MASTER FOR 2002 SPECS
RESURFACING PROJECTS
GENERAL
| RG01 | PROJECT SPECIAL PROVISIONS |
| RG03 | NOTICE TO BIDDERS (Cluster Projects) |
| RG05 | CONTRACT TIME AND LIQUIDATED DAMAGES (FLOATING DATES) |
| RG06 | CONTRACT TIME AND LIQUIDATED DAMAGES The date of availability ______________________________________ The completion date ______________________________________ The liquidated damages $______________________________________ |
| RG07 | INTERMEDIATE CONTRACT TIME NUMBER AND LIQUIDATED DAMAGES (Holiday and Time Restrictions) |
| RG09 | PROSECUTION OF WORK $______________________________________ |
| RG11 | SAFETY INDEX RATING |
| RG12 | RAILROAD GRADE CROSSING |
| RG15 | MAJOR CONTRACT ITEMS Line #                     Description _____________     __________________________________________ _____________     __________________________________________ _____________     __________________________________________ _____________     __________________________________________ |
| RG18 | SPECIALTY ITEMS Line #                     Description _____________     __________________________________________ _____________     __________________________________________ _____________     __________________________________________ _____________     __________________________________________ |
| RG21 | NO SPECIALTY ITEMS |
| RG24 | POSTED WEIGHT LIMITS |
| RG33 | SCHEDULE OF ESTIMATED COMPLETION PROGESS Fiscal Year                     Progress (Dollar Value) _________________     ____________________________% _________________     ____________________________% _________________     ____________________________% _________________     ____________________________% |
| RG34 | ON-LINE ELECTRONIC BIDDING |
| RG36 | DISADVANTAGE BUSINESS ENTERPRISES (with Goals) _____% |
| RG39 | DISADVANTAGE BUSINESS ENTERPRISES (without Goals) |
| RG40 | MENTOR-PROTÉGÉ PROGRAM
(When requested by the Proposals and Contract Engineer) |
| RG42 | MINORITY AND WOMEN BUSINESSES (State - with Goals) MB = _____% WB = _____% |
| RG43 | FUEL PRICE ADJUSTMENT |
| RG45 | MINORITY AND WOMEN BUSINESSES (State - 0.0% Goals) |
| RG48 | RETAINAGE and PROMPT PAYMENT (FEDERAL AID PROJECTS) |
| RG51 | PROMPT PAYMENT (STATE FUNDED PROJECTS) |
| RG54 | PARTIAL PAYMENTS (STATE FUNDED PROJECTS) |
| RG57 | SUBMISSION OF BIDS - ALTERNATIVES |
| RG63 | DOMESTIC STEEL AND IRON PRODUCTS (ALL PROJECTS) |
| RG65 | RECYCLED STEEL |
| RG66 | U.S. DEPARTMENT OF TRANSPORTATION HOTLINE (F.A. Only) |
| RG69 | CERTIFICATION FOR FEDERAL-AID CONTRACTS (F.A. Only) |
| RG72 | SUBMISSION OF RECORDS - FEDERAL-AID PROJECTS (BRZ) |
| RG75 | SUBMISSION OF RECORDS - FEDERAL-AID PROJECTS (on NHS + 1 million project cost) |
| RG78 | SUBMISSION OF RECORDS - FEDERAL-AID PROJECTS (not on NHS) |
| RG80 | COMPENSATION AND RECORD KEEPING (ALL PROJECTS) |
| RG84 | PLANT PEST QUARANTINES (ALL PROJECTS) |
| RG87 | SAFETY VESTS (ALL PROJECTS) |
| RG90 | TRAINING REQUIREMENTS ______Trainees |
| RG91 | DIRECTOR OF CONSTRUCTION IN LIEU OF CHIEF ENGINEER (ALL PROJECTS) |
| RG92 | CONTRACTOR BORROW SOURCE |
| RG95 | OUTSOURCING OUTSIDE THE USA |
| RG100 | CRANE SAFETY |
| RG105 | FORCE ACCOUNT |
| RG120 | BORROW AND WASTE SITE RECLAMATION PROCEDURES |
| RG151 | ACT OF GOD - DEC 2002 LET |
| RG155 | DISQUALIFICATION OF BIDDERS |
| RG170 | CONTROL OF EROSION,SILTATION AND POLLUTION |
| RG175 | REJECTION OF BIDS |
| ROADWAY | |
| RR01 | PROJECT SPECIAL PROVISIONS - ROADWAY |
| RR02 | BORROW EXCAVATION |
| RR03 | AGGREGATE BASE COURSE GRADATION AND PLASTICITY INDEX |
| RR04 | SHOULDER CONSTRUCTION |
| RR05 | ROADWAY EXCAVATION |
| RR07 | SHOULDER RECONSTRUCTION (3rd Div.) |
| RR10 | SHOULDER CONSTRUCTION PROCEDURE (12th Division) |
