This bidtabs sheet is in English units. The Metric Units version is also available.

 
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  1                                                                                                                                                                                       
                          AVERAGE UNIT BIDS                                                                                                                                                                                                                    
                                                                                                                                                                                                                                                               
DATE     9701-9712                                                                                                                                                                                                                                             
COMPLETE FILE FOR THIS PERIOD                                                                                                                                                                                                                                  
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
                                                                                                                                                                                                                                                               
*****  JAN 1997  *****                                                                                                                                                                                                                                         
                                                                                                                                                                                                                                                               
09/01  F-2415  8.1171501  CRAVEN     5,375,000.00  MSC  FBD           0.000   0    0   0                   1   2  17                                                                                                                                           
                   PROJECT TOTAL =   5,375,000.00   STEINER SHIPYARD, INC.                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
10/01  B-2179  8.1750901  WATAUGA      215,332.90  RWY  BRS  2,658    0.081   1    0   0  SLS U  C         4  11  75                                                                                                                                           
10/02  B-2179  8.1750901  WATAUGA      181,118.03  BRG  BRS           0.012   1  333  15  SLS U  C         4  11  75      18+52.00-L                                                                                                                           
                   PROJECT TOTAL =     396,450.93   TAYLOR & MURPHY CONST.                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
11/01  B-2538  8.2602201  DAVIDSON     432,048.30  RWY  BRZ  1,403    0.308   2  612   0  S      C         2   9  60                                                                                                                                           
11/02  B-2538  8.2602201  DAVIDSON     155,133.00  CLV  BRZ           0.005   1    2   7  S      C         2   9  60    19+37.00-LRE                                                                                                                           
                   PROJECT TOTAL =     587,181.30   JOHN H. BRINKLEY, INC.                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
12/01  E-2987  8.2623101  FORSYTH    1,470,356.65  BRG  STP           0.047   1   98  31           B       2   9  62    10+21.97-L-                                                                                                                            
                   PROJECT TOTAL =   1,470,356.65   FOWLER JONES BEERS CON                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
13/01          7.1511085  BEAUFORT     859,656.30  SUR          32   27.000   2    0   0  S                1   2  15    MAPS 1-2                                                                                                                               
13/02          7.1521085  BEAUFORT     280,475.00  SUR          23   11.950   2    0   0  S                1   2  15    MAPS 3-7                                                                                                                               
13/03          7.1574885  BEAUFORT     199,325.44  SUR         125    1.600   2    0   0  S                1   2  15    MAPS 8                                                                                                                                 
13/04          7.1811085  GREENE       179,527.10  SUR          29    6.100   2    0   0  S                1   2  18    MAPS 9                                                                                                                                 
13/05          7.1821085  GREENE       142,285.40  SUR          23    6.250   2    0   0  S                1   2  18    MAPS 10-12                                                                                                                             
13/06          7.2021085  LENOIR       290,442.10  SUR          24   12.250   2    0   0  S                1   2  20    MAPS 13-30                                                                                                                             
13/07          7.2072485  LENOIR        40,757.50  SUR          25    1.650   2    0   0  S                1   2  20    MAPS 31-36                                                                                                                             
13/08          7.2073685  LENOIR        10,028.40  SUR          40    0.250   2    0   0  S                1   2  20    MAPS 37                                                                                                                                
13/09          7.2211085  PITT         472,260.55  SUR          47   10.050   2    0   0  S                1   2  22    MAPS 38-39                                                                                                                             
13/10          7.2221085  PITT         434,442.30  SUR          25   17.250   2    0   0  S                1   2  22    MAPS 40-48                                                                                                                             
13/11          7.2271685  PITT          10,384.10  SUR          35    0.300   2    0   0  S                1   2  22    MAPS 49                                                                                                                                
13/12          7.2272085  PITT          67,617.23  SUR         128    0.530   2    0   0  S                1   2  22    AMSP 50                                                                                                                                
                   PROJECT TOTAL =   2,987,201.42   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
14/01          7.1611086  CARTERET     166,497.40  SUR          37    4.500   2    0   0  S                1   2  16    MAP 1                                                                                                                                  
14/02          7.1621086  CARTERET     135,857.50  SUR          36    3.750   2    0   0  S                1   2  16    MAPS 2-4                                                                                                                               
14/03          7.1711086  CRAVEN       271,138.96  SUR          37    7.300   2    0   0  S                1   2  17    MAPS 5                                                                                                                                 
14/04          7.1721086  CRAVEN     1,158,559.50  SUR          28   40.900   2    0   0  S                1   2  17    MAPS 6-23                                                                                                                              
14/05          7.1771386  CRAVEN        13,793.50  SUR          31    0.450   2    0   0  S                1   2  17    MAPS 24                                                                                                                                
14/06          7.1772986  CRAVEN        40,220.46  SUR          38    1.050   2    0   0  S                1   2  17    MAPS 25                                                                                                                                
14/07          7.1774586  CRAVEN        18,417.50  SUR          26    0.700   2    0   0  S                1   2  17    MAPS 26                                                                                                                                
14/08          7.1775786  CRAVEN       107,548.31  SUR          47    2.290   2    0   0  S                1   2  17    MAPS 27                                                                                                                                
14/09          7.1911086  JONES         90,027.24  SUR          37    2.450   2    0   0  S                1   2  19    MAPS 28                                                                                                                                
14/10          7.1921086  JONES        195,167.50  SUR          27    7.300   2    0   0  S                1   2  19    MAPS 29-34                                                                                                                             
14/11          7.2121086  PAMLICO      191,747.00  SUR          26    7.400   2    0   0  S                1   2  21    MAPS 35-40                                                                                                                             
14/12          7.2170886  PAMLICO       42,807.66  SUR          30    1.450   2    0   0  S                1   2  21    MAPS 41-44                                                                                                                             
14/13          4.6023201  PAMLICO       21,785.50  SUR          27    0.820   2    0   0  S                1   2  21    MAPS 45-47                                                                                                                             
                   PROJECT TOTAL =   2,453,568.03   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
16/01  R-2405  6.279005T  PENDER     5,458,912.30  RWY       1,537    3.551   4    0   0   LS U  C         1   3  27                                                                                                                                           
                   PROJECT TOTAL =   5,458,912.30   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
19/01          7.2521110  NEW HANOV    188,075.95  SUR          66    2.830   2    0   0  S                1   3  25    MAPS 1-5                                                                                                                               
19/02          7.2573210  NEW HANOV    358,190.90  SUR         112    3.200   2    0   0  S                1   3  25    MAPS 6-11                                                                                                                              
19/03          7.2611110  ONSLOW       506,458.15  SUR          78    6.500   2    0   0  S                1   3  26    MAPS 12                                                                                                                                
19/04          7.2621110  ONSLOW       276,302.80  SUR          53    5.200   2    0   0  S                1   3  26    MAPS 13-15                                                                                                                             
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  2                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
19/05          7.2711110  PENDER     1,194,515.40  SUR          81   14.800   2    0   0  S                1   3  27    MAPS 16-17                                                                                                                             
19/06          7.2721110  PENDER       215,686.20  SUR          51    4.240   2    0   0  S                1   3  27    MAPS 18-21                                                                                                                             
19/07          7.2770610  PENDER        29,138.05  SUR          65    0.450   2    0   0  S                1   3  27    MAPS 22-23                                                                                                                             
19/08          7.2774710  PENDER        99,318.75  SUR          58    1.700   2    0   0  S                1   3  27    MAPS 24-25                                                                                                                             
                   PROJECT TOTAL =   2,867,686.20   THE PAPCO GROUP, INC.                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
20/01  UM-256  5.4080011  WAKE         632,001.00  RWY      10,361    0.061  10  482   0           B       2   5  40                                                                                                                                           
20/02  UM-256  5.4080011  WAKE         216,057.54  BRG                0.000   4  396  15           B       2   5  40    WESTBOUND LA                                                                                                                           
20/03  UM-256  5.4080011  WAKE         271,801.66  BRG                0.000   4  396  15           B       2   5  40    EASTBOUND LA                                                                                                                           
                   PROJECT TOTAL =   1,119,860.20   LANFORD BROTHERS COMPA                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
21/01  R-2558  6.469004T  ROBESON    8,260,879.40  RWY       1,473    5.610   4  654   0   LS U  C B       1   6  46                                                                                                                                           
21/02  R-2558  6.469004T  ROBESON      138,168.89  CLV                0.004   1  202   8   LS U  C B       1   6  46     575+97.00-L                                                                                                                           
21/03  R-2558  6.469004T  ROBESON       84,955.55  CLV                0.000   1  202   5   LS U  C B       1   6  46     593+15.00-L                                                                                                                           
21/04  R-2558  6.469004T  ROBESON       86,547.35  CLV                0.000   1  202   5   LS U  C B       1   6  46    9+80.00C/LME                                                                                                                           
21/05  R-2558  6.469004T  ROBESON      175,599.63  CLV                0.004   1  202   5   LS U  C B       1   6  46     11+75.00-L1                                                                                                                           
21/06  R-2558  6.469004T  ROBESON      280,155.70  BRG             A  0.026   3  836  19   LS U  C B       1   6  46    582+09-L-(WB                                                                                                                           
21/07  R-2558  6.469004T  ROBESON      257,095.70  BRG             A  0.000   3  836  19   LS U  C B       1   6  46    582+09-L-(EB                                                                                                                           
21/08  R-2558  6.469004T  ROBESON      753,608.50  BRG             Q  0.052   3  854  15   LS U  C B       1   6  46    20+55-L1-(WB                                                                                                                           
21/09  R-2558  6.469004T  ROBESON      710,195.00  BRG             Q  0.000   3  854  15   LS U  C B       1   6  46    20+55-L1-(EB                                                                                                                           
21/10  R-2558  6.469004T  COLUMBUS     377,506.70  BRG             Q  0.026   2  845  19   LS U  C B       1   6  43    27+59.9-L1-W                                                                                                                           
21/11  R-2558  6.469004T  COLUMBUS     351,436.20  BRG             Q  0.000   2  845  19   LS U  C B       1   6  43    27+59.9-L1-E                                                                                                                           
21/12  R-2558  6.469004T  COLUMBUS      52,660.00  BRG             A  0.026   3   98  19   LS U  C B       1   6  43    34+84.5-L1-W                                                                                                                           
21/13  R-2558  6.469004T  COLUMBUS     258,896.70  BRG             A  0.000   3  836  19   LS U  C B       1   6  43    34+84.5-L1-E                                                                                                                           
                   PROJECT TOTAL =  11,787,705.32   BMCO CONSTRUCTION, INC                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
22/01          7.4711191  ALAMANCE     233,043.38  SUR          27    8.780   2    0   0  S                2   7  47    MAPS 1-2                                                                                                                               
22/02          7.4721191  ALAMANCE     584,870.94  SUR          27   21.770   2    0   0  S                2   7  47    MAPS 3-13                                                                                                                              
22/03          7.4770191  ALAMANCE     489,982.78  SUR         105    4.670   2    0   0  S                2   7  47    MAPS 14-17                                                                                                                             
22/04          7.4770791  ALAMANCE      19,618.46  SUR          36    0.550   2    0   0  S                2   7  47    MAPS 18-19                                                                                                                             
22/05          7.4772391  ALAMANCE      12,863.82  SUR          30    0.430   2    0   0  S                2   7  47    MAPS 20-21                                                                                                                             
                   PROJECT TOTAL =   1,340,379.38   RILEY PAVING, INC.                                                                                                                                                                                         
                                                                                                                                                                                                                                                               
