting technical
documentation. The P & N information package will be sent to team members
so that they will receive it at least two weeks prior to the team meeting. The
supporting technical information will include the environmental features map of
the study area and a summary of any information or comments from the public
concerning purpose and need and community concerns. This statement should
clearly demonstrate that a “need” exists and should define the “need” in terms
understandable to the general public. The statement should clearly describe the
problems that the proposed action is to correct.
A team meeting will be held to discuss the draft P & N Statement and Study Area
along with supporting data. Team members will review the information prior to
the meeting and be prepared to discuss any concerns. At the meeting, the
NCDOT Project Development Engineer will provide the environmental features
map of the Study Area. Also, any other readily available information will be
presented for the team’s information. It may be necessary to conduct more than one meeting on purpose and need if
additional information is needed. The goal of the meeting is for team members to
concur with and sign the Purpose and Need and Study Area Concurrence Form.
If concerns are raised at the team meeting, which require additional
documentation or revisions to the P & N Statement, the NCDOT will incorporate
the additions or revisions and redistribute the P and N Statement for concurrence
or comment. This will be done prior to the follow-up Concurrence Point I meeting
or as soon as possible if it is determined that a second meeting is not required.
Also, at this meeting, the Project Team should concur that the project’s purpose
can be accomplished by upgrading the existing highway corridor and that new
location alternatives will not be studied at this time. As the project progresses,
new environmental input and public comment could necessitate studying new
location alternatives. If, during the project study, NCDOT determines that new
location alternatives should be investigated, then the Merger 01 Process For
New Location Projects (Process 1) should be followed.
Once concurrence is obtained for Purpose and Need, the Team can address
Concurrence Point 2. Concurrence for both Concurrence Points 1 and 2 can be
obtained in one meeting, if possible. Refer to Step 13 – Concurrence Point 2, for
information needed for the Concurrence Point 2 meeting.
The NCDOT project manager may elect to delay the Concurrence Point 1
meeting until the environmental input has been collected, especially, if it is
unclear whether the project is a candidate for the Merger 01 Process.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
10. Environmental Analysis
The potentially impacted human and natural resources will be delineated for the
entire study corridor. NCDWQ wetland ratings and wetland type will be identified
and will include any CAMA wetland Areas of Environmental Concern. In
addition, where it is available, use NCDCM’s GIS wetland data to identify wetland
significance. An agency wetland and field review meeting will be held to:
- Verify jurisdictional wetland and stream boundaries. These boundaries will be
established to a level of detail sufficient for the purposes of project planning.
The USACE will provide written jurisdictional determinations.
- Review any potential wetland mitigation sites that may be noted during the
delineation effort and coordinate with EEP.
The field review meeting will be set up by PDEA’s Natural System Specialist.
11. Notice of Intent (When Applicable)
If NCDOT and FHWA determine an EIS should be prepared, a Notice of Intent
will be filed in the Federal Register. If it is not clear at this point that potential
project impacts warrant an EIS, the decision to prepare a Notice of Intent may be
delayed until more information is available. The preparation of an EIS is typically
unlikely for a widening project, which usually requires the preparation of an EA.
12. Develop Design Options
PDEA should coordinate with the Roadway Design Unit, Utilities Section, Traffic
Engineering (Congestion Management), the Division, and FHWA to determine
design options that meet the purpose of the project. Design options can include
typical section options (number of lanes, curb and gutter, shoulder, median
section, or 5 lane, etc.) and hydraulic structure requirements (bridge or culvert
and length of bridge).
13. Concurrence Point 2 – Design Options for Detailed Study
The intent of the Concurrence Point 2 meeting is to obtain consensus from the
Project Team on which design options will be fully evaluated as alternatives,
including the “no build” alternative, in the Environmental Assessment. The
alternatives selected must meet the Purpose and Need of the project, with the
exception of the “no build” alternative. If possible, the Concurrence Point 2
meeting will be held at the same time as the Concurrence Point 1 meeting.
Design options to consider include typical sections, hydraulic structures, potential
utility impacts, and widening scenarios.
Typical Section: The typical section components (number of lanes, lane width,
and shoulder treatment) should address the facility deficiencies as stated in the
Purpose and Need of the project. At the Concurrence Point 2 meeting, NCDOT
will present the typical section which best addresses the Purpose and Need of
the project. NCDOT should present information supporting the typical section
recommendation such as capacity analyses, AASHTO design standards, bicycle
and pedestrian needs, local government recommendations, utility
accommodations, development and environmental constraints, and traffic
flow/access concerns. After viewing the proposed typical section and supporting information, the team
will decide if additional typical section alternatives need to be studied and
compared at Concurrence Point 2A.
