Process III – Agency Coordination Process
For Bridge Replacement Projects that are processed as Categorical Exclusion
General
Project Team Meetings
Step by Step Implementation Procedures
Data Collection
Request Environmental Input
Project Scoping
Develop Project Team
Environmental Features Map
Concurrence Point 2/2A – Options to Evaluate in Detail and Bridging Decision
Public Involvement (As appropriate)
Concurrence Point 3 and 4A – LEDPA/Preferred Alternative Selection and Avoidance and Minimization
Prepare CE and Conceptual Mitigation Proposal
Issue CE
Design Public Hearing (optional)
Develop Right-of-Way Plans for the Project
Complete Right-of-Way Plans for the Project
NCDCM On-site Pre-application Meeting
Concurrence Point 4C – Permit Drawings Review
Compensatory Mitigation Requirements
Submit Permit Application
Permit Application Review and Processing
Agency Public Notice (if required)
Permit Decision
Changes to the Project’s Design, Construction Methodology or Construction Timeframe
Complete Final Plans for the Project
Let Project to Construction
Preconstruction Meeting
Compliance Monitoring
Project Completion
General
A process flow chart that outlines the coordination process for bridge
replacement projects that are processed as Categorical Exclusions is attached
(Process III). This flow chart depicts the major milestones in the process but
does not include all of the many activities that NCDOT must complete in the
project development process. These other activities will be completed by
NCDOT and input provided into the process at the appropriate time. For
example, public involvement may be a critical component of the project
development activities and could be ongoing throughout the process.
Information developed through public involvement will be made available to
Project Team members for consideration in the decision making process.
Projects that are included in this process should normally require the preparation
of a Categorical Exclusion. Programmatic Categorical Exclusions will not be
done for projects that follow this process. The Categorical Exclusion for a
specific project should provide sufficient information to address all applicable
federal and state laws and regulations.
The Project Team will review each project at its initial meeting to determine the
appropriate Merger Process that the project should follow. For example, a
Bridge Replacement/CE project that needs Project Team concurrence on
Purpose and Need would follow Process I or Process II instead of Process III.
Project Team Meetings
Team meetings will be held at each of the concurrence points in the Agency
Coordination Process. Additional meetings may be held as determined
necessary by the teams. NCDOT’s Project Development Engineer should
coordinate closely with the appropriate USACE, FHWA, and NCDENR team
member in scheduling any meetings and clearly defining the purpose of the
upcoming meeting. The Project Development Engineer or Hydraulics Project
Engineer will send the package of information for the meeting to team members
so that they will have it in hand at least two weeks prior to the meeting.
The transmittal to each team member should clearly state the purpose and
objective of the meeting. This will allow team members time to review the
information and be prepared to discuss any issues or concerns they have at the
meeting.
At the end of each meeting, the Project Development Engineer, with the team’s
help, should summarize the results of the meeting, including agreements or
concurrence points achieved. If agreement or concurrence is not obtained the
next steps or action should be clearly identified. If additional information or
action is required, the type of information or action needed and the responsible
agency(s) or team member(s) should be clearly noted. The Project Development
Engineer or Hydraulics Project Engineer is responsible for preparing minutes of
all meetings for distribution to all team members.
On-site project field reviews can be very beneficial in helping to understand a
project’s purpose and need, human and natural environmental features and
alternative analysis. Project Teams are encouraged to hold combined field
reviews/meetings as needed to assist in the decision making process.
Step by Step Implementation Procedures
The following discussion is intended to provide more detailed guidance and
explanation on the various steps and concurrence points in the attached flow
chart. The numbered paragraphs correspond to steps or blocks in the chart.
1. Data Collection
The Project Development Engineer will collect all available information and
background data. The project study area will be established and
photogrammetric and topographic data will be collected.
Typical data necessary for the project include: shell mapping, traffic forecast,
utility locations, accident analysis and preliminary comments on the project from
NCDOT Division Personnel, County School Bus Coordinator, County EMS
Director, and County or City Planning staff.