23/01          5.6021120  DAVIDSON     697,032.64  SUR          43   16.070   2    0   0  S                2   9  60    MAPS 1-8                                                                                                                               
23/02          7.6011159  DAVIDSON     527,499.69  SUR          55    9.520   2    0   0  S                2   9  60    MAPS 9-12                                                                                                                              
23/03          7.6021159  DAVIDSON     831,982.96  SUR          43   19.460   2    0   0  S                2   9  60    MAPS 13-19                                                                                                                             
                   PROJECT TOTAL =   2,056,515.29   MOFFITT & PIERCE CONST                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
24/01          5.6321119  ROWAN        109,028.15  SUR          69    1.580   2    0   0  S                2   9  63    MAPS 1-3                                                                                                                               
24/02          7.6311157  ROWAN        755,889.65  SUR         168    4.510   2    0   0  S                2   9  63    MAPS 4-6                                                                                                                               
24/03          7.6321157  ROWAN      1,544,516.75  SUR          81   19.010   2    0   0  S                2   9  63    MAPS 7-17                                                                                                                              
24/04          7.6370257  ROWAN         13,735.00  SUR          69    0.200   2    0   0  S                2   9  63    MAPS 18                                                                                                                                
24/05          7.6370657  ROWAN         26,310.00  SUR          64    0.410   2    0   0  S                2   9  63    MAPS 19                                                                                                                                
24/06          7.6371357  ROWAN         25,290.10  SUR          82    0.310   2    0   0  S                2   9  63    MAPS 20                                                                                                                                
24/07          7.6371457  ROWAN        160,954.60  SUR          88    1.820   2    0   0  S                2   9  63    MAPS 21                                                                                                                                
24/08          7.6372457  ROWAN         89,113.80  SUR          66    1.360   2    0   0  S                2   9  63    MAPS 22-23                                                                                                                             
                   PROJECT TOTAL =   2,724,838.05   THE PAPCO GROUP, INC.                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
25/01          7.6111158  DAVIE        274,384.43  SUR          82    3.340   2    0   0  S                2   9  61    MAP 1                                                                                                                                  
25/02          7.6121158  DAVIE        185,220.95  SUR          62    3.010   2    0   0  S                2   9  61    MAPS 2-5                                                                                                                               
25/03          7.6171258  DAVIE         77,899.18  SUR          64    1.210   2    0   0  S                2   9  61    MAPS 6-7                                                                                                                               
                   PROJECT TOTAL =     537,504.56   THE PAPCO GROUP, INC.                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
26/01          7.6211160  FORSYTH      206,226.68  SUR          40    5.160   2    0   0  S                2   9  62    MAPS 1-2                                                                                                                               
26/02          7.6221160  FORSYTH      851,099.11  SUR          75   11.280   2    0   0  S                2   9  62    MAPS 3-8                                                                                                                               
26/03          7.6271860  FORSYTH      110,817.08  SUR          48    2.330   2    0   0  S                2   9  62    MAPS 9-10                                                                                                                              
26/04          7.6272360  FORSYTH       79,611.55  SUR          57    1.390   2    0   0  S                2   9  62    MAPS 11-12                                                                                                                             
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  3                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
26/05          7.6272860  FORSYTH      166,667.42  SUR          63    2.640   2    0   0  S                2   9  62    MAPS 13                                                                                                                                
                   PROJECT TOTAL =   1,414,421.84   THE PAPCO GROUP, INC.                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
27/01  U-1959  7.6411156  STOKES       222,490.98  SUR          52    4.320   2    0   0  S                2   9  64    MAPS 1-3                                                                                                                               
27/02  U-1959  7.6421156  STOKES       487,204.19  SUR          46   10.490   2    0   0  S                2   9  64    MAPS 4-7                                                                                                                               
27/03  U-1959  7.6472256  STOKES        18,190.00  SUR          61    0.300   2    0   0  S                2   9  64    MAPS 8                                                                                                                                 
27/04  U-1959  9.8092212  STOKES        75,704.77  SUR          34    2.250   2    0   0  S                2   9  64    MAPS 9                                                                                                                                 
                   PROJECT TOTAL =     803,589.94   VIRGINIA-CAROLINA PAVI                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
28/01          7.8011230  CLEVELAND    499,590.46  SUR          46   10.750   2    0   0  S                3  12  80    MAPS 1-2                                                                                                                               
28/02          7.8021230  CLEVELAND    785,424.42  SUR          34   23.100   2    0   0  S                3  12  80    MAPS 3-25                                                                                                                              
28/03          7.8072930  CLEVELAND    320,015.66  SUR          96    3.320   2    0   0  S                3  12  80    MAPS 26-31                                                                                                                             
28/04          7.8074030  CLEVELAND     24,017.50  SUR          32    0.750   2    0   0  S                3  12  80    MAP 32                                                                                                                                 
28/05          7.8074130  CLEVELAND     39,511.46  SUR          27    1.480   2    0   0  S                3  12  80    MAP 33                                                                                                                                 
28/06          7.8079630  CLEVELAND     14,510.20  SUR          32    0.450   2    0   0  S                3  12  80    MAP 34                                                                                                                                 
28/07          7.8079730  CLEVELAND     87,712.08  SUR          54    1.620   2    0   0  S                3  12  80    MAP 35                                                                                                                                 
28/08          7.8079930  CLEVELAND     56,726.42  SUR          42    1.350   2    0   0  S                3  12  80    MAP 36                                                                                                                                 
28/09          7.8311230  LINCOLN       19,006.56  SUR          48    0.400   2    0   0  S                2  12  83    MAP 37                                                                                                                                 
                   PROJECT TOTAL =   1,846,514.76   JOHN E. JENKINS, INC.                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
29/01  R-2623  9.8122511  CATAWBA    3,292,007.05  RWY       1,256    2.620   2    0   0  S   U            2  12  79                                                                                                                                           
29/02  R-2623  9.8122511  CATAWBA      428,602.75  BRG             Q  0.030   3  845  15  S   U            2  12  79    81+73.00 -L-                                                                                                                           
29/03  R-2623  9.8122511  CATAWBA      399,256.53  BRG             Q  0.029   3  845  15  S   U            2  12  79    111+63.50 -L                                                                                                                           
                   PROJECT TOTAL =   4,119,866.33   DIXIE GRADING & EQUIPM                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
30/01          7.0021089  TRANSYLVA    213,652.50  SUR          26    8.240   2    0   0  S                4  14 100    MAPS 1-12                                                                                                                              
30/02          7.9411089  HAYWOOD      612,324.11  SUR         130    4.720   2    0   0  S                4  14  94    MAPS 13-14                                                                                                                             
30/03          7.9421089  HAYWOOD      274,601.50  SUR          25   11.130   2    0   0  S                4  14  94    MAPS 15-28                                                                                                                             
30/04          7.9470489  HAYWOOD      141,897.23  SUR         107    1.320   2    0   0  S                4  14  94    MAP 29                                                                                                                                 
30/05          7.9479989  HAYWOOD        2,354.50  SUR          47    0.050   2    0   0  S                4  14  94    MAP 30                                                                                                                                 
                   PROJECT TOTAL =   1,244,829.84   ASHEVILLE DIVISION,                                                                                                                                                                                        
                                                                                                                                                                                                                                                               
