Obtain Concurrence Point 1 |
February 2001 |
 |
Hold Citizens Workshop |
October 2001 |
 |
Obtain Concurrence Point 2 |
February 2005 |
 |
Obtain Concurrence Point 2A |
October 2005 |
 |
Complete Draft Environmental Document |
July 2006 |
 |
Hold Public Hearing |
September 2006 |
 |
Obtain Concurrence Point 3 |
November 2006 |
 |
Obtain Concurrence Point 4A |
June 2007 |
 |
Complete Final Environmental Document |
December 2007 |
| |
Begin to Purchase Right of Way |
Spring 2009 |
| |
Begin Construction |
After 2015 |