2. Request Environmental Input
Once the project study area is set, the Project Development Engineer will request
environmental input from the Offices of Natural and Human Environment (ONE
and OHE) using the proper mapping and request (NCDOT’s internal) forms. The
study area should be set to encompass the worst case scenario for replacement
of the bridge to either side of the existing bridge [including, if appropriate, minor
realignments of the approach roadway.]
Public notification of these data gathering activities will be handled by NCDOT’s
Location and Surveys Unit who will contact property owners via standard form
letter, before their collection of topographic data. If necessary, additional public
involvement opportunities are available later in the project development process.
The Natural Resources Technical Report is prepared and distributed to
resources agencies including all potential Project Team members.
3. Project Scoping
The Project Scoping Meeting is held by NCDOT to discuss background data,
engineering and environmental inventories and substantial project issues.
Resource agencies will be invited to attend and provide input. Agencies should
provide written input in response to the scoping letter or attend the scoping
meeting.
The project will need to go through the screening process after the scoping
meeting to determine if a Project Team is needed. This decision will be made, by
the NCDOT, USACE, FHWA, and NCDENR.
At the project scoping meeting, NCDOT will provide the proposed project
schedule. The meeting attendees will present any issues that may impact the
proposed schedule. Needed revisions to the project schedule will be identified
and adjusted appropriately by NCDOT.
4. Develop Project Team
If a Project Team is needed, then the Project Development Engineer will consult
with the appropriate USACE, FHWA, and NCDENR representative to identify
specific Project Team members prior to Step 6 (Concurrence Point 2/2A).
NCDOT will provide a written verification of the team roster to all the team
members. If an agency declines to participate on the team, its decision will be
documented in writing to NCDOT, NCDENR, USACE, and FHWA. If an agency
drops from the Project Team during the process, its self-removal will also be
documented in writing.
Note:
Notices of Intent and Purpose and Need Statements [Concurrence Point 1] are
not required on typical Bridge Replacement Projects. If either an EIS is planned
for the project or the purpose and need for the project is in question; the project
should be processed through Process I or II.
5. Environmental Features Map
NCDOT will develop a map illustrating resource areas of concern as well as
topographic or photogrammetric mapping. The purpose of this mapping is to
provide a means for identifying alternatives that warrant study. Such features on
the mapping will include but are not limited to:
- Infrastructure and topography
- Community features (i.e., boundaries, schools, churches, community centers, hospitals, transit dependent populations, demographics, etc.
- Floodplains
- Historic properties and possible areas of archaeological concern
- Wetlands, streams, buffers, river basins, and water supply watersheds (GIS level information)
- Wildlife refuges and game lands
- Recreational areas and parks
- Hazardous material sites
- Existing land use map and locally adopted land use plan
- Threatened and Endangered Species information
- Significant Natural Heritage Program Areas
- Utilities within project study area using best available information
Based on the environmental features map, the study area may be re-confirmed.
6. Concurrence Point 2/2A – Options to Evaluate in Detail and Bridging
Decision
The intent of the Concurrence Point 2/2A meeting is to obtain consensus from
the Project Team on which replacement options will be fully evaluated as
alternatives in the Categorical Exclusion. Options to consider include: closure
without replacement [“no build”], rehabilitation, replace in-place with off-site
detour, replace in-place with on-site detour [either side of existing bridge],
replace on new alignment [either side of existing bridge] and others as
determined by project situation and the Project Team.
Information which should be presented at the Concurrence Point 2/2A meeting
may include: Natural Systems Technical Report, Phase 1 historic property
evaluation and boundaries of known listed and potentially eligible historic sites,
community profile including existing and future land use, comments from the
local government, traffic flow/access concerns, safety concerns, potential utility
impacts, aerial photography and digital terrain mapping. Wetland and stream
delineations, NCDWQ wetland ratings and wetland type, and any CAMA areas of
environmental concern will be identified.