31/01          7.9111090  CHEROKEE     571,921.66  SUR          42   13.530   2    0   0  S                4  14  91    MAP 1-2                                                                                                                                
31/02          7.9121090  CHEROKEE     221,978.10  SUR          25    9.060   2    0   0  S                4  14  91    MAP 3-6                                                                                                                                
31/03          7.9221090  CLAY          82,489.80  SUR          37    2.200   2    0   0  S                4  14  92    MAP 7-8                                                                                                                                
31/04          7.9321090  GRAHAM       100,303.40  SUR          24    4.170   2    0   0  S                4  14  93    MAP 9-11                                                                                                                               
                   PROJECT TOTAL =     976,692.96   HARRISON CONST. CO., I                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
32/01          7.9511087  HENDERSON    142,334.70  SUR          83    1.720   2    0   0  S                4  14  95    MAPS 1                                                                                                                                 
32/02          7.9521087  HENDERSON    739,460.00  SUR          34   21.440   2    0   0  S                4  14  95    MAPS 2-28                                                                                                                              
32/03          7.9571387  HENDERSON     42,395.32  SUR         137    0.310   2    0   0  S                4  14  95    MAPS 29                                                                                                                                
32/04          7.9821087  POLK         130,071.95  SUR          25    5.110   2    0   0  S                3  14  98    MAPS 30-34                                                                                                                             
32/05          7.9870787  POLK          15,593.90  SUR          26    0.610   2    0   0  S                3  14  98    MAPS 35                                                                                                                                
                   PROJECT TOTAL =   1,069,855.87   ASHEVILLE DIVISION,                                                                                                                                                                                        
                                                                                                                                                                                                                                                               
33/01          7.9611088  JACKSON    1,228,190.44  SUR         130    9.430   2    0   0  S                4  14  96    MAPS 1-3                                                                                                                               
33/02          7.9621088  JACKSON      336,742.00  SUR          35    9.560   2    0   0  S                4  14  96    MAPS 4-12                                                                                                                              
33/03          7.9672088  JACKSON      194,660.84  SUR          87    2.240   2    0   0  S                4  14  96    MAPS 13-16                                                                                                                             
33/04          7.9672388  JACKSON       13,115.00  SUR          24    0.540   2    0   0  S                4  14  96    MAP 17                                                                                                                                 
33/05          7.9672688  JACKSON       26,026.74  SUR          70    0.370   2    0   0  S                4  14  96    MAP 18                                                                                                                                 
33/06          7.9711088  MACON        273,834.17  SUR         105    2.620   2    0   0  S                4  14  97    MAP 19                                                                                                                                 
33/07          7.9721088  MACON        305,701.50  SUR          48    6.330   2    0   0  S                4  14  97    MAPS 20-25                                                                                                                             
33/08          7.9911088  SWAIN        763,347.34  SUR         155    4.910   2    0   0  S                4  14  99    MAPS 26                                                                                                                                
33/09          7.9921088  SWAIN        145,925.00  SUR          25    5.840   2    0   0  S                4  14  99    MAPS 27-32                                                                                                                             
33/10          7.9972688  SWAIN         97,480.86  SUR         137    0.710   2    0   0  S                4  14  99    MAPS 33                                                                                                                                
                   PROJECT TOTAL =   3,385,023.89   HARRISON CONST. CO., I                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  4                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
                         *****  JAN 1997 TOTAL = $56,023,955.06                                                                                                                                                                                                
                                                                                                                                                                                                                                                               