Widening Scenarios: At the Concurrence Point 2 meeting, team members should
provide guidance to NCDOT to aid in preparing a widening scenario which would
minimize impacts to the human and natural environment. The team should also
decide if alternative widening scenarios should be developed due to
environmental conflicts existing on both sides of the road. Based on information
received at this meeting, NCDOT will develop the designs for the widening
alternatives identified by the team to present at the Concurrence Point 2A
meeting for review and possible further refinement.
Hydraulic Structures: Based on available information, any potential need for
special bridging accommodations should be discussed at Concurrence Point 2.
The final bridging decisions will be made at Concurrence Point 2A. If there is a
discrepancy concerning the type of hydraulic structure to carry forward at the
Concurrence Point 2 meeting, NCDOT will prepare alternatives to be reviewed at
Concurrence Point 2A.
Information which should be presented at the Concurrence Point 2 meeting
includes: the environmental features map, environmental input obtained from the
Offices of Human and Natural Environment (requested in Step 6), local
government comments, public comments, traffic flow/access concerns, safety
concerns, and preliminary mapping. Delineated wetlands and streams will be
included on the environmental features map.
The NCDOT will request formal concurrence at this meeting by asking the team
members to sign the Concurrence Point 2 form which specifies the widening
scenarios and typical section alternatives which will be studied and compared at
Concurrence Point 2A. If additional documentation or revisions to the
alternatives are necessary, the NCDOT will incorporate the additions or revisions
and redistribute the information. If necessary, an additional team meeting will be
scheduled to resolve outstanding concerns.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
14. Preliminary Design of Detailed Study Alternatives
After receipt of the delineations and necessary preliminary plan sheet mapping,
the Design Engineer will begin to develop the preliminary design for the best fit
alignment using the guidance provided at the Concurrence Point 2 meeting,
public input, potential utility impacts, local government input, and environmental
input. A preliminary design is a very specific design that includes horizontal and
vertical alignments, edge of pavements, slope stakes, turn lanes, superelevation,
and right of way limits.
If typical section, widening scenarios, or structural alternatives were identified at
Concurrence Point 2, the preliminary designs will be developed for these
alternatives also. The right of way, utility, and construction cost estimates will
also be obtained after completion of the preliminary designs. During the
development of the design, care will be taken to avoid impacts to the natural and
human environment, where practicable. The Design Engineer will coordinate the
preliminary design for each detailed study alternative with the Utilities Section.
The Utilities Section will identify areas where any known utilities are impacted.
Where it is not practicable to avoid impacts, minimization measures will be
employed.
After the preliminary designs are completed, impacts will be identified and
quantified. Upon completion of the preliminary designs, the PDEA Engineer will
prepare a Preliminary Alternatives Report. The report will identify the impacts
and costs associated with each design option. This report will be sent to the
merger team members for preparation of the Concurrence Point 2A meeting. At
this time, the preliminary designs will include any recommended control of
access that will be acquired for the project. (The control of access limits are
needed so they can be reflected in right of way estimates, shown to the public,
and for the Project Team’s review).
15. Concurrence Point 2A - Bridging Decisions and Final Alternatives to Carry Forward
The purpose of this meeting will be for the team to concur on the alignment
refinement, alternatives to carry forward, and bridging decisions. This
concurrence includes selecting the hydraulic structures to be carried forward, as
well as which typical sections and widening scenarios to carry forward.
Information to be presented at this meeting include the preliminary design
alternatives, GPS wetlands and streams overlaid on the preliminary designs,
bridge and culvert alternative designs (if alternatives were identified at
Concurrence Point 2), typical section alternative designs (if alternatives were
identified at Concurrence Point 2), comparison of impacts (wetlands, streams,
Section 4(f) resources, historic properties, CAMA AEC’s, relocatees, potential
utility impacts, etc.) among all alternatives that were identified at Concurrence Point 2.
Using the hydraulic recommendations and all available environmental
information, the Project Team will determine the placement and length of bridges.
In addition, a review will be made to determine which natural resources warrant
additional avoidance measures. The bridge locations and approximate lengths
will be identified on each alternative.