Also, if recommended by the NCDOT, USACE, NCDENR and FHWA, then the
concurrence meeting shall be held on site to:
- Review preliminary design alternatives
- Review any potential mitigation sites including causeway removal
opportunities that may be noted during the delineation effort and
coordinate with the EEP
- Review recommendations for bridging decision, including bridge length
This concurrence point should include discussions of structure-type [bridge,
culvert, or others] and appropriate bridge length or culvert size, utility relocations,
and any other design elements considered a necessary part of the project.
Construction methodologies and access and other issues should also be
discussed.
During the Concurrence Point 2/2A meeting, the Project Team will discuss
Federal, state and local environmental statutes and regulations that may apply to
each of the detailed study alternatives. Within NCDOT, the Office of the Natural
Environment (ONE) is responsible for ensuring that the specific required steps
are followed for each of the environmental permits, certifications, consultations,
reviews and determinations that may be required throughout the project’s life.
The Hydraulics Unit will ensure the FEMA flood insurance program regulations
are followed where applicable.
NCDOT will provide the current schedule. Any changes made to the schedule
will be presented along with the reasons for the change. The agencies will
present any issues that may impact the project schedule. Needed revisions to
the project schedule will be identified and adjusted appropriately by NCDOT.
The NCDOT will request formal concurrence at this meeting by asking the team
members to sign the Concurrence Point 2/2A Form. If additional documentation
or revisions to the provided information are necessary, the NCDOT will
incorporate the additions or revisions and redistribute the information packet. If
necessary, an additional team meeting will be scheduled to resolve outstanding
concerns.
After receipt of the delineations and necessary preliminary mapping, the Design
Engineer will begin to develop the preliminary designs for the replacement
alternatives developed at the Concurrence Point 2/2A meeting. If typical section
or structure-type alternatives were identified at Concurrence Point 2/2A, the
preliminary designs will be developed for these alternatives as well. During the
development of the design, care will be taken to avoid where practicable, impacts
to the natural and human environment. The Design Engineer will coordinate the
preliminary design for each detailed study alternative with the Utilities Section.
The Utilities Section will identify areas where utilities are impacted.
Where it is not practicable to avoid impacts, minimization measures will be
employed.
The USACE will review the project impacts to determine if the project can be
authorized by a General Permit or whether an Individual Permit will be required.
If the determination is for an Individual Permit, then NCDOT will submit a merger
permit application to USACE, and USACE will issue a public notice on the
proposed project.
If it appears at this time that the project can be authorized under a General
Permit (GP), then the process will proceed to Step 7 without a permit application
to USACE. If, at anytime after Concurrence Point 2, it appears likely that the
project will require authorization by an Individual Permit rather than a GP, then
the process will return to this point. Any team decisions that have been made
following Concurrence Point 2, including Concurrence Point 3, LEDPA/Preferred
Alternative selection, will be considered invalid, and NCDOT will submit a permit
application to USACE to provide for the necessary public involvement/public
interest review. Potential subsequent points in the process where the decisions
may be made that an individual permit is required include: at Concurrence Point
4A, after the team members receive copies of the CE, at Concurrence Point 4C,
and at the Permit Decision step. After the public notice process has been
completed, the Concurrence Point 3 meeting should be scheduled.
7. Public Involvement (As appropriate)
If determined appropriate by the Project Development Engineer, a Citizens
Informational Workshop or other form of Public Involvement [Newsletter, etc.]
should take place at this time. At a workshop, aerial photography showing all
replacement alternatives brought forward from Concurrence Point 2/2A will be
presented for public review and comments. Newsletters will describe the
alternatives under consideration and invite comments. Any typical section or
structure-type alternatives identified at Concurrence Point 2/2A should be noted
in order to gain public comments and preferences.
8. Concurrence Point 3 and 4A – LEDPA/Preferred Alternative Selection and Avoidance and Minimization
A Project Team meeting will be held to determine the least environmentally
damaging practicable alternative (LEDPA) [Preferred Alternative under NEPA]
among the replacement alternatives selected for study at Concurrence Point
2/2A. At this meeting the Project Team will also review public comments to
determine if further refinement of the LEDPA or proposed typical section is
necessary. The Project Development Engineer will send the package of
information for the meeting to Project Team members so they will have it in hand
at least two weeks prior to the meeting.