*****  FEB 1997  *****                                                                                                                                                                                                                                         
                                                                                                                                                                                                                                                               
14/01  U-2556  8.1171003  CRAVEN     8,392,402.80  RWY  STP  2,858    2.936   2    0   0                   1   2  17                                                                                                                                           
14/02  U-2556  8.1171003  CRAVEN       272,025.00  RWY  STP           0.000   0    0   0                   1   2  17    NEW BERN                                                                                                                               
14/03  U-2556  8.1171003  CRAVEN        88,781.53  CLV  STP           0.000   1  202   9                   1   2  17    53+61.50-L-                                                                                                                            
14/04  U-2556  8.1171003  CRAVEN        79,495.90  CLV  STP           0.000   1  201   3                   1   2  17    167+13.00-L-                                                                                                                           
                   PROJECT TOTAL =   8,832,705.23   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
15/01  U-2802  9.8070186  ALAMANCE     865,760.50  RWY       2,697    0.321   2    0   0    S              2   7  47                                                                                                                                           
15/02  U-2802  9.8070186  ALAMANCE      16,900.00  RWY                0.000   0    0   0    S              2   7  47    CITY OF BURL                                                                                                                           
                   PROJECT TOTAL =     882,660.50   SANTARO INDUSTRIES, IN                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
16/01  R-2422  6.804796   WAYNE      1,297,767.80  RWY         578    2.246   1    0   0  SLS U            2   4  33    10+50-129+10                                                                                                                           
                   PROJECT TOTAL =   1,297,767.80   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
17/01  U-2226  9.8022831  CARTERET   5,613,225.00  RWY       2,338    2.401   4    0   0    S    C         1   2  16                                                                                                                                           
17/02  U-2226  9.8022831  CARTERET      75,467.62  CLV                0.000   1    1  17    S    C         1   2  16      60+55.00-L                                                                                                                           
17/03  U-2226  9.8022831  CARTERET      77,264.57  CLV                0.000   1    1  10    S    C         1   2  16      86+62.00-L                                                                                                                           
                   PROJECT TOTAL =   5,765,957.19   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
18/01  U-2400  9.8100163  STANLY     6,455,928.68  RWY       1,913    3.375   2  614   0  S S UR C B       2  10  68                                                                                                                                           
18/02  U-2400  9.8100163  STANLY       951,367.50  RWY                0.000   0    0   0  S S UR C B       2  10  68    ALBEMARLE                                                                                                                              
18/03  U-2400  9.8100163  STANLY        55,901.42  CLV                0.000   1    1  12  S S UR C B       2  10  68    56+15.00-L-R                                                                                                                           
18/04  U-2400  9.8100163  STANLY       278,265.46  CLV                0.007   1    3   8  S S UR C B       2  10  68    174+02.0-L-R                                                                                                                           
18/05  U-2400  9.8100163  STANLY       575,857.80  BRG             I  0.023   3  745  12  S S UR C B       2  10  68    153+13.99-L-                                                                                                                           
                   PROJECT TOTAL =   8,317,320.86   BRANCH HIGHWAYS, INC.                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
19/01          5.5021154  ORANGE       258,047.90  SUR          33    7.900   2    0   0  S                2   7  50    MAPS 1-3                                                                                                                               
19/02          7.5011192  ORANGE       407,958.22  SUR          35   11.520   2    0   0  S                2   7  50    MAPS 4-7                                                                                                                               
19/03          7.5021192  ORANGE       433,092.40  SUR          60    7.270   2    0   0  S                2   7  50    MAPS 8-10                                                                                                                              
19/04          7.5070292  ORANGE        25,771.17  SUR          54    0.480   2    0   0  S                2   7  50    MAPS 11                                                                                                                                
19/05          7.5070392  ORANGE       351,295.25  SUR          98    3.580   2    0   0  S                2   7  50    MAPS 12-15                                                                                                                             
19/06          7.5071192  ORANGE        69,432.71  SUR          77    0.900   2    0   0  S                2   7  50    MAPS 16                                                                                                                                
19/07          7.5071692  ORANGE         8,642.20  SUR          86    0.100   2    0   0  S                2   7  50    MAPS 17                                                                                                                                
                   PROJECT TOTAL =   1,554,239.85   BLYTHE CONSTRUCTION, I                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
22/01          5.5221083  CHATHAM       95,725.30  SUR          28    3.410   2    0   0  S                2   8  52    MAP 3                                                                                                                                  
22/02          7.5211037  CHATHAM      108,465.53  SUR          45    2.400   2    0   0  S                2   8  52    MAPS 1-2                                                                                                                               
22/03          7.5221037  CHATHAM      306,404.00  SUR          27   11.150   2    0   0  S                2   8  52    MAPS 3-12                                                                                                                              
22/04          7.5273037  CHATHAM       20,356.57  SUR          70    0.290   2    0   0  S                2   8  52    MAP 13                                                                                                                                 
22/05          5.5411079  LEE           65,178.62  SUR          14    4.550   2    0   0  S                2   8  54    MAPS 1,2,4                                                                                                                             
22/06          5.5421079  LEE            7,000.00  SUR                0.000   0    0   0  S                2   8  54                                                                                                                                           
22/07          5.5473779  LEE           17,250.00  SUR          18    0.970   2    0   0  S                2   8  54    MAPS 12,18                                                                                                                             
22/08          7.5411036  LEE          261,421.93  SUR          40    6.500   2    0   0  S                2   8  54    MAPS 1-5                                                                                                                               
22/09          7.5421036  LEE          131,354.98  SUR          24    5.440   2    0   0  S                2   8  54    MAPS 6-10                                                                                                                              
22/10          7.5473736  LEE          341,552.41  SUR          68    5.020   2    0   0  S                2   8  54    MAPS 11-20                                                                                                                             
                   PROJECT TOTAL =   1,354,709.34   LEE PAVING COMPANY                                                                                                                                                                                         
                                                                                                                                                                                                                                                               
23/01          5.5521082  MONTGOMER     30,131.80  SUR           8    3.600   2    0   0  S                2   8  55    MAP 3                                                                                                                                  
23/02          7.5511038  MONTGOMER    180,378.26  SUR          34    5.320   2    0   0  S                2   8  55    MAP 1-2                                                                                                                                
23/03          7.5521038  MONTGOMER    166,298.50  SUR          28    5.950   2    0   0  S                2   8  55    MAP 3-7                                                                                                                                
23/04          7.5570538  MONTGOMER     71,608.83  SUR          93    0.770   2    0   0  S                2   8  55    MAP 8-10                                                                                                                               
23/05          7.5572638  MONTGOMER     60,205.74  SUR          48    1.250   2    0   0  S                2   8  55    MAP 11-12                                                                                                                              
23/06          7.5574438  MONTGOMER     79,722.52  SUR          35    2.280   2    0   0  S                2   8  55    MAP 13-18                                                                                                                              
                   PROJECT TOTAL =     588,345.65   MOFFITT & PIERCE CONST                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  5                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
                                                                                                                                                                                                                                                               