The team will decide if typical section and widening alternatives identified at
Concurrence Point 2 need to be carried forward or if some alternatives can be
eliminated. Any alternative that does not receive concurrence to be eliminated
will be carried forward in the EA and at the public hearing. If appropriate, only
one alignment design may be carried forward through the EA and public hearing.
During the Concurrence Point 2A meeting, the Project Team will discuss which
federal, state, and local environmental statutes and regulations may apply to
each of the detailed study alternatives. Within NCDOT, the Office of the Natural
Environment (ONE) is responsible for ensuring that the specific required steps
are followed for each of the environmental permits, certifications, consultations,
reviews and determinations that may be required throughout the project’s life.
The Hydraulics Unit will ensure that FEMA flood insurance program regulations
are followed where applicable.
All team members will be asked to sign a Concurrence Form at the meeting to
signify that they agree with the bridge locations and approximate lengths,
alternatives eliminated, and refined alternatives. After the bridge locations and
alternative refinements are determined, an updated construction cost estimate
and summary of impacts for each remaining alternative will be developed. This
information will be provided for each alternative carried forward in the
Environmental Assessment.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
16. Prepare Draft EIS/EA, Conceptual Mitigation Proposal and Section 404 Application
The environmental document will be completed according to NEPA and an
identification of impacts will be made for each of the alternatives that are studied
in detail. There will be a discussion of why preliminary alternatives were
eliminated. NCDOT will address potential on-site compensatory mitigation options. For
potential on-site mitigation sites, NCDOT ONE will prepare a feasibility study that
includes an environmental evaluation that identifies historic resources,
threatened and endangered species, parks, community issues, etc. NCDOT
ONE may arrange an agency field meeting to review any potential on-site
mitigation opportunities, discuss the environmental evaluation results, and
determine which sites are acceptable to the agencies.
Pursuant to the Memorandum of Agreement among the NCDOT, NCDENR, and
USACE signed July 22, 2002, the Ecosystem Enhancement Program (EEP) will
provide all compensatory mitigation that is not satisfied by acceptable on-site
mitigation.
Preliminary determinations about the Federal, state, and local environmental
statutes and regulations that may apply to each of the detailed study alternatives
will be included within the environmental document. If the project is within a
CAMA county(ies), then potentially relevant CAMA land use plan policies that
may apply to each detailed study alternative will also be included within the draft
environmental document.
All information produced in previous studies will be incorporated in an
environmental document.
The FHWA and NCDOT will review the preliminary environmental document for
adequacy as it relates to NEPA requirements. NCDOT will revise the
environmental document based on these comments or consult further with
FHWA to resolve issues.
The NEPA document shall develop an analysis of secondary/indirect and
cumulative impacts of sufficient scope and detail to fulfill all NEPA requirements.
In addition, the analysis should be developed, in concurrence with current
policies and procedures, to a level of detail sufficient to make decisions required
by all other state and Federal laws, statutes, rules, and regulations.
17. Issue DEIS/EA and Submit Section 404 Application
NCDOT and FHWA will sign the title page of the environmental document (DEIS
or EA) prior to NCDOT circulating it. NCDOT will submit the Section 404 permit
application to the USACE at the time of document approval. NCDOT will also
provide the USACE with a mailing list developed in the public involvement
process that includes adjacent property owners and mailing labels. The
environmental document will be distributed to federal agencies, State
Clearinghouse, and local agencies and organizations for review and comment.
After issuance of the environmental document, an interagency field review will be
made unless the Project Team determines otherwise. The purpose of this
meeting is for team members to review alternatives in the field prior to the
Concurrence Point 3 meeting; however, it may not be necessary if team
members have reviewed alternatives in the field previously.
18. Notice of Availability and Section 404 Public Notice
The USACE will issue the Section 404 Public Notice. The environmental
document and Public Notice are made available for public and agency comment
for the prescribed time frames. NCDOT should consult with the USACE, NCDOT
Board Members, and other interested parties to set the public hearing date.
Once the date is set, the Corps should be immediately notified of the location,
time and place. NCDOT will publicize the public hearing.
19. Design Public Hearing
NCDOT will hold the Design Public Hearing. Team members are encouraged to
attend the public hearing to fully understand the public concerns. The USACE
and other team members will be invited to attend the public hearing.
