MASTER FOR 2002 SPECS
GENERAL CONSTRUCTION PROJECTS


GENERAL

SP1G01 PROJECT SPECIAL PROVISIONS - General
SP1G04 CONTRACT TIME AND LIQUIDATED DAMAGES
The date of availability for this contract is _________________________________
The completion date for this contract is _________________________________
The liquidated damages for this contract time are $________________________________ per calendar day.
(ANY type of permit)
SP1G05 CONTRACT TIME AND LIQUIDATED DAMAGES (Floating Availability Dates)
(ANY type of permit)
SP1G07 CONTRACT TIME AND LIQUIDATED DAMAGES
The date of availability for this contract is _________________________________
The completion date for this contract is _________________________________
The liquidated damages for this contract time are $________________________________ per calendar day.
(ICT for REFORESTATION and Any type of Permit)
SP1G10 CONTRACT TIME AND LIQUIDATED DAMAGES (7-1-95)
The date of availability for this contract is _________________________________
The completion date for this contract is _________________________________
The liquidated damages for this contract time are $________________________________ per calendar day.
SP1G13 INTERMEDIATE CONTRACT TIME NUMBER AND LIQ. DAMAGES
All work except reforestation completed by _________________________________
The date of availability for this work is _________________________________
The liquidated damages for this intermediate contract time are $________________________________ per calendar day.
SP1G14 SAFETY INDEX RATING (All Projects)
SP1G16 MANDATORY PRE-BID CONFERENCE: PREQUALIFYING TO BID
SP1G19 PRE-BID CONFERENCE
SP1G22 DELAY IN RIGHT OF ENTRY
SP1G25 NOTICE TO BIDDERS (Cluster Projects)
SP1G28 MAJOR CONTRACT ITEMS
Line #                                                Description
______________________      ________________________________
______________________      ________________________________
______________________      ________________________________
______________________      ________________________________
______________________      ________________________________
______________________      ________________________________
SP1G31 NO MAJOR CONTRACT ITEMS
SP1G34 NO SPECIALITY ITEMS
SP1G37 SPECIALITY ITEMS
Line #                                        Description
______________________      Guardrail Items
______________________      Fencing Items
______________________      Signing Items
______________________      Long-Life Pavement Markings
______________________      Pavement Markers
______________________      Lighting Items
______________________      Utility Construction Items
______________________      Erosion Control Items
______________________      Reforestation Items
______________________      Planting Items
______________________      Rest Area Items
______________________      Signal Items
______________________      ITS System Items
______________________      Drilled Piers
SP1G40 SPECIAL REQUIREMENTS FOR WORK IN NATIONAL FOREST
SP1G43 FUEL PRICE ADJUSTMENT (English)
SP1G46 FUEL PRICE ADJUSTMENT (Metric)
SP1G49 PARTNERING
SP1G58 SCHEDULE OF ESTIMATED COMPLETION PROGRESS
SP1G60 ON-LINE ELECTRONIC BIDDING
SP1G61 DISADVANTAGED BUSINESS ENTERPRISES (with Goals)________ %
SP1G64 DISADVANTAGED BUSINESS ENTERPRISES (0.0% Goals)
SP1G67 MINORITY AND WOMEN BUSINESSES (with goals)
MB ____________ %
WB ____________ %
SP1G70 MINORITY AND WOMEN BUSINESSES (without goals)
SP1G73 RETAINAGE AND PROMPT PAYMENT
(FEDERAL AID PROJECTS)
SP1G75 MENTOR-PROTÉGÉ PROGRAM
(When requested by the Proposals and Contract Engineer)
SP1G76 PROMPT PAYMENT (STATE FUNDED PROJECTS)
SP1G82 PARTIAL PAYMENTS (STATE FUNDED PROJECTS)
SP1G85 CERTIFICATION FOR FEDERAL-AID CONTRACTS (F.A. Only)
SP1G88 CONTRACTOR'S LICENSES REQUIREMENTS
Use on roadway, rest area, weigh station, project signal work, and lighting projects when heating, plumbing, air conditioning, or electrical work is included in the projects.