24/01          5.5621083  MOORE         98,492.00  SUR          23    4.300   2    0   0  S                2   8  56    MAP 3                                                                                                                                  
24/02          7.5611035  MOORE        365,004.50  SUR          38    9.680   2    0   0  S                2   8  56    MAP 1                                                                                                                                  
24/03          7.5621035  MOORE        367,590.00  SUR          29   12.500   2    0   0  S                2   8  56    MAPS 2-9                                                                                                                               
24/04          7.5670135  MOORE         13,593.50  SUR          38    0.360   2    0   0  S                2   8  56    MAPS 10                                                                                                                                
24/05          7.5674035  MOORE        102,930.75  SUR          90    1.150   2    0   0  S                2   8  56    MAP 11-12                                                                                                                              
                   PROJECT TOTAL =     947,610.75   HIGHWAY CONSTRUCTORS,                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
25/01          5.5721082  RANDOLPH      96,488.59  SUR          31    3.100   2    0   0  S                2   8  57    MAP 6,7,8                                                                                                                              
25/02          7.5711045  RANDOLPH     427,269.71  SUR          40   10.660   2    0   0  S                2   8  57    MAPS 1-5                                                                                                                               
25/03          7.5721045  RANDOLPH     529,211.55  SUR          24   21.700   2    0   0  S                2   8  57    MAPS 6-29                                                                                                                              
25/04          7.5770245  RANDOLPH      51,452.64  SUR          30    1.740   2    0   0  S                2   8  57    MAPS 30-32                                                                                                                             
25/05          7.5770345  RANDOLPH     277,220.47  SUR          75    3.700   2    0   0  S                2   8  57    MAPS 33-38                                                                                                                             
25/06          7.5773245  RANDOLPH      13,735.40  SUR          38    0.360   2    0   0  S                2   8  57    MAP 39                                                                                                                                 
                   PROJECT TOTAL =   1,395,378.36   MOFFITT & PIERCE CONST                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
28/01          7.5321034  HOKE         125,403.50  SUR          23    5.370   2    0   0  S                2   8  53    MAPS 1-13                                                                                                                              
28/02          7.5911033  SCOTLAND     152,860.00  SUR          49    3.100   2    0   0  S                2   8  59    MAP 1                                                                                                                                  
28/03          7.5921033  SCOTLAND     174,727.00  SUR          22    7.850   2    0   0  S                2   8  59    MAPS 2-7                                                                                                                               
28/04          7.5972133  SCOTLAND      55,159.50  SUR          45    1.220   2    0   0  S                2   8  59    MAPS 8-11                                                                                                                              
                   PROJECT TOTAL =     508,150.00   HIGHWAY CONSTRUCTORS,                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
29/01          7.5811037  RICHMOND     136,540.50  SUR          50    2.720   2    0   0  S                2   8  58    MAPS 1-2                                                                                                                               
29/02          7.5821037  RICHMOND     223,730.00  SUR          21   10.500   2    0   0  S                2   8  58    MAPS 3-11                                                                                                                              
29/03          7.5871637  RICHMOND      89,173.00  SUR          78    1.140   2    0   0  S                2   8  58    MAPS 12-13                                                                                                                             
29/04          7.5871837  RICHMOND      39,632.00  SUR          45    0.880   2    0   0  S                2   8  58    MAP 14                                                                                                                                 
29/05          7.5873637  RICHMOND      24,237.50  SUR          61    0.400   2    0   0  S                2   8  58    MAPS 15-16                                                                                                                             
29/06          7.5874937  RICHMOND      34,572.00  SUR          38    0.920   2    0   0  S                2   8  58    MAP 17                                                                                                                                 
                   PROJECT TOTAL =     547,885.00   HIGHWAY CONSTRUCTORS,                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
30/01          5.7021091  ALLEGHANY     41,530.12  SUR          10    4.000   2    0   0  S                3  11  70    MAPS 1-5                                                                                                                               
30/02          5.7221091  AVERY         77,704.46  SUR          10    7.700   2    0   0  S                4  11  72    MAPS 6-15                                                                                                                              
30/03          7.7021203  ALLEGHANY    152,566.09  SUR          10   14.610   2    0   0  S                3  11  70    MAPS 16-25                                                                                                                             
30/04          7.7121203  ASHE         257,436.27  SUR          10   25.550   2    0   0  S                4  11  71    MAPS 26-55                                                                                                                             
30/05          7.7221203  AVERY         70,218.48  SUR          10    7.350   2    0   0  S                4  11  72    MAPS 56-67                                                                                                                             
30/06          7.7521203  WATAUGA      199,315.06  SUR          10   19.210   2    0   0  S                4  11  75    MAPS 68-94                                                                                                                             
                   PROJECT TOTAL =     798,770.48   MAYMEAD, INC.                                                                                                                                                                                              
                                                                                                                                                                                                                                                               
31/01          5.7421092  SURRY        151,693.58  SUR          11   14.120   2    0   0  S                2  11  74    MAPS 1-17                                                                                                                              
31/02          5.7621092  WILKES        56,217.76  SUR          11    5.260   2    0   0  S                3  11  76    MAPS 18-21                                                                                                                             
31/03          5.7721092  YADKIN        16,582.91  SUR           9    1.900   2    0   0  S                2  11  77    MAPS 22                                                                                                                                
31/04          7.7321204  CALDWELL      76,177.34  SUR          10    7.650   2    0   0  S                3  11  73    MAPS 23-39                                                                                                                             
31/05          7.7421204  SURRY         93,372.79  SUR          10    9.790   2    0   0  S                2  11  74    MAPS 40-44                                                                                                                             
31/06          7.7621204  WILKES       211,997.73  SUR          10   20.230   2    0   0  S                3  11  76    MAPS 45-59                                                                                                                             
31/07          7.7721204  YADKIN       201,695.11  SUR          10   19.920   2    0   0  S                2  11  77    MAPS 60-78                                                                                                                             
                   PROJECT TOTAL =     807,737.22   MAYMEAD, INC.                                                                                                                                                                                              
                                                                                                                                                                                                                                                               
32/01          7.7011199  ALLEGHANY    329,171.30  SUR          57    5.790   2    0   0  S                3  11  70    MAPS 1-2                                                                                                                               
32/02          7.7021199  ALLEGHANY      5,492.50  SUR          32    0.170   2    0   0  S                3  11  70    MAPS 3                                                                                                                                 
32/03          7.7111199  ASHE         567,097.00  SUR          70    8.060   2    0   0  S                4  11  71    MAPS 5-7                                                                                                                               
32/04          7.7171399  ASHE         184,984.00  SUR         157    1.180   2    0   0  S                4  11  71    MAPS 8-9                                                                                                                               
32/05          9.8112517  ALLEGHANY     66,213.60  SUR          60    1.100   2    0   0  S                3  11  70    MAP 5                                                                                                                                  
                   PROJECT TOTAL =   1,152,958.40   JAMES R. VANNOY & SONS                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
33/01          7.7211200  AVERY        253,981.12  SUR          54    4.720   2    0   0  S                4  11  72    MAPS 1-2                                                                                                                               
33/02          7.7221200  AVERY         35,729.61  SUR          37    0.960   2    0   0  S                4  11  72    MAPS 3-4                                                                                                                               
33/03          7.7511200  WATAUGA      283,970.62  SUR          69    4.100   2    0   0  S                4  11  75    MAPS 7-8                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  6                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
33/04          7.7521200  WATAUGA       38,054.30  SUR          33    1.150   2    0   0  S                4  11  75    MAPS 9                                                                                                                                 
33/05          7.7570400  WATAUGA       36,718.46  SUR          52    0.710   2    0   0  S                4  11  75    MAPS 10                                                                                                                                
33/06          9.8113203  AVERY         35,214.78  SUR          39    0.900   2    0   0  S                4  11  72    MAPS 5-6                                                                                                                               
                   PROJECT TOTAL =     683,668.89   MAYMEAD, INC.                                                                                                                                                                                              
                                                                                                                                                                                                                                                               