20. Agency and Public Comment Period
The public may submit written comments to NCDOT, FHWA and/or the USACE
after the public hearing. Also, agency and public comments on the
environmental document and the Section 404 Public Notice may be submitted to
NCDOT and the USACE, respectively. The agencies will format their letters to
identify which comments are pertinent to the selection of the Least
Environmentally Damaging Practicable Alternative (LEDPA)/Preferred
Alternative. NCDOT will adequately address those specific comments prior to
selection of the LEDPA/Preferred Alternative and distribute their responses within
the information material for the Concurrence Point 3 meeting.
21. Post Hearing Meeting
Following the comment periods, NCDOT will review and summarize the
comments received from the document review and public hearing process. The
USACE will forward the comments on the Section 404 Public Notice for inclusion
in the summary. NCDOT will then hold a post hearing meeting. Project Team
members are invited to attend this meeting. The purpose of this meeting is to
evaluate all substantive comments received and determine if any additional
studies or changes are needed to properly address issues that have been raised.
Any additional work or studies to resolve comments will be completed by
NCDOT. All agency comments on the environmental document and Section 404
Public Notice that affect the selection of the LEDPA/Preferred Alternative will be
addressed and appropriate information or responses prepared prior to the
Concurrence Point 3 meeting.
22. Concurrence Point 3 – LEDPA/Preferred Alternative Selection
A Project Team meeting will be held to determine the Least Environmentally
Damaging Practicable Alternative (LEDPA) [Preferred Alternative under NEPA].
The Project Development Engineer will send the package of information for the
meeting to Project Team members so they will have it in hand at least two weeks
prior to the meeting. The package will include a matrix (for example, summary
information from DEIS) illustrating a comparison of impacts for the detailed study
alternatives and a brief summary of previous Project Team decisions. The
package will also include a summary of substantive comments received from
agencies and the public and how these comments were addressed.
When all substantive comments submitted by the agencies during the
environmental document review and the public hearing/public notice commenting
period have been adequately addressed and no new issues have been identified,
the Project Team will select a LEDPA/Preferred Alternative. At the time it is
selected, Project Team members will be reasonably certain that the
LEDPA/Preferred Alternative will comply with all relevant regulations and permit
requirements, is safe, and can be authorized. Project Team members in
agreement with the LEDPA/Preferred Alternative will provide their formal
concurrence at this meeting by signing the Concurrence Point 3 Form.
During the Concurrence Point 3 meeting, the Project Team will confirm the
preliminary determination made during the Concurrence Point 2A meeting about
the federal, state, and local environmental statutes and regulations that may
apply to the LEDPA/Preferred Alternative. This confirmation is required due to
changes that may have occurred in the project design and/or in the statutes and
regulations since the preliminary determination was made during the
Concurrence Point 2A meeting. Within NCDOT, the Office of the Natural
Environment (ONE) is responsible for ensuring that the specific required steps
are followed for each of the environmental permits, certifications, consultations,
reviews and determinations that may be required throughout the project’s life.
The Hydraulics Unit will ensure that FEMA flood insurance regulations are
followed where appropriate.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
The public will be notified, by the NCDOT, of the selection of the
LEDPA/Preferred Alternative via newsletter, news release or other means
determined satisfactory by NCDOT policy.
23. Concurrence Point 4A – Avoidance and Minimization
Following selection of the LEDPA/Preferred Alternative, a Project Team meeting
will be held to discuss additional avoidance and minimization efforts not included
in the preliminary design during the alternative analysis phase of the project.
This concurrence point should address issues such as minor alignment shifts,
horizontal and vertical alignment, slopes, potential utility conflicts and impacts,
and construction techniques. For projects where bridge length and location
were not previously agreed to, a decision on these parameters will be included in
the Concurrence Point 4A meeting. Upon agreement that project jurisdictional
impacts have been avoided and minimized to the maximum extent practicable
based on current information and design available at that time, the Project Team
members will sign the Concurrence Point 4A Form. When avoiding and
minimizing jurisdictional resource impacts, other resources will be considered.
It should be recognized that additional minimization may be achieved during the
final design process with more precise mapping, including the project hydraulic
design (Concurrence Point 4B and 4C), and utility relocation design. Upon
reaching this concurrence point, the project development engineer will document
all avoidance and minimization that has been achieved to this point in project
development. This information will be provided to the Project Team and to the
Office of Natural Environment for inclusion in the updated permit application.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
24. Prepare Final EIS or FONSI
NCDOT/FHWA will prepare the Final EIS or FONSI. The Final EIS will discuss
the rationale behind the selection of the LEDPA/Preferred Alternative. It is not
necessary to complete Concurrence Point 4A prior to the completion of the Final
EIS or FONSI. However, any additional avoidance and minimization measures
that have been identified or incorporated up to that point in the project
development should be included in the Final EIS or FONSI. The FHWA and
NCDOT will review the final environmental document for adequacy as it relates to
NEPA requirements. NCDOT will revise the environmental document based on
these comments or consult further with the FHWA to resolve issues. The Final
EIS or FONSI will include all environmental commitments and the mitigation plan
to address all resources requiring mitigation, such as wetlands, streams, Section
106, Section 4(f), public access, etc.