The package will include a matrix illustrating a comparison of impacts for the
detailed study alternatives and a brief summary of previous Project Team
decisions. The package will also include a summary of substantive comments
received from agencies and the public and how these comments were
addressed.
At this time, Project Team members will be reasonably certain that the LEDPA
will comply with all relevant regulations and permit requirements and can be
authorized. Project Team members in agreement with the LEDPA will provide
their formal concurrence at this meeting by signing the Concurrence Point 3
Form.
If concurrence is not reached due to a need for additional documentation,
NCDOT will develop the additional information and submit it to Project Team
members. If necessary, another meeting will be scheduled to address the
additional information.
This meeting will also serve as Concurrence Point 4A. This concurrence point
should address issues such as alignment shifts, horizontal and vertical
alignment, slopes, potential utility conflicts and impacts, and construction
techniques. When avoiding and minimizing jurisdictional resource impacts, other
resources will be considered. In the event 4A cannot be achieved, an additional
meeting may be required. Through minimization efforts achieved by the initial
project design and refinements to this stage, no more minimization
recommendations should be needed until Concurrence Point 4C, unless the
project is to convert a bridge to culvert or an individual permit is required; then a
4B meeting will be appropriate. Refer to Process II, Step 29 for a description of
4B procedures. When a 4B meeting is not conducted, then 4B issues will need
to be discussed at the Concurrence Point 3/4A meeting.
During the Concurrence Point 3 meeting, the Project Team will confirm the
preliminary determination made during the Concurrence Point 2/2A meeting
about the Federal, state and local environmental statutes and regulations that
may apply to the LEDPA/Preferred Alternative. This confirmation is required due
to changes that may have occurred in the project design and/or in the statutes
and regulations since the preliminary determination was made during the
Concurrence Point 2/2A meeting. Within NCDOT, the Office of the Natural
Environment (ONE) is responsible for ensuring that the specific required steps
are followed for each of the environmental permits, certifications, consultations,
reviews and determinations that may be required throughout the project’s life.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The meeting attendees will present any issues that may impact the
project schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
9. Prepare CE and Conceptual Mitigation Proposal
The Categorical Exclusion will be completed according to appropriate regulations
and an identification of impacts will be made for each of the alternatives that
were studied in detail. The CE document will discuss the rationale for selection of
the LEDPA/preferred alternative. The CE document will include all
environmental commitments currently identified for all resources such as
wetlands, streams, Section 106, Section 4(f), public access, etc.
NCDOT will address potential on-site compensatory mitigation options. For
potential on-site mitigation sites, NCDOT ONE will prepare a feasibility study that
includes an environmental evaluation that identifies historic resources,
threatened and endangered species, parks, community issues, etc. NCDOT
ONE may arrange an agency field meeting to review any potential on-site
mitigation opportunities, discuss the environmental evaluation results, and
determine which sites are acceptable to the agencies.
Pursuant to the Memorandum of Agreement among the NCDOT, NCDENR, and
USACE, signed July 22, 2002, the Ecosystem Enhancement Program (EEP) will
provide all compensatory mitigation that is not satisfied by acceptable on-site
mitigation. The FHWA and NCDOT will review the environmental document for
adequacy as it relates to appropriate requirements.
Preliminary determinations about the Federal, state and local environmental
statutes and regulations that may apply to the LEDPA/preferred alternative will
be included within the final environmental document. If the project is within the
20 CAMA counties, then potentially relevant CAMA land use plan policies that
may apply to the LEDPA/preferred alternative will also be included within the final
environmental document.
10. Issue CE
NCDOT and FHWA will sign the title page of the environmental document.
Project Team members will be provided a copy of the CE.
11. Design Public Hearing (optional)
NCDOT may hold a Design Public Hearing. Team members are encouraged to
attend the public hearing to fully understand the public concerns. The USACE
and other team members will be invited to attend the public hearing.