34/01  U-2061  7.7311201  CALDWELL     407,234.27  SUR          93    4.360   2    0   0  S                3  11  73    MAPS 1-4                                                                                                                               
34/02  U-2061  7.7321201  CALDWELL     187,172.24  SUR          32    5.780   2    0   0  S                3  11  73    MAPS 5-7                                                                                                                               
34/03  U-2061  7.7371101  CALDWELL     247,225.39  SUR         106    2.340   2    0   0  S                3  11  73    MAP 8                                                                                                                                  
34/04  U-2061  7.7371201  CALDWELL     144,855.14  SUR         115    1.260   2    0   0  S                3  11  73    MAP 9                                                                                                                                  
34/05  U-2061  7.7371501  CALDWELL     432,547.78  SUR          87    4.990   2    0   0  S                3  11  73    MAPS 10-11                                                                                                                             
34/06  U-2061  7.7611201  WILKES       638,908.62  SUR          72    8.880   2    0   0  S                3  11  76    MAPS 12-15                                                                                                                             
34/07  U-2061  7.7621201  WILKES       392,162.01  SUR          38   10.200   2    0   0  S                3  11  76    MAPS 16-21                                                                                                                             
34/08  U-2061  7.7671901  WILKES        73,870.56  SUR         137    0.540   2    0   0  S                3  11  76    MAPS 22-23                                                                                                                             
34/09  U-2061  7.7672901  WILKES        49,042.36  SUR          77    0.640   2    0   0  S                3  11  76    MAPS 24                                                                                                                                
34/10  U-2061  9.8112940  WILKES        34,110.37  SUR         162    0.210   2    0   0  S                3  11  76    MASP 25                                                                                                                                
                   PROJECT TOTAL =   2,607,128.74   MIDSTATE CONTRACTORS,                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
35/01  U-2061  7.7411202  SURRY        715,019.22  SUR          58   12.280   2    0   0  S                2  11  74    MAPS 1-5                                                                                                                               
35/02  U-1961  7.7421202  SURRY        495,995.71  SUR          38   13.160   2    0   0  S                2  11  74    MAPD 6-12                                                                                                                              
35/03  U-1961  7.7470902  SURRY         94,163.00  SUR          66    1.430   2    0   0  S                2  11  74    MAPS 13-14                                                                                                                             
35/04  U-1961  7.7471702  SURRY         74,888.36  SUR          57    1.320   2    0   0  S                2  11  74    MAPS 15-17                                                                                                                             
35/05  U-1961  7.7711202  YADKIN       450,812.00  SUR          85    5.320   2    0   0  S                2  11  77    MAPS 21-22                                                                                                                             
35/06  U-1961  7.7721202  YADKIN       191,889.31  SUR          35    5.550   2    0   0  S                2  11  77    MAPS 23-25                                                                                                                             
35/07  U-1961  7.7770502  YADKIN        50,557.63  SUR          75    0.670   2    0   0  S                2  11  77    MAPS 26                                                                                                                                
35/08  U-1961  7.7770802  YADKIN        11,474.78  SUR          36    0.320   2    0   0  S                2  11  77    MAPS 27                                                                                                                                
35/09  U-1961  7.7771402  YADKIN       276,227.68  SUR         142    1.950   2    0   0  S                2  11  77    MAPS 28                                                                                                                                
35/10  U-1961  7.7773002  YADKIN        78,602.16  SUR          54    1.450   2    0   0  S                2  11  77    MAPS 29-30                                                                                                                             
35/11  U-2061  9.8110720  SURRY         46,903.77  SUR          72    0.650   2    0   0  S                2  11  74    MAPS 18-19                                                                                                                             
35/12  U-1961  9.8111763  SURRY         29,198.70  SUR          49    0.600   2    0   0  S                2  11  74    MAP 20                                                                                                                                 
                   PROJECT TOTAL =   2,515,732.32   CARL ROSE & SONS, INC.                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
36/01          7.8211234  IREDELL      162,446.25  SUR          57    2.840   2    0   0  S                2  12  82    MAPS 1-2                                                                                                                               
36/02          7.8221234  IREDELL      968,374.62  SUR          44   21.990   2    0   0  S                2  12  82    MAPS 3-40                                                                                                                              
36/03          7.8273134  IREDELL       88,032.07  SUR          54    1.630   2    0   0  S                2  12  82    MAPS 41-44                                                                                                                             
                   PROJECT TOTAL =   1,218,852.94   CENTRAL CAROLINA DIVIS                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
37/01          7.8411187  BUNCOMBE     803,544.36  SUR          89    9.070   2    0   0  S                3  13  84    MAPS 1-2                                                                                                                               
37/02          7.8421187  BUNCOMBE     699,526.40  SUR          38   18.210   2    0   0  S                3  13  84    MAPS 3-19                                                                                                                              
37/03          7.8470287  BUNCOMBE     227,890.15  SUR          63    3.640   2    0   0  S                3  13  84    MAPS 20-25                                                                                                                             
37/04          7.8472687  BUNCOMBE      14,319.95  SUR          89    0.160   2    0   0  S                3  13  84    MAPS 26                                                                                                                                
37/05          9.8130526  BUNCOMBE      52,410.35  SUR          32    1.640   2    0   0  S                3  13  84    MAPS 27                                                                                                                                
                   PROJECT TOTAL =   1,797,691.21   ASHEVILLE DIVISION,                                                                                                                                                                                        
                                                                                                                                                                                                                                                               