Preliminary determinations about the federal, state, and local environmental
statutes and regulations that may apply to the LEDPA/Preferred Alternative will
be included within the final environmental document. If the project is within a CAMA county (ies), then potentially relevant CAMA land
use plan policies that may apply to the LEDPA/Preferred Alternative will also be
included within the final environmental document.
25. Issue Final EIS or FONSI
NCDOT and FHWA will sign the title page of the Final EIS or FONSI prior to
NCDOT circulating it. The environmental document will be distributed to federal
agencies, State Clearinghouse, and local agencies and organizations for review
and comment.
26. Agency and Public Comment Period
The agencies and the public may submit written comments to NCDOT and
FHWA concerning the Final EIS or FONSI. NCDOT will respond directly to the
commenting agencies concerning comments received on a FONSI. Comments
received on a FEIS will be addressed in the ROD with copies provided to the
commenting agency.
27. Prepare and Issue ROD (For EIS Projects Only)
FHWA will issue the ROD. The ROD will address any comments received on the
FEIS. A Notice of Availability will be issued.
(For phased projects, refer to the text at the end of this document)
28. Development of Right of Way Plans
After achieving Concurrence Points 3 and 4A, the Design Engineer will request
final surveys (plan sheet mapping) if necessary to develop the right of way plans
for the project. The design will be based on the alignment as agreed to at
Concurrence Point 4A and will incorporate all agreed upon commitments
contained in the FONSI or ROD. After the design engineers complete the
horizontal and vertical alignment for the roadway, the Utilities Section will review
the horizontal and vertical alignment for the roadway and will begin to coordinate
with the Hydraulics Unit regarding the utility locations. The Hydraulics Unit
begins the development of the proposed drainage design and the Geotechnical
Engineering Unit begins the detailed geotechnical investigations for the project.
29. Concurrence Point 4B – 30 Percent Hydraulic Review
At the time the hydraulic design for the project is 30 percent complete, the
Hydraulics Project Engineer will hold a Concurrence Point 4B meeting to review
the development of the drainage design. All appropriate Project Team members
should attend (USACE and NCDWQ attendance is mandatory. If the project is
within a CAMA county (ies), NCDCM attendance is mandatory).
If a project requires a State Stormwater Management Permit, the Hydraulics
Project Engineer will work with the NCDWQ Stormwater Management Section to
obtain the permit and report its progress to the team members. The Hydraulics
Project Engineer will provide the package of information to team members so
that they receive it two weeks in advance of the meeting.
Also, before the Concurrence Point 4B meeting is held, the Hydraulics Project
Engineer will consult with the ONE staff to ensure that the environmental surveys
(wetlands, threatened and endangered species, streams, and buffer) for each
project is complete and current.
At the 4B meeting, the Hydraulics Project Engineer will present preliminary
drainage designs to the team members. The drainage plans will depict the
boundaries of the affected environmental areas (wetlands, perennial and
intermittent streams, buffers, CAMA AEC’s, etc.), existing draining structures,
layout of proposed drainage structures, and stormwater best management
devices. Large structures such as bridges and box culverts will also be
discussed.
The Utilities Section will coordinate the determination of the utility conflicts and
the development of the utility relocation preliminary designs with the utility
owners and the design engineers. Concurrence will include selecting the
hydraulic structures to be used at each stream crossing.
The Hydraulics Project Engineer will take notes of comments received during the
meeting. The Hydraulics Project Engineer will distribute meeting minutes, which
will include how comments will be addressed. Also, the meeting minutes will
identify onsite mitigation opportunities that will be incorporated into the project
design as appropriate. Any other mitigation identified that was not included in the
final environmental document will be included.
It is understood minor vertical changes may be needed due to hydraulic needs.
If vertical changes occur that result in additional environmental impacts, minor
horizontal adjustments in alignment may be appropriate.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
30. Complete Right of Way Plans for the Project
Upon receiving the completed hydraulic design for the project, Design Engineers
will incorporate the hydraulic design and establish the proposed right of way
limits for the project. The Structure Design Engineers begin to develop the designs for bridges and
culverts.