12. Develop Right-of-Way Plans for the Project
After selection of the LEDPA /preferred alternative, the Location and Surveys
Unit and the Photogrammetry Unit perform the final surveys and prepare the plan
sheets needed for the development of the right of way plans. Upon receiving the
plan sheets, the Design Engineers begins to develop the right of way plans for
the project. After the Design Engineers complete the horizontal and vertical
alignment refinement, the Hydraulics Unit begins the development of the
proposed drainage design and the Geotechnical Unit begins the detailed
Geotechnical investigations for the project. The drainage plans will depict the
boundaries of the affected environmental areas (wetlands, perennial and
intermittent streams, buffers, Coastal Area Management Act Areas of
Environmental Concern (CAMA AEC), etc.) (The Design Engineers will develop
the right of way plans following the alignment that was agreed upon at
Concurrence Point 3/4A). The Utilities Section will coordinate the determination
of the utility conflicts and the development of the utility relocation preliminary
designs with the utility owners and the Design Engineers.
13. Complete Right-of-Way Plans for the Project
Upon receiving the completed hydraulic design for the project, NCDOT Design
Engineers incorporate the hydraulic design and establish the proposed right of
way limits for the project. The Structure Design Engineers begin to develop the
designs for bridges and culverts. The project is then reviewed with construction,
the Utilities Section, and right of way personnel to note any additional changes
that may be required. The right of way plans are completed and sent to the Right
of Way Branch to begin purchase of land required for the project.
14. NCDCM On-site Pre-application Meeting
For projects within the 20 CAMA counties that require a CAMA major permit,
NCDOT staff will request an on-site pre-application meeting with the appropriate
NCDCM Field Representative. The purpose of this meeting is to review the
plans and/or permit drawings and information that will be submitted with the
CAMA permit application. This will ensure that when the CAMA major permit
application is formally submitted, it contains all of the information necessary for
processing. The purpose of this meeting is not to make changes to the project
design, construction methodology or construction timeframe.
Any potential changes to the project identified at this on-site pre-application
meeting will be discussed with the full Project Team at the 4C meeting prior to
approval.
15. Concurrence Point 4C – Permit Drawings Review
At the time the hydraulic design is 100 percent complete and the permit drawings
for the project are finalized, the Hydraulics Unit will hold a 4C meeting.
At the 4C meeting, the Hydraulics Project Engineer will present copies of the
stormwater management plan to the Project Team members. A stormwater
management plan is a narrative, project-specific, stormwater design report. It
outlines project involvement, river basins, classifications of the involved water
bodies, selected structural and non-structural best management practices, best
management practice devices, and major structures (bridges and box culverts).
The final permit drawings for the permit application will also be reviewed and
revised based on comments received at this meeting. Any area where utility
relocations affect additional environmental resources beyond the footprint of the
roadway will be shown on the permit drawings and will be included in the impacts
presented in the application. In addition, if the project is within a CAMA
county(ies) and a CAMA Major Permit is required, then all utility locations that are
not included in the permit drawings will be described within the CAMA Major
Permit application either in narrative form or in a separate spreadsheet. The
level of detail of utility relocation information required with the CAMA Major
Permit application will be determined on a project-by-project basis at the NCDCM
on-site pre-application meeting.
The Hydraulics Engineer will record minutes of the meeting and will address the
team’s comments. Changes will be made based on the team’s comments. The
changes will be made in the permit drawings before the permit application is
sent. The Concurrence Form indicates that the Project Team agrees that the
drawings as presented are satisfactory to be submitted with the application.
(This does not supercede the regulatory review process.)
After the changes are incorporated, the Hydraulics Project Engineer will ask for a
signature of the Concurrence Form. The Concurrence Form will be detailed
enough to document and identify changes. Any changes to impacts to wetlands,
streams, buffers, or CAMA AECs that occur after the 4C document is signed will
require the Resource Agencies to revisit the design, and may require a new 4C
meeting. The NCDOT Permit Specialist will contact the agencies via email, letter,
phone call, or scheduling a meeting as appropriate to facilitate review of these
changes.
NCDOT will provide the current schedule. Any changes made to the schedule
since the last concurrence meeting will be presented along with the reasons for
the change. The agencies will present any issues that may impact the project
schedule. Needed revisions to the project schedule will be identified and
adjusted appropriately by NCDOT.