38/01          7.8511188  BURKE        559,900.58  SUR          54   10.440   2    0   0  S                3  13  85    MAPS 1-4                                                                                                                               
38/02          7.8521188  BURKE        576,528.76  SUR          41   14.000   2    0   0  S                3  13  85    MAPS 5-23                                                                                                                              
38/03          7.8570888  BURKE         17,057.78  SUR          43    0.400   2    0   0  S                3  13  85    MAPS 24                                                                                                                                
38/04          7.8571288  BURKE         10,686.62  SUR          43    0.250   2    0   0  S                3  13  85    MAPS 25                                                                                                                                
38/05          7.8571988  BURKE        149,040.09  SUR          47    3.190   2    0   0  S                3  13  85    MAPS 26-28                                                                                                                             
38/06          7.8572588  BURKE         14,067.08  SUR          43    0.330   2    0   0  S                3  13  85    MAPS 29                                                                                                                                
38/07          7.8579788  BURKE         45,066.53  SUR          43    1.060   2    0   0  S                3  13  85    MAPS 30                                                                                                                                
                   PROJECT TOTAL =   1,372,347.44   MIDSTATE CONTRACTORS,                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
39/01          7.8611186  MADISON      308,522.15  SUR          49    6.340   2    0   0  S                4  13  86    MAPS 1-3                                                                                                                               
39/02          7.8621186  MADISON      152,271.05  SUR          41    3.700   2    0   0  S                4  13  86    MAPS 4-7                                                                                                                               
39/03          7.8671386  MADISON       84,165.20  SUR          53    1.580   2    0   0  S                4  13  86    AMSP 8-9                                                                                                                               
39/04          7.9011186  YANCEY       719,476.45  SUR          40   17.920   2    0   0  S                4  13  90    MAPS 10-12                                                                                                                             
39/05          7.9021186  YANCEY        78,059.85  SUR          35    2.200   2    0   0  S                4  13  90    MAPS 13-14                                                                                                                             
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  7                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
39/06          7.9070786  YANCEY       150,975.60  SUR          85    1.780   2    0   0  S                4  13  90    MAPS 15                                                                                                                                
                   PROJECT TOTAL =   1,493,470.30   ASHEVILLE DIVISION,                                                                                                                                                                                        
                                                                                                                                                                                                                                                               
40/01          7.8711190  MCDOWELL     673,870.54  SUR          49   13.670   2    0   0  S                3  13  87    MAPS 1-4                                                                                                                               
40/02          7.8721190  MCDOWELL     173,941.73  SUR          43    4.020   2    0   0  S                3  13  87    MAPS 5-9                                                                                                                               
40/03          7.8771690  MCDOWELL      38,137.10  SUR          50    0.760   2    0   0  S                3  13  87    MAPS 10                                                                                                                                
40/04          7.8772090  MCDOWELL      38,803.42  SUR          54    0.720   2    0   0  S                3  13  87    MAPS 11                                                                                                                                
40/05          7.8811190  MITCHELL     211,388.65  SUR          43    4.870   2    0   0  S                4  13  88    MAPS 12-14                                                                                                                             
40/06          7.8821190  MITCHELL      73,916.22  SUR          41    1.800   2    0   0  S                4  13  88    MAPS 15-17                                                                                                                             
40/07          7.8870390  MITCHELL      17,120.33  SUR          46    0.370   2    0   0  S                4  13  88    MAPS 18                                                                                                                                
40/08          7.8872490  MITCHELL      23,940.70  SUR          41    0.580   2    0   0  S                4  13  88    MAPS 19                                                                                                                                
                   PROJECT TOTAL =   1,251,118.69   ASHEVILLE DIVISION,                                                                                                                                                                                        
                                                                                                                                                                                                                                                               
41/01          7.8911189  RUTHERFOR    729,529.71  SUR          52   13.900   2    0   0  S                3  13  89    MAPS 1-4                                                                                                                               
41/02          7.8921189  RUTHERFOR    463,565.97  SUR          44   10.500   2    0   0  S                3  13  89    MAPS 5-11                                                                                                                              
41/03          7.8971089  RUTHERFOR     76,990.43  SUR          47    1.640   2    0   0  S                3  13  89    MAPS 12-13                                                                                                                             
41/04          7.8972389  RUTHERFOR     25,832.94  SUR          47    0.550   2    0   0  S                3  13  89    MAPS 14                                                                                                                                
                   PROJECT TOTAL =   1,295,919.05   THOMPSON CONTRACTORS,                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
                         *****  FEB 1997 TOTAL = $48,988,126.21                                                                                                                                                                                                
                                                                                                                                                                                                                                                               
*****  MAR 1997  *****                                                                                                                                                                                                                                         
                                                                                                                                                                                                                                                               
12/01  U-2302  8.1501003  ORANGE     5,638,751.39  RWY  STP  2,759    2.044   5  634   0  S   U  CW        2   7  50    10+00-117+00                                                                                                                           
12/02  U-2302  8.1501003  ORANGE        49,987.30  RWY  STP           0.000   0    0   0  S   U  CW        2   7  50    OWASA COST                                                                                                                             
12/03  U-2302  8.1501003  ORANGE       118,955.70  CLV  STP           0.000   1    2  11  S   U  CW        2   7  50    99+30 -L-REV                                                                                                                           
                   PROJECT TOTAL =   5,807,694.39   RIFENBURG CONSTRUCTION                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
13/01  R-2218  8.T521103  CHATHAM    9,514,232.77  RWY  NHF  1,763    5.396   4    0   0         C         2   8  52                                                                                                                                           
13/02  R-2218  8.T521103  CHATHAM       49,529.96  CLV  NHF           0.000   1  201  35         C         2   8  52    274+62.91-LM                                                                                                                           
13/03  R-2218  8.T521103  CHATHAM       76,190.87  CLV  NHF           0.000   1  201  28         C         2   8  52    329+04.57-LM                                                                                                                           
13/04  R-2218  8.T521103  CHATHAM       97,968.36  CLV  NHF           0.000   1  202  19         C         2   8  52    338+11.53-LM                                                                                                                           
13/05  R-2218  8.T521103  CHATHAM        8,825.08  CLV  NHF           0.000   1  201  11         C         2   8  52    353+62.22-LM                                                                                                                           
13/06  R-2218  8.T521103  CHATHAM       39,255.57  CLV  NHF           0.000   1  201   8         C         2   8  52    396+50.98-LM                                                                                                                           
13/07  R-2218  8.T521103  CHATHAM       30,037.42  CLV  NHF           0.000   1  201   5         C         2   8  52    406+57.70-LM                                                                                                                           
13/08  R-2218  8.T521103  CHATHAM       57,191.28  CLV  NHF           0.000   1  201   4         C         2   8  52    413+26.07-LM                                                                                                                           
13/09  R-2218  8.T521103  CHATHAM       29,133.34  CLV  NHF           0.000   1  201   5         C         2   8  52    417+80.48-LM                                                                                                                           
13/10  R-2218  8.T521103  CHATHAM       34,796.44  CLV  NHF           0.000   1  201  17         C         2   8  52    467+33.65-LM                                                                                                                           
                   PROJECT TOTAL =   9,937,161.09   BROWN & ROOT, INC.                                                                                                                                                                                         
                                                                                                                                                                                                                                                               
15/01  R-2224  6.961021   JACKSON    1,072,517.18  RWY       1,469    0.730   2    0   0   LS U            4  14  96                                                                                                                                           
                   PROJECT TOTAL =   1,072,517.18   PHILLIPS & JORDAN, INC                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
16/01          7.0371043  CHOWAN        69,384.12  SUR          63    1.100   2    0   0  S                1   1   3    MAPS 1-4                                                                                                                               
16/02          7.0821243  HYDE          56,694.53  SUR          25    2.250   2    0   0  S                1   1   8    MAPS 5-6                                                                                                                               
16/03          7.0911243  MARTIN       528,430.94  SUR          48   11.070   2    0   0  S                1   1   9    MAPS 7-14                                                                                                                              
16/04          7.0921243  MARTIN        73,676.79  SUR          25    2.900   2    0   0  S                1   1   9    MAPS 15-16                                                                                                                             
16/05          7.0974043  MARTIN       230,160.37  SUR          85    2.710   2    0   0  S                1   1   9    MAPS 17-22                                                                                                                             
16/06          7.1321243  TYRRELL       87,535.17  SUR          34    2.600   2    0   0  S                1   1  13    MAPS 23-24                                                                                                                             
16/07          7.1411243  WASHINGTN    532,821.96  SUR          31   17.100   2    0   0  S                1   1  14    MAPS 25-27                                                                                                                             
16/08          7.1421243  WASHINGTN     50,693.94  SUR          27    1.900   2    0   0  S                1   1  14    MAPS 28                                                                                                                                
16/09          7.1473243  WASHINGTN     13,387.09  SUR          33    0.400   2    0   0  S                1   1  14    MAPS 29-30                                                                                                                             
                   PROJECT TOTAL =   1,642,784.91   NELLO L. TEER COMPANY                                                                                                                                                                                      
                                                                                                                                                                                                                                                               