The project is then reviewed with Construction and Right of Way Personnel to
note any additional changes that may be required. The right of way plans are
completed and sent to the Right of Way Branch to begin purchase of land
required for the project.
31. NCDCM On-Site Pre-Application Meeting
For projects within a CAMA county(ies) that require a CAMA major permit, the
NCDOT ONE Permit Specialist will request an on-site pre-application meeting
with the appropriate NCDCM Field Representative. The purpose of this meeting
is to review the plans and/or permit drawings and information that will be
submitted with the CAMA permit application. This will ensure that, when the
CAMA major permit application is formally submitted, it contains all of the
information necessary for processing. The purpose of this meeting is not to
make changes to the project design, construction methodology or construction
timeframe. However, if any potential changes to the project are identified at the
on-site pre-application meeting, they will be discussed with the full Project Team
at the Concurrence Point 4C meeting prior to approval.
32. Concurrence Point 4C - Permit Drawings Review
At the time the hydraulic design is 100 percent complete and the permit drawings
for the project are finalized, the Hydraulics Unit will hold a 4C meeting. At the
4C meeting, the Hydraulics Project Engineer will present copies of the
Stormwater Management Plan to the Project Team members. A Stormwater
Management Plan is a narrative, project-specific, Stormwater Design Report. It
outlines project involvement, river basins, classifications of the involved water
bodies, selected structural and non-structural best management practices, best
management practice devices, and major structures (bridges and box culverts).
The final permit drawings for the permit application will also be reviewed and
revised based on comments received at this meeting. Any area where utility
relocations affect additional environmental resources beyond the footprint of the
roadway will be shown on the permit drawings and will be included in the impacts
presented in the application. In addition, if the project is within a CAMA
county(ies) and a CAMA Major Permit is required, then all utility locations that are
not included in the permit drawings will be described within the CAMA Major
Permit application either in narrative form or in a separate spreadsheet. The
level of detail of utility relocation information required with the CAMA Major
Permit application will be determined on a project-by-project basis at the NCDCM
on-site pre-application meeting.
The Hydraulics Project Engineer will record minutes of the meeting and will
address the team’s comments. Changes will be made based on the team’s
comments. The changes will be made in the permit drawings before the permit
application is sent. The Concurrence form indicates that the Project Team
agrees that the drawings as presented are satisfactory to be submitted with the
application. (This does not supercede the regulatory review process.)
After the changes are incorporated, the Hydraulics Project Engineer will ask for a
signature of the Concurrence Point 4C Form. The Concurrence Form will be
detailed enough to document and identify changes. Any changes to impacts to
wetlands, streams, buffers, or CAMA AEC’s that occur after the 4C document is
signed will require the resource agencies to revisit the design, and may require a
new 4C meeting. The NCDOT Permit Specialist will contact the agencies via email,
letter, phone call or scheduling a meeting as appropriate to facilitate review
of these changes.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
33. Compensatory Mitigation Requirements
Compensatory mitigation requirements will be identified based on final project
impacts.
In those events where on-site mitigation opportunities are available and
determined acceptable and/or necessary by the Project Team, the mitigation plan
and design will be developed in concert with the overall project design. Removal
of existing causeway fills is strongly encouraged to offset project impacts and/or
create mitigation credits for future project impacts. The on-site mitigation will be
developed and implemented by NCDOT in collaboration with the Project Team
and EEP. Under no circumstances will the project be permitted until such time
that the detailed on-site mitigation plan is complete and approved by the
permitting agencies.
Pursuant to the Memorandum of Agreement among the NCDOT, NCDENR, and
USACE, signed July 22, 2002, the Ecosystem Enhancement Program (EEP) will
provide all compensatory mitigation that is not satisfied by acceptable on-site
mitigation.
34. Submit Permit Application(s)
The Office of Natural Environment Permit Specialist submits updated permit
application(s) as appropriate to all of the agencies for which permits are required.
Permit application(s) will be submitted within two months of the 4C meeting. The
permit application package will vary according to each agencies specific
requirements.
35. Permit Application Review and Processing
Upon receiving the permit application from NCDOT, the permitting agency(ies)
will review the application for completeness. If the permit application is
determined to be incomplete, the permitting agency(ies) will return the application
to NCDOT for additional information, and/or inform NCDOT of the additional
information that is required.