SP1G91 SUBMISSION OF BIDS - ALTERNATES
SP1G95 RECYCLED STEEL  *Deleted July 2006 letting*
SP1G97 DOMESTIC STEEL AND IRON PRODUCTS (All Projects)
SP1G100 U.S. DEPARTMENT OF TRANSPORTATION HOTLINE (F.A. Only)
SP1G103 SUBMISSION OF RECORDS - FEDERAL-AID PROJECTS (BRZ)
SP1G106 SUBMISSION OF RECORDS - FEDERAL-AID PROJECTS (on NHS + 1 million project cost)
SP1G109 SUBMISSION OF RECORDS - FEDERAL-AID PROJECTS (not on NHS)
SP1G110 COMPENSATION AND RECORD KEEPING (All Projects)
SP1G111 CONTRACTOR BORROW SOURCE
SP1G112 SUBSURFACE INFORMATION (Is not available)
SP1G115 SUBSURFACE INFORMATION (Roadway)
SP1G118 SUBSURFACE INFORMATION (Structures)
SP1G119 SUBSURFACE INFORMATION (Roadway & Structures)
SP1G120 BORROW AND WASTE SITE RECLAMATION PROCEDURES
SP1G121 PAYMENTS FOR MATERIALS - PORTABLE CONCRETE BARRIER
SP1G124 PAYMENTS FOR MATERIALS - REMOVABLE PAVEMENT MARKING MATERIAL
SP1G130 PLANT PEST QUARANTINE
SP1G133 COOPERATION BETWEEN CONTRACTORS
SP1G136 TRAINING REQUIREMENTS
__________Trainees
SP1G139 SAFETY VESTS (All Projects)
SP1G142 BID DOCUMENTATION
SP1G143 DIRECTOR OF CONSTRUCTION IN LIEU OF CHIEF ENGINEER
SP1G145 TWELVE MONTH GUARANTEE - TIP ONLY
SP1G150 OUTSOURCING OUTSIDE THE USA
SP1G151 ACT OF GOD - DEC 2002 LET
SP1G155 DISQUALIFICATION OF BIDDERS
SP1G160 CRANE SAFETY
SP1G165 FORCE ACCOUNT
SP1G170 CONTROL OF EROSION, SILTATION AND POLLUTION
SP1G175 REJECTION OF BIDS
SP1G180 EROSION & SEDIMENT CONTROL STORMWATER CERTIFICATION
   
ROADWAY  
   
SP1R01 PROJECT SPECIAL PROVISONS - Roadway
SP2R01 CLEARING AND GRUBBING
Method"____________"shown on Standard No._________
SP2R02 CLEARING AND GRUBBING
Method"____________"as detailed in the plans
SP2R05 BURNING RESTRICTIONS
SP2R10 DEMOLITION OF BUILDINGS AND APPURTENANCES
SP2R15 BUILDING AND UNDERGROUND STORAGE TANK REMOVAL
SP2R18 PROJECTS WITH SIGNAL POLES, OVERHEARD SIGN STRUCTURES AND HIGH MOUNT LIGHTING
SP2R20 EXCAVATION OF ROCK BY EXPLOSIVES
SP2R25 ROADWAY EXCAVATION
SP2R30 TEMPORARY DETOURS
SP2R31 TEMPORARY DETOURS (for lump sum grading)
SP2R35 SHALLOW UNDERCUT
SP2R37 BORROW EXCAVATON
SP2R40 FALSE SUMPS
SP2R45 SHOULDER AND FILL SLOPE MATERIAL
(LUMP SUM GRADING jobs with shoulder and/or fill slopes.)
SP2R50 SHOULDER AND FILL SLOPE MATERIAL
(shoulder and/or fill slopes.)
SP2R57 BORROW EXCAVATION (TRUCK MEASURMENT)
SP2R58 BORROW EXCAVATION (IN PLACE OR TRUCK MEASURMENT)
SP2R65 RESTRICTIONS ON CONSTRUCTION OF EMBANKMENTS
SP2R70 COAL FLY ASH IN EMBANKMENTS
SP2R75 EMBANKMENT MONITORING
SP2R80 ROCK EMBANKMENT
SP2R90 DRAINAGE DITCH EXCAVATION (HAND METHOD)
SP3R01 REINFORCED CONCRETE TAPERED INLET
SP3R05 SADDLE BRANCH CONNECTOR
SP3R10 C.S.SLOTTED DRAIN
SP3R15 15" R. C. PIPE TEE DROP INLET
SP3R20 SEEPS
SP3R25 _____INCH (mm) WELDED STEEL PIPE (By Boring and Jacking)
SP3R30 FLOWABLE FILL
SP3R35 PIPE ALTERNATES
SP4R01 REINFORCED BRIDGE APPROACH FILLS, STA._______
SP5R01 COMPACTION OF SUBGRADE
(use with Field Inspection Notes)
SP5R05 PREPARATION OF SUBGRADE AND BASE
SP5R10 AGGREGATE BASE COURSE GRADATION AND PLASTICITY INDEX
(use west of frost line)
SP5R15 AGGREGATE FOR SOIL-CEMENT BASE
SP5R20 LIME AND CEMENT TREATED SOIL
SP6R01 ASPHALT PAVEMENTS SUPERPAVE
SP6R06 ASPHALT PAVER - FIXED STRING LINE
SP6R07 ASPHALT PAVER - MOBILE AND FIXED STRING LINE
SP6R15 ASPHALT BINDER CONTENT OF ASPHALT PLANT MIXES
Asphalt Concrete Base Course, Type B25.0___________ ------------------------------ 4.3%