17/01  E-3600  7.0511242  DARE          65,992.05  SUR  STP    183    0.360   2    0   0  S                1   1   5    MAP 1                                                                                                                                  
17/02  U-2651  7.0521242  DARE         138,443.60  SUR          31    4.450   2    0   0  S                1   1   5    MAPS 2-20                                                                                                                              
17/03  U-2651  7.0572642  DARE           2,079.80  SUR          35    0.060   2    0   0  S                1   1   5    MAPS 21                                                                                                                                
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
                                                                                                                                                                                                                                                               
              NORTH CAROLINA DEPARTMENT OF TRANSPORTATION        PAGE  8                                                                                                                                                                                       
                                                                                                                                                                                                                                                               
PROPOS T.I.P.   PROJECT   COUNTY         $ TOTAL   JOB  FUND  THOU$    PROJ  DESCRIPTION   WORK TYPES    AREA    CNTY   LOCATION                                                                                                                               
NO/BRK  NO.                                                   /MILE   MILES  NO. CD1 CD2  GDPFSLSLURACWB     DIVS                                                                                                                                              
17/04  E-3600  8.2050901  DARE         690,782.15  SUR  STP     95    7.300   2    0   0  S                1   1   5    MAPS 22-23                                                                                                                             
17/05  U-2651  9.8014824  DARE          10,589.00  SUR          30    0.350   2    0   0  S                1   1   5    MAPS 24-25                                                                                                                             
                   PROJECT TOTAL =     907,886.60   BARNHILL CONTRACTING C                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
18/01          7.0611241  GATES        849,583.06  SUR          41   20.900   2    0   0  S                1   1   6    MAPS 1-5                                                                                                                               
18/02          7.0621241  GATES        156,712.14  SUR          25    6.270   2    0   0  S                1   1   6    MAPS 6-8                                                                                                                               
18/03          7.1221241  PERQUIMAN    154,967.98  SUR          23    6.700   2    0   0  S                1   1  12    MAPS 9-11                                                                                                                              
18/04          7.1272041  PERQUIMAN     18,068.08  SUR         100    0.180   2    0   0  S                1   1  12    MAP 12                                                                                                                                 
                   PROJECT TOTAL =   1,179,331.26   ROSE BROTHERS PAVING C                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
19/01          7.2411111  DUPLIN     1,252,722.70  SUR         111   11.250   2    0   0  S                1   3  24    MAPS 1-2                                                                                                                               
19/02          7.2421111  DUPLIN       628,263.50  SUR          50   12.600   2    0   0  S                1   3  24    MAPS 3-8                                                                                                                               
19/03          7.2470311  DUPLIN        66,693.75  SUR          74    0.900   2    0   0  S                1   3  24    MAPS 9-10                                                                                                                              
                   PROJECT TOTAL =   1,947,679.95   BARRUS CONSTRUCTION CO                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
20/01          7.2811111  SAMPSON    1,029,192.48  SUR          95   10.850   2    0   0  S                1   3  28    MAPS 11-13                                                                                                                             
20/02          7.2821111  SAMPSON      528,179.10  SUR          41   12.790   2    0   0  S                1   3  28    MAPS 14-20                                                                                                                             
20/03          7.2870211  SAMPSON       20,802.16  SUR          30    0.700   2    0   0  S                1   3  28    MAP 21                                                                                                                                 
20/04          7.2870911  SAMPSON       53,323.64  SUR          46    1.150   2    0   0  S                1   3  28    MAPS 22-24                                                                                                                             
20/05          7.2871211  SAMPSON       64,365.88  SUR          64    1.000   2    0   0  S                1   3  28    MAPS 25                                                                                                                                
                   PROJECT TOTAL =   1,695,863.26   BARNHILL CONTRACTING C                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
24/01          7.2911184  EDGECOMBE    473,913.08  SUR          44   10.710   2    0   0  S                2   4  29    MAPS 1-4                                                                                                                               
24/02          7.2921184  EDGECOMBE    275,546.60  SUR          23   12.240   2    0   0  S                2   4  29    MAPS 5-8                                                                                                                               
24/03          7.2974184  EDGECOMBE    158,465.14  SUR          75    2.120   2    0   0  S                2   4  29    MAPS 9-12                                                                                                                              
24/04          7.3011185  HALIFAX      575,359.57  SUR          40   14.360   2    0   0  S                2   4  30    MAPS 1-5                                                                                                                               
24/05          7.3021185  HALIFAX      164,467.80  SUR          21    7.880   2    0   0  S                2   4  30    MAPS 6-9                                                                                                                               
24/06          7.3071585  HALIFAX       40,114.70  SUR          44    0.910   2    0   0  S                2   4  30    MAPS 10                                                                                                                                
24/07          7.3073085  HALIFAX       32,831.56  SUR          50    0.660   2    0   0  S                2   4  30    MAPS 11-14                                                                                                                             
24/08          7.3073385  HALIFAX      111,351.30  SUR          89    1.250   2    0   0  S                2   4  30    MAPS 15-20                                                                                                                             
24/09          7.3074285  HALIFAX       19,338.58  SUR          36    0.530   2    0   0  S                2   4  30    MAP 21                                                                                                                                 
24/10          7.3211187  NASH         384,866.74  SUR          74    5.230   2    0   0  S                2   4  32    MAPS 1-2                                                                                                                               
24/11          7.3221187  NASH         246,826.40  SUR          22   11.480   2    0   0  S                2   4  32    MAPS 3-7                                                                                                                               
24/12          7.3270587  NASH          17,175.50  SUR          23    0.760   2    0   0  S                2   4  32    MAP 8                                                                                                                                  
24/13          7.3272387  NASH          10,903.38  SUR          61    0.180   2    0   0  S                2   4  32    MAP 9                                                                                                                                  
24/14          7.3273187  NASH         673,478.73  SUR         131    5.140   2    0   0  S                2   4  32    MAPS 10-15                                                                                                                             
24/15          7.3274387  NASH          31,737.83  SUR          88    0.360   2    0   0  S                2   4  32    MAP 16                                                                                                                                 
                   PROJECT TOTAL =   3,216,376.91   BARNHILL CONTRACTING C                                                                                                                                                                                     
                                                                                                                                                                                                                                                               
25/01          7.3111186  JOHNSTON     900,616.00  SUR          79   11.360   2    0   0  S                2   4  31    MAPS 1-3                                                                                                                               
25/02          7.3121186  JOHNSTON     633,967.25  SUR          29   21.710   2    0   0  S                2   4  31    MAPS 4-13