| RR13 | FINAL ACCEPTANCE AND FOURTEEN DAY OBSERVATION PERIOD (Plant Mix) |
| RR16 | FINAL ACCEPTANCE AND FOURTEEN DAY OBSERVATION PERIOD (AST) |
| RR19 | PRICE ADJUSTMENT - ASPHALT BINDER PLANT MIX $______________________________; DATE:________________________ |
| RR20 | FINAL SURFACE TESTING - ASPHALT PAVEMENT |
| RR22 | NOTES TO CONTRACTOR |
| RR25 | CONDITIONING ROAD |
| RR28 | INCIDENTAL STONE BASE |
| RR31 | ASPHALT PAVEMENTS SUPERPAVE |
| RR32 | ASPHALT CONCRETE PLANT MIX PAVEMENTS - MARSHALL MIX |
| RR34 | CONSTRUCTION SEQUENCE |
| RR38 | ASPHALT PAVER - FIXED STRING LINE |
| RR39 | ASPHALT PAVER - MOBILE AND FIXED STRING LINE * Deleted June 2006 LETTING* |
| RR41 | COATED, PAVED AND LINED CORRUGATED STEEL CULVERT PIPE |
| RR43 | BINDER CONTENT OF ASPHALT PLANT MIXES SUPERPAVE Asphalt Concrete Base Course, Type B25.0__ ------------------------------ 4.3% Asphalt Concrete Intermediate Course, Type I19.0__ ---------------------- 4.7% Asphalt Concrete Surface Course, Type S 4.75A --------------------------- 7.0% Asphalt Concrete Surface Course, Type SF 9.5A --------------------------- 6.5% Asphalt Concrete Surface Course, Type S9.5__ ---------------------------- 6.0% Asphalt Concrete Surface Course, Type S12.5__ --------------------------- 5.5 |
| RR46 | ASPHALT PLANT MIXTURES |
| RR49 | ASPHALT CONCRETE SURFACE COURSE COMPACTION |
| RR50 | COARSE AGGREGATE |
| RR51 | BORROW MATERIAL |
| RR52 | WEDGE COURSE |
| RR55 | ASPHALT SURFACE TREATMENT SEAL COAT shall be a ___________________seal |
| RR56 | WARRANTY OF ASPHALT SURFACE TREATMENT |
| RR58 | REPAIR OF EXISTING PAVEMENT |
| RR61 | RESURFACING EXISTING BRIDGES |
| RR64 | PAVING INTERSECTIONS - Contractor condition, prime, and surface |
| RR67 | PAVING INTERSECTIONS - State Forces condition, prime |
| RR70 | PAVING INTERSECTIONS, DRIVEWAYS AND MAILBOX TURNOUTS |
| RR73 | PAVING INTERSECTIONS, DRIVEWAYS AND MAILBOX TURNOUTS (3rd Div.) |
| RR76 | NOTE TO CONTRACTOR (Pavement varies in width) |
| RR79 | TRENCHING FOR BASE COURSE (Contractor disposes of excess material) |
| RR82 | TRENCHING FOR BASE COURSE (State Forces dispose of Excess material) |
| RR85 | ASPHALT CONCRETE SURFACE COURSE, TYPE ___ (LEVELING COURSE) |
| RR88 | PATCHING EXISTING PAVEMENT |
| RR91 | SEALING EXISTING PAVEMENT CRACKS |
| RR94 | REPAIR AND SEALING OF EXISTING PAVEMENT CRACKS |
| RR95 | MATERIAL TRANSFER VEHICLE (MTV) (Asphalt Binder PG 76-22) |
| RR97 | ADJUSTMENT OF MANHOLES (5th Division) |
| RR100 | ADJUSTMENT OF MANHOLES (rings or rapid set) |
| RR103 | ADJUSTMENT OF MANHOLES, METER BOXES, AND VALVE BOXES (cast iron or steel fittings not permitted) |
| RR105 | RETROFITTING WHEELCHAIR RAMPS W/DETECTABLE WARNINGS (RAISED TRUNCATED DOMES) |
| RR107 | WHEELCHAIR RAMPS FOR RESURFACING PROJECTS |
| RR109 | AGGREGATE PRODUCTION |
| RR112 | CONCRETE BRICK AND BLOCK PRODUCTION |
| RR115 | HIGH STRENGTH CONCRETE FOR DRIVEWAYS |
| RR116 | DRUMS |
| RR117 | PORTABLE CONCRETE BARRIER |
| RR118 | REMOVAL OF EXISTING PAVEMENT MARKERS |
| RR119 | PAVEMENT MARKING GENERAL REQUIREMENTS |
| RR120 | GUARDRAIL POSTS AND OFFSET BLOCKS |
| R1 | TRAFFIC CONTROL |
| R2 | WORK ZONE SIGNING (Contractor provides advance warning signs only) (State Forces provide other construction warning signs) |
| R3 | WORK ZONE SIGNING (Contractor provides all construction warning signs) |
| R4 | TIME LIMITATIONS FOR PLACEMENT AND REPLACEMENT OF PAVEMENT MARKINGS AND MARKERS COMPLETED BY CONTRACTORS ON NEWLY RESURFACED AREAS |
| R5 | ROADWAY STANDARD DRAWINGS |
| R6 | NORTH CAROLINA MOVING AHEAD SIGNS (Use with NCMA projects) |
R7 | TRAFFIC CONTROL | R8 | WORK ZONE SIGNS | R9 | BARRICADES |