16. Compensatory Mitigation Requirements
Compensatory mitigation requirements will be identified based on final project
impacts.
In those events where on-site mitigation opportunities are available and
determined acceptable and/or necessary by the Project Team, the mitigation plan
and design will be developed in concert with the overall project design. Removal
of existing causeway fills is strongly encouraged to offset project impacts and/or
create mitigation credits for future project impacts. The on-site mitigation will be
developed and implemented by NCDOT in collaboration with the Project Team
and EEP. Under no circumstances will the project be permitted until such time
that the detailed on-site mitigation plan is complete and approved by the
permitting agencies.
Pursuant to the Memorandum of Agreement among the NCDOT, NCDENR, and
USACE, signed July 22, 2002, the Ecosystem Enhancement Program (EEP) will
provide all compensatory mitigation that is not satisfied by acceptable on-site
mitigation.
17. Submit Permit Application
ONE submits permit application(s) as appropriate to all of the agencies for which
permits are required. Permit application(s) will be submitted within two months
after the 4C meeting. The permit application package will vary according to each
agencies specific requirements.
18. Permit Application Review and Processing
Upon receiving the permit application from NCDOT, the permitting agency(ies)
will review the application for completeness. If the permit application is
determined to be incomplete, then the permitting agency(ies) will return the
application to NCDOT for additional information, and/or inform NCDOT of the
additional information that is required.
After the permitting agency(ies) determine that the permit application is complete,
then the permitting agency(ies) will assemble and distribute the application
package for comment to any designated review agencies. This process varies
according to the permit being requested. If the permit application is found to be incomplete or inaccurate after processing
has begun, or if additional information from NCDOT is necessary to adequately
assess the project, then the permitting agency(ies) that have permit processing
deadlines may place an application on hold. NCDOT may also request in writing
that its permit application be placed on hold at any time. If the permit application
is placed on hold by the permitting agency(ies), then the processing shall be
resumed upon receipt of the necessary changes or necessary information from
NCDOT. If NCDOT requested that the permit application be placed on hold, then
the processing shall be resumed upon receipt of a written request from NCDOT
to resume processing.
During the permit application review and processing period, additional
discussions and/or meetings may be conducted between NCDOT and the
environmental agency(ies) to resolve any outstanding issues. The goal of the
agency coordination process, however, is to resolve all of these issues before the
permit application is submitted in order to prevent delays in construction letting.
19. Agency Public Notice (if required)
If required by law or otherwise determined to be appropriate, the permitting
agency(ies) will issue a Public Notice requesting comments from the public on
the permit application. For example, USACE is required to issue a Public Notice
for any project that requires an Individual Permit. The USACE Public Notice is
normally issued for a 30-day review and comment period. In such a case, the
Public Notice would have been issued after Step 6, Concurrence Point 2/2A.
However, if, in the opinion of the USACE, an additional public notice is warranted
due to changes in the project or new information, a second Public Notice will be
issued. NCDCM is required to issue a 30-day Public Notice after a permit
application is accepted as complete for any project that requires a CAMA Major
Permit. NCDWQ generally is not required to issue a separate Public Notice.
20. Permit Decision
After the relevant permitting agency(ies) have reviewed the permit application(s)
for compliance, and comments have been received and properly considered from
the public, as well as relevant state and federal review agencies, a permit
decision will be made. The permit decision may be in the form of an approval,
approval with conditions or denial. If a permit is issued, it will typically list specific
conditions or restrictions on the development. The project must be constructed
according to the permit conditions. A permit decision may be in the form of a
denial if the outstanding issues have not been resolved satisfactorily. A permit
denial is very unlikely for projects that follow the agency coordination process
provided that the full Project Team has reached concurrence at each
concurrence point. After a permit decision is made by a state permitting agency, then the state
agency decision can be appealed by NCDOT or by a third party. If this occurs,
then the state permitting agency(ies) will respond according to their specific
requirements.
