Transportation Division 11 is comprised of the following counties: Alleghany, Ashe, Avery, Caldwell, Surry, Watauga, Wilkes, Yadkin.
Add Left Turn Lane and Realign SR 1138 (Osborne Rd) [STIP Number: R-5160]
County: Alleghany
Division: 11
R-5160
Route: NC 18
Location: SR 1173 (Tayson Rd) to SR 1138 (Osborne Rd)
Add Left Turn Lane and Realign SR 1138 (Osborne Rd)
Length: N/A
Estimated Cost: $750,000
Letting Date: October 2009
Note: This project is also located in county.
Pavement Rehab [STIP Number: R-5156]
County: Alleghany
Division: 11
R-5156
Route: NC 93
Location: US 221 to Virginia State Line
Pavement Rehab
Length: 5.1 miles
Estimated Cost: $1,325,185
Letting Date: September 2009
Note: This project is also located in county.
Pavement Rehab [STIP Number: R-5157]
County: Alleghany
Division: 11
R-5157
Route: NC 93
Location: US 221 to Virginia State Line
Pavement Rehab
Length: 5.1 miles
Estimated Cost: $1,325,185
Letting Date: September 2009
Note: This project is also located in county.
Pavement Rehab and Guardrail [STIP Number: R-5154]
County: Ashe
Division: 11
R-5154
Route: NC 16
Location: NC 88 to Virginia State Line
Pavement Rehab and Guardrail
Length: 13.1 miles
Estimated Cost: $2,311,563
TRUE
Letting Date: July 2009
Note: This project is also located in county.
Widening and Pavement Rehab [STIP Number: R-5158]
County: Avery
Division: 11
R-5158
Route: NC 194
Location: US 221 to US 19 E
Widening and Pavement Rehab
Length: 4.2 miles
Estimated Cost: $1,030,620
TRUE
Letting Date: July 2009
Note: This project is also located in county.
Pavement Rehab [STIP Number: U-5141]
County: Caldwell
Division: 11
U-5141
Route: US 321
Location: SR 1178 (Hibriten Dr SE) to SCL Lenoir
Pavement Rehab
Length: 6.9 miles
Estimated Cost: $478,748
TRUE
Letting Date: July 2009
Note: This project is also located in county.
Paint Bridge Girders [STIP Number: B-5185, B-5186, B-5187]
County: Surry
Division: 11
B-5185, B-5186, B-5187
Route: Bridges over I-77
Location: Bridges #210, 211, 214, 87,120,147,167,168,187, 198, 204, 208
Paint Bridge Girders
Length: N/A
Estimated Cost: $2,143,942
TRUE
Letting Date: August 2009
Note: This project is also located in county.
Pavement Rehab [STIP Number: I-5130]
County: Surry
Division: 11
I-5130
Route: I-77
Location: MM 88.4 to MM 90
Pavement Rehab
Length: 1.6 miles
Estimated Cost: $300,000
Letting Date: September 2009
Note: This project is also located in county.
Pavement Rehab [STIP Number: R-5155]
County: Surry
Division: 11
R-5155
Route: US 52
Location: Stokes County Line to SR 1815 (Cooke School Rd)
Pavement Rehab
Length: 12.6 miles
Estimated Cost: $3,247,234
TRUE
Letting Date: August 2009
Note: This project is also located in county.
Pavement Rehabilitation [STIP Number: I-5103]
Counties: Surry , Yadkin
Division: 11
I-5103
Route: I-77
Location: US 21 (Exit 79) to MP 84
Pavement Rehabilitation
Length: 5.0 miles
Estimated Cost: $4,032,676
TRUE
Letting Date: May 2009
Note: This project is also located in Yadkin county.
Widen to Multi-lanes, Landscaping, Sidewalks [STIP Number: U-4020]
County: Watauga
Division: 11
U-4020
Route: US 421 (King Street)
Location: NC 194 to US 321
Widen to Multi-lanes, Landscaping, Sidewalks
Length: 1.1 miles
Estimated Cost: $17,536,221
TRUE
Letting Date: June 2009
Note: This project is also located in county.
Pavement Rehab and Guardrail [STIP Number: R-5153]
County: Wilkes
Division: 11
R-5153
Route: NC 16 N
Location: SR 1559 (Old NC 16) to Ashe County line
Pavement Rehab and Guardrail
Length: 5.5 miles
Estimated Cost: $1,602,356
TRUE
Letting Date: July 2009
Note: This project is also located in county.
Widening and Pavement Rehab [STIP Number: R-5159]
County: Wilkes
Division: 11
R-5159
Route: NC 115
Location: US 421 to Iredell County Line
Widening and Pavement Rehab
Length: 9.3 miles
Estimated Cost: $5,000,000
Letting Date: December 2009
Note: This project is also located in county.
Pavement Rehabilitation [STIP Number: I-5103]
Counties: Surry , Yadkin
Division: 11
I-5103
Route: I-77
Location: US 21 (Exit 79) to MP 84
Pavement Rehabilitation
Length: 5.0 miles
Estimated Cost: $4,032,676
TRUE
Letting Date: May 2009
Note: This project is also located in Surry county.
Pavement Rehab [STIP Number: I-5129]
County: Yadkin
Division: 11
I-5129
Route: I-77
Location: Iredell County Line to South of SR 1125 (Asbury Church Rd)
Pavement Rehab
Length: 3.2 miles
Estimated Cost: $1,500,000
Letting Date: October 2009
Note: This project is also located in county.
Back to Recovery Project Map