After the permitting agency(ies) determine that the permit application is complete,
the permitting agency(ies) will assemble and distribute the application package
for comment to any designated review agencies. This process varies according
to the permit being requested.
If the permit application is found to be incomplete or inaccurate after processing
has begun, or if additional information from NCDOT is necessary to adequately
assess the project, the permitting agency(ies) that have permit processing
deadlines may place an application on hold. NCDOT may also request in writing
that its permit application be placed on hold at any time. If the permit application
is placed on hold by the permitting agency(ies), the processing shall be resumed
upon receipt of the necessary changes or necessary information from NCDOT. If
NCDOT requested that the permit application be placed on hold, the processing
shall be resumed upon receipt of a written request from NCDOT to resume
processing.
During the permit application review and processing period, additional
discussions and/or meetings may be conducted between NCDOT and the
environmental agency(ies) to resolve any outstanding issues. The goal of the
Merger 01 Process, however, is to resolve all of these issues before the permit
application is submitted to prevent delays in the construction letting.
36. Agency Public Notice if Required
If required by law or otherwise determined to be appropriate, the permitting
agency(ies) will issue a Public Notice requesting comments from the public on
the permit application. For example, the USACE is required to issue a Public
Notice for any project that requires an Individual Permit. The USACE Public
Notice is normally issued for a 30-day review and comment period. In such a
case, the Public Notice would have been issued after the Draft EIS or EA and
prior to Concurrence Point 3. However, if, in the opinion of the USACE, an additional Public Notice is
warranted due to changes in the project or new information, a second Public
Notice will be issued. NCDCM is required to issue a 30-day Public Notice after a
permit application is accepted as complete for any project that requires a CAMA
Major Permit. NCDWQ generally is not required to issue a separate Public
Notice.
37. Permit Decision
After the relevant permitting agency (ies) have reviewed the permit application(s)
for compliance, and comments have been received and properly considered from
the public, as well as relevant state and federal review agencies, a permit
decision will be made. The permit decision may be in the form of an approval,
approval with conditions or denial. If a permit is issued, it will typically list specific
conditions or restrictions on the development. The project must be constructed
according to the permit conditions. A permit decision may be in the form of a
denial if the outstanding issues have not been resolved satisfactorily. A permit
denial is very unlikely for projects that follow the Merger 01 Process provided that
the full Project Team has reached concurrence at each concurrence point.
After a permit decision is made by a state permitting agency, the state agency
decision can be appealed by NCDOT or by a third party. If this occurs, then the
state permitting agency(ies) will respond according to their specific requirements.
38. Changes to the Project’s Design, Construction Methodology or Construction Timeframe
If changes to the project’s design, construction methodology or construction
timeframe are needed at any time, additional coordination with the relevant
environmental agency(ies) will be required. This includes the agencies that have
permit authority over the project, as well as any other agencies that implement
federal, state and local environmental statutes and regulations that apply to the
project. If changes occur after the permit decisions are made, these changes
may require the submittal of a request for a modification, amendment, Letter of
Refinement or renewal to the relevant permit(s). A primary goal of the Merger
01 Process is to greatly reduce, and eliminate if possible, the number of changes
that may require additional coordination with the environmental agency (ies) after
the original permits are issued. Permit modifications, in particular, are very timeconsuming
and problematic for all concerned parties due to the relatively short
timeframe required for resolution.
It is the responsibility of NCDOT, not the Contractor, to conduct any additional
coordination that may be required with the relevant environmental agency(ies).
Coordination with the relevant environmental agencies, including the submittal of
any required permit modification requests, should occur at least 2-3 months
before the work in question must be conducted to allow adequate time for
processing. When reviewing the request, the relevant environmental agency(ies) may request
additional information before making a decision. The decision may be in the form
of an approval, approval with conditions or denial.
39. Complete Final Plans for the Project
During the course of the right of way acquisition, the Design Engineers will begin
to develop the final plans for the project. The final design is a very detailed
design that also includes computing and summarizing the contract quantities
required for the project, incorporating right of way revisions, compiling plans from
various units (Traffic Engineering Branch, Roadside Environmental Unit, Utilities
Section, etc) and incorporating them in the project. NCDOT will make sure that
all environmental commitments and permit conditions are incorporated. NCDOT
will ensure that construction drawings match the permit plan drawings and permit
conditions, including any permit modifications.
40. Let Project
The project is advertised so that all interested contractors can bid on the project.
The bids are opened on the project letting date. After receiving bids, the project
is considered for award by the Board of Transportation. The Board then usually
awards the contract to the low bidder and construction will usually start
approximately 45 days after the contract is awarded. The contractor will be
bound to the permit conditions and any environmental commitments that were
developed during the NEPA and/or NCEPA environmental documentation.
41. Preconstruction Meeting
After the contract is awarded, and prior to the initiation of construction, NCDOT
and the Contractor will hold a preconstruction meeting. NCDOT will provide all
Project Team members with a copy of the final plans at least 2 weeks prior to the
preconstruction meeting along with a description of any changes that have been
made to the project’s design, construction methodology or construction
timeframe. The purpose of this meeting is to review the final plans and the
contents of the bid package, including any permit conditions, and environmental
commitments. The preconstruction meeting will be scheduled for a time when
the USACE, NCDWQ and NCDCM (if a CAMA major permit was issued) can
attend. All of the Project Team members will be invited to the preconstruction
meeting with a minimum of thirty (30) days’ notice.
42. Compliance Monitoring
The NCDOT Division Engineer will ensure that all permits, permit conditions and
associated documents are readily available on site at all times. The Division
Engineer is responsible for ensuring that all federal, state, and local
environmental statutes and regulations are adhered to after the project is let,
including any permit conditions and environmental commitments. The Division Environmental Officer will provide assistance to the Division
Engineer in meeting these requirements. Representatives from USACE,
NCDCM, NCDWQ and other environmental agencies may visit the project site,
including any disposal or borrow areas, at any time to conduct compliance
inspections.
43. Project Completion
All work, including compliance with environmental conditions, must be completed
prior to the expiration date of the permits. If necessary, a permit renewal may be
requested. The decision to renew a permit may be in the form of an approval,
approval with conditions or denial depending upon the relevant agency(ies)
specific requirements. Renewal (extension) of permits must occur before the
permits expire.
Upon completion of all work approved within the 401 Water Quality Certification
or applicable Buffer Rules, and any subsequent modifications, NCDOT will return
the Certificate of Completion to the NCDWQ 401/Wetlands Unit after obtaining
the Division Engineer’s signature.
Upon completion of all work, the Division Engineer and Division Environmental
Officer will sign and return the USACE compliance form to the USACE.
Permitting Process for Phased Widening Projects
Many project corridor lengths are broken into a number of project segments and
are funded at different timeframes for right of way acquisition and construction.
Therefore, right of way plan preparation and final plan preparation occur at
various time frames depending upon the project segment’s schedule.
For a project that has multiple project segments, the following process will occur:
The NEPA document will be written for the entire project corridor length (Steps 1-
27). At the time of the Draft EIS or EA issuance, NCDOT will submit a Section
404 permit application for the entire project corridor. The application will include
the plan for how compensatory mitigation will be addressed for the entire project
(Step 33). An approved compensatory mitigation plan must be provided for the
entire project before any project segment is permitted. Following the submittal of
the application, the steps in the process that extend to the issuance of the FONSI
or ROD (whichever is applicable) will be completed for the entire project corridor
length and Concurrence Point 4A will be achieved for the entire project corridor
length.
The development of right of way plans on through to the project letting and
construction (Steps 28-43) will begin for the project segment(s) that are
imminently scheduled for right of way acquisition and letting.
At the time the right of way plans are completed, an updated permit application
will be submitted that will include right of way plans for the project segment(s)
that are imminently scheduled for right of way acquisition and letting. Preliminary
designs will be submitted with the permit application for the remaining project
segments that are scheduled for later years. The permitting agencies will then
take final action on the permit application for all project segments. Any permits
that are issued will have conditions that a final design will have to be submitted
and written approval and/or permit modification obtained from the USACE and
NCDENR before construction can begin on those project segments where only
preliminary design was submitted with the application.
As the right of way and letting date draws near for the remaining project
segment(s), the development of right of way plans and the completion of steps
that lead to the project letting and construction will be completed (Steps 28-43).
At the time the right of way plans for the remaining project segment(s) are
completed, a request for a permit modification will be submitted for those project
segment(s). This request will contain the final design information for the project
segment(s). Prior to providing written approval and/or a permit modification, the
USACE and NCDENR, in coordination with the Project Team, will ensure that all
appropriate avoidance and minimization measures have been incorporated in the
project design. NCDOT will be notified of the decision on the requested
segment(s) approval.
|