Asphalt Concrete Intermediate Course, Type I19.0___________ ----------------------- 4.7%
Asphalt Concrete Surface Course, Type S 4.75A ----------------------------------------- 7.0%
Asphalt Concrete Surface Course, Type SF 9.5A ----------------------------------------- 6.5%
Asphalt Concrete Surface Course, Type S9.5___________ ----------------------------- 6.0%
Asphalt Concrete Surface Course, Type S12.5___________ ---------------------------- 5.5%
SP6R20 ASPHALT PLANT MIXTURES
SP6R25 PRICE ADJUSTMENT - ASPHALT BINDER FOR PLANT MIX
$_____________ Date ______________
SP6R40 TYING PROPOSED ASPHALT PAVEMENT TO EXISTING CONCRETE PAVEMENT
SP6R45 FINAL SURFACE TESTING - ASPHALT PAVEMENTS (Rideability)
SP6R50 SEALING EXISTING PAVEMENT CRACKS
SP6R55 SEALING EXISTING PAVEMENT CRACKS AND JOINTS
SP6R60 FILTER FABRIC FOR PERMEABLE ASPHALT DRAINAGE LAYER
SP6R65 MATERIAL TRANSFER VEHICLE (MTV)
(Asphalt Binder PG 76-22)
SP7R01 WATERPROOFING CONCRETE PAVEMENT JOINTS
SP7R05 TYING PROPOSED CONCRETE PAVEMENT TO EXISTING CONCRETE PAVEMENT
SP7R10 TYING PROPOSED CONCRETE PAVEMENT TO PROPOSED ASPHALT PAVEMENT
SP7R15 BEGINNING AND ENDING OF CONCRETE PAVEMENT
SP8R01 GEOCOMPOSITE SHOULDER DRAIN
SP8R02 CONSTRUCTION SURVEYING
SP8R03 DISPOSAL OF WASTE AND DEBRIS
SP8R05 DITCH DRAIN
SP8R07 FUNNEL AND FUNNEL DRAIN
SP8R10 MODIFIED CONCRETE FLUME WITH CONCRETE OUTLET
SP8R15 MODIFIED CONCRETE FLUME WITH FUNNEL OUTLET
SP8R20 SLUICE GATE
SP8R27 ENDWALLS (RSD 838.80 on sheet 1A)
SP8R31 SANDBAG HEADWALL
SP8R35 GRATES AND FRAME (DRIVEWAY DROP INLET)
SP8R40 2'-6" (750 mm) CONCRETE CURB AND GUTTER (SPECIAL)
SP8R45 CONVERTING EXISTING DROP INLET TO SHOULDER DROP INLET
SP8R50 CONVERT EXISTING __________ TO _________
SP8R55 REMOVE AND STOCKPILE EXISTING GUARDRAIL
SP8R57 GUARDRAIL POSTS AND OFFSET BLOCKS
SP8R60 GUARDRAIL ANCHOR UNITS, TYPE M350
SP8R65 GUARDRAIL ANCHOR UNITS, TYPE 350
SP8R70 STEEL BEAM GUARDRAIL (WEATHERING STEEL WITH WOOD POSTS)
SP8R75 IMPACT ATTENUATOR UNITS, TYPE 350
SP8R80 VINYL COATED CHAIN LINK FENCE, 48" FABRIC WITH 1/2" MESH, GUARDRAIL MOUNTED
SP8R85 TEMPORARY WOVEN WIRE FENCE
SP8R86 PROJECTS WITH FENCING
SP8R90 VINYL COATED CHAIN LINK FENCE _______ INCH (mm) FABRIC
SP8R95 ERECTING FENCE ON RETAINING WALL
SP8R100 CHAIN LINK FENCING WITH BARBED WIRE ON EXTENSION ARMS
SP8R105 Preformed Scour Hole with Level Spreader Apron
SP8R110 CONCRETE PAVED DITCH LEVEL SPREADER
SP8R105 PREFORMED SCOUR HOLE WITH LEVEL SPREADER APRON
SP8R120 CONCRETE SIDEWALKS, DRIVEWAYS AND WHEELCHAIR RAMPS
SP8R125 RETROFITTING WHEELCHAIR RAMPS WITH DETECTABLE WARNINGS RAISED TRUNCATED DOMES
SP9R01 STREET SIGNS AND ROUTE MARKERS
SP9R03 SHIPPING SIGNS
SP10R01 HIGH STRENGTH CONCRETE FOR DRIVEWAYS
SP10R05 AGGREGATE PRODUCTION
SP10R10 CONCRETE BRICK AND BLOCK PRODUCTION
SP10R12 COARSE AGGREGATE
SP10R15 FINE AGGREGATE
SP10R16 PORTLAND CEMENT CONCRETE (Alkali-Silica Reaction)
SP10R17 BORROW MATERIAL
SP10R20 METAL POSTS AND RAILS
SP10R25 COATED, PAVED AND LINED CORRUGATED STEEL CULVERT PIPE
SP10R30 TRAFFIC CONTROL
SP10R45 PAINT TESTING AND SAMPLING
SP11R01 TEMPORARY SHORING FOR THE MAINTENANCE OF TRAFFIC
SP11R05 DRUMS
SP11R10 PORTABLE CONCRETE BARRIER
SP11R15 WORK ZONE SIGNS
SP11R20 BARRICADES
SP12R01 PAVEMENT MARKING GENERAL REQUIREMENTS
SP14R01 COORDINATION OF LIGHTING WORK
(Existing lighting AND New roadway lighting)
SP16R01 PERMANENT SEEDING AND MULCHING