21. Changes to the Project’s Design, Construction Methodology or Construction Timeframe
If changes to the project’s design, construction methodology or construction
timeframe are needed at any time, then additional coordination with the relevant
environmental agency(ies) will be required. This includes the agencies that have
permit authority over the project, as well as any other agencies that implement
federal, state and local environmental statutes and regulations that apply to the
project. If changes occur after the permit decisions are made, then these
changes may require the submittal of a request for a modification, amendment,
Letter of Refinement or renewal to the relevant permit(s). A primary goal of the
agency coordination process is to greatly reduce, and eliminate if possible, the
number of changes that may require additional coordination with the
environmental agency(ies) after the original permits are issued. Permit
modifications, in particular, are very time-consuming and problematic for all
concerned parties due to the relatively short timeframe required for resolution.
It is the responsibility of NCDOT, not the Contractor, to conduct any additional
coordination that may be required with the relevant environmental agency(ies).
Coordination with the relevant environmental agencies, including the submittal of
any required permit modification requests, should occur at least 2-3 months
before the work in question must be conducted to allow adequate time for
processing. When reviewing the request, the relevant environmental agency(ies)
may request additional information before making a decision. The decision may
be in the form of an approval, approval with conditions or denial.
22. Complete Final Plans for the Project
During the course of the right of way acquisition, the Design Engineers will begin
to develop the final plans for the project. The final design is a very detailed
design that also includes computing and summarizing the contract quantities
required for the project, incorporating right of way revisions, compiling plans from
various Units (Traffic Engineering Branch, Roadside Environmental Unit, Utilities
Section, etc.) and incorporating them in the project. NCDOT will ensure that
construction drawings match the permit plan drawings and permit conditions,
including any permit modifications.
23. Let Project to Construction
The project is advertised so that all interested contractors can bid on the project.
The bids are opened on the project letting date. After receiving bids, the project
is considered for award by the Board of Transportation. The Board then usually
awards the contract to the low bidder and construction will usually start
approximately 45 days after the contract is awarded. The contractor will be
bound to the permit conditions and any environmental commitments that were
developed during the agency coordination process and environmental
documentation.
24. Preconstruction Meeting
After the contract is awarded, and prior to the initiation of construction, NCDOT
and the Contractor will hold a preconstruction meeting. NCDOT will provide all
Project Team members with a copy of the final plans at least 2 weeks prior to the
preconstruction meeting along with a description of any changes that have been
made to the project’s design, construction methodology or construction
timeframe. The purpose of this meeting is to review the final plans and the
contents of the bid package, including any permit conditions and environmental
commitments. The preconstruction meeting will be scheduled for a time when the
USACE, NCDWQ and NCDCM (if a CAMA major permit was issued) can attend.
All of the Project Team members will be invited to the preconstruction meeting
with a minimum of thirty (30) days notice.
25. Compliance Monitoring
The NCDOT Division Engineer will ensure that all permits, permit conditions and
associated documents are readily available on site at all times. The Division
Engineer is responsible for ensuring that all federal, state and local
environmental statutes and regulations are adhered to after the project is let,
including any permit conditions and environmental commitments. The Division
Environmental Officer will provide assistance to the Division Engineer in meeting
these requirements. Representatives from USACE, NCDCM, NCDWQ and other
environmental agencies may visit the project site, including any disposal or
borrow areas, at any time to conduct compliance inspections.
26. Project Completion
All work, including compliance with environmental conditions, must be completed
prior to the expiration date of the permits. If necessary, a permit renewal may be
requested. The decision to renew a permit may be in the form of an approval,
approval with conditions or denial depending upon the relevant agency(ies)
specific requirements. Renewal (extension) of permits must occur before the
permits expire.
Upon completion of all work approved within the 401 Water Quality Certification
or applicable Buffer Rules, and any subsequent modifications, NCDOT will return
the Certificate of Completion to the NCDWQ 401/Wetlands Unit after obtaining
the Division Engineer’s signature.
Upon completion of all work, the Division Engineer and Division Environmental
Officer will sign and return the USACE compliance form to the